ML033240610
| ML033240610 | |
| Person / Time | |
|---|---|
| Site: | Brunswick |
| Issue date: | 10/09/2003 |
| From: | Ogle C NRC/RGN-II/DRS/EB |
| To: | Keenan J Carolina Power & Light Co |
| References | |
| -RFPFR IR-03-008 | |
| Download: ML033240610 (45) | |
See also: IR 05000324/2003008
Text
UNITED STATES
NUCLEAR RGULATORY COMMISSION
REGION II
SAMNLiNMATLANTA~~O~WALCEMTER
6.S FORSYTH STREET SW SUITE 23T85
ATLANTA, GEQRGIA 30303-8931
October 9 , 2003
Carolina Power and Light Company
ATTN:
Mr. J~ S. Keenan
Vice President
Brunswick Steam Electric Plant
P. 5. Box 10429
Southport, NC 28461
SUBJECT:
BRUNSWICK S E A M ELECTRIC PLANT - NRC SAFETY SYSTEM DESIGN
AND PERFORMANCE CAPABILITY INSPECTION - REPORT NOS.
05000325/2003008and 05000324/2003008
Dear Mr. Keenan:
This refers to the safety system design and performance capability team inspection conducted
on August 11 -1 5 and August 2549,2003, at the Brunswick facility. The enclosed inspection
report documents the inspection findings, which were discussed on August 29, 2003, with
Mr. C. J. Gannon and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and
compliance with the Commissions rules and regulations and with the conditions of your license.
The team reviewed selected procedures and records, observed activities, and interviewed
personnel.
Based on the results of this inspection, one finding of very low safety significance (Green) was
identified. This issue was determined to involve a violation of NRC requirements. This finding
has very low safety significance and has been entered into your corrective action program.
However, the NflC is withholding the treatment of this issue as a non-cited violation as provided
by Section VI.A.4 of the NRCs Enforcement Policy, pending our review of your corrective
actions related to restoration of compliance. lf you contest this finding, you should provide a
response with the basis for your concern, within 40 days of the date of this inspection report to
the Nuclear flegulatory Commission, ATTN: Document Control Desk, Washington, BC 20555-
1001
~ with copies to the Regional Administrator, Region II; the Director, Office of Enforcement,
United States Nuclear Regulatory Commission, Washington, DC 20555-0001 ; and the NRC
Resident Inspector at the Brunswick faciiity.
In accordance with 10CFR 2.790 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRCs document system
ATTACHMENT 1
2
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
~
Enaineerina Bran
Division of iieactor Safety
Docket NOS.: 50-325,50-324
Enclosure: NRC Inspection Report
w/Attachment: Supplemental Information
cc w/encl:
C. J. Gannen, Director
Site Operations
Brunswick Steam Electric Plant
Carolina Power & Light
Electronic Mail Distribution
W. C. No11
Plant Manager
Brunswick Steam Electric Plant
Carolina Power & Light Company
Electronic Mail Distribution
Terry C. Morton, Manager
Performance Evaluation and
Regulatory Affairs CPB 9
Carolina Power & bight Company
Electronic Mail Distribution
Edward T. O'Neil, Manager
Support Services
Carolina Power & Light Company
Brunswick Steam Electric Plant
Electronic Mail Distribution
Licensing Supervisor
Carolina Power and bight Company
Electronic Mail Distribution
(cc w/encl cent'd - See page 3)
(cc w/encl cont'd)
William D. Johnson
Vice President & Corporate Secretary
Carolina Power and bight Company
Electronic Mail Distribution
3
John H. Q'Neill, Jr.
Shaw, Pittman, Potts & Trowbridge
23067 N. Street, NW
Washington, BC 20037-1 128
Beverly Hall, Acting Director
Division of Radiation Protection
N. C. Department of Environment
and Natural Resources
Electronic Mail Distribution
Peggy Force
Assistant Attorney General
State of North Carolina
Electronic Mail Distribution
Chairman of the North Carolina
c/o Sam Watson, Staff Attorney
Electronic Mail Distribution
Robert P. Gruber
Executive Director
Public Staff NCUC
4326 Mail Serw'ce Center
Raleigh, NC 27699-4326
Public Service Commission
State of South Carolina
P. 0.
Box I1 649
Columbia, SC 2924 1
Donald E. Warren
Brunswick County Board of
Commissioners
P. 0. Box 249
Bolivia. NC 28422
Utilities Commission
(cc w/mcl cont'd - See page 4)
(cc w/encl contd)
Dan E. Summers
mergericy Management Coordinator
New Hanover County Department of
P. 0.
Box 1525
Wilmington, NC 28402
Emergency Management
4
Docket Nos.:
License NO§.:
Report Nos.:
Licensee:
Facility:
Location:
Bates:
Inspectors:
Approved by:
U.S. NUCLAR REGULATORY COMMISSION
REGION 11
50-325,50-324
DPW-71, BPW-62
05000325/2003008 and 05000324/2003008
Carolina Power and Light
Brunswick Steam Electric Plant, Units I and 2
8470 River Road SE
Southport, NC 28461
August 11-15, 2003
August 25-29,2003
J. Moorrnan, Senior Reactor Inspector (Lead Inspector)
N. Merriweather, Senior Reactor Inspector
R. Schin, Senior Reactor Inspector (Week 1 only)
M. Thomas, Senior Reactor Inspector
M. Mayrni, Reactor Inspector (Week 2 only)
N. Staples, Reactor Inspector
Charles R. Ogle, Chief
Engineering Branch 1
Division of Reactor Safety
Enclosure
SUMMARY OF FINDINGS
bR 05000325/2003-008, 05000324/2003-008; 08/11-15/2003 and 08/25-29/2003; Brunswick
Steam Electric Plant, Units 1 and 2; safety system design and performance capability.
This inspection was conducted by a team of inspectors from the Region II office. The team
identified 1 Green unresolved item. The significance of most findings is indicated by their color
(Green, White, Yellow, Red) using IMC 0609, Significance Determination Process (SBP).
Findings for which the SBP does not apply may be Green or be assigned a severity level after
NRC management review. The NRCs program for overseeing the safe operation of commercial
nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 3,
dated Juiy 2000.
A.
NRC-Identified and Self-Revealina Findinas
Cornerstone: Mitigating Systems
m.
The team identified a violation of 10 CFR 50, Appendix B, Criterion Ill, Qesign
Control requirements. The Technical Specification (TS) allowable value for the
Condensate Storage Tank (CST) Level - Low function, for automatic high pressure
coolant injection (HPCI) pump suction transfer to the suppression pool, was not
adequately supported by design calculations. The calcuIations did not adequately
address the potential for air entrainment in the HPCI process flow due to vortexing. This
finding is in the licensees corrective action program as Action Request 102456.
This finding is unresolved pending further NRC review of the requirements for the CST
Level - Low function and of the corrective actions related to restoration of compliance
with 10 CFR 50, Appendix B, Criterion 111, Design Control requirements. The finding is
greater than minor because it affects the design control attribute of the mitigating
systems cornerstone objective. It is of very low safety significance (Green) because the
finding is a design deficiency that will not result in loss of the HPCl function per BL 91-
18 (Rev. I ) and the likelihood of having a low level in the CST that would challenge the
CST level - low automatic HPCI suction transfer function is very low. In addition,
alternate core cooling methods would normally be available, including reactor core
isolation cooling (RCIC) as well as automatic depressurization system and low pressure
coolant injection. (Section 1821.1 1. b)
B.
Licensee-Identified Violations
None
REPORT DETAILS
1.
REACTOR SAFETY
Cornerstones: Initiating Events and Mitigating Systems
1821 Safety Svstem Desian and Performance Casabilitv (71 11 1.21)
This team inspection reviewed selected components and operator actions that would be
used to prevent or mitigate the consequences of a loss of direct current power event.
Components in the high pressure coolant injection (HPCI), reactor core isolation cooling
(RCIC), and 125E5.0 volt (v) direct current (dc) electrical systems were included. This
inspection also covered supporting equipment, equipment which provides power to
these components, and the associated instrumentation and controls. The loss of dc
power event is a risk-significant event as determined by the licensees probabilistic risk
assessment.
.I
.I 1
a.
b.
Svstem Needs
Process Medium
Inspection Scowe
The team reviewed the licensees installed configuration and calculations for water
volume in the condensate storage tank (CST) and for net positive suction head for the
HPCI pump. This included reviews of system drawings and walkdown inspection of
installed equipment to compare arrangements and dimensions to those used in the
calculations. The team also reviewed the licensees calculations supporting the
Technical Specification (TS) setpoint for the CST level instrumentation which initiates an
automatic transfer of the HPCB pump suction from the CST to the suppression pool.
This included checking the adequacy of the calculations and comparing calculated
values to values in the TS and in the instrument calibration procedures.
Findines
introduction: An unresolved item of very low safety significance (Green) was identified
for inadequate design control of the HPCI suction source from the CST. The
calculations which determined the CST low level setpoint for automatic HPCl system
suction transfer from the CST to the suppression pool did not adequately account for air
entrainment in the process flow due to vortexing. This finding involved a violation of
NRC requirements. However, it is unresolved pending further NRC review of the
requirements for the CST bevel - bow function and corrective actions related to
restoration of compliance.
Description: Vortexing in pump suction sources is a well known phenomenon. It is
discussed in typical textbooks on centrifugal pumps. NRC Regulatory Guide I.8z5
Sumps for Emergency Core Cooling and Containment Spray Systems, dated June
1974, discussed the need to preventing vortexing. Regulatory Guide 1.82, Rev. 1,
dated November 1985, and Rev. 2, dated May 1996, included specific guidance on how
to prevent air ingestion due to vortexing in containment heat removal systems. That
2
guidance included limiting the Froude number (Fr) to less than 0.8 for BWW suppression
pool suctions [where Fr is equal to the inlet pipe velocity (U) in feet per second divided
by the square root of (the suction pipe centerline submergence below the water level (S)
in feet times gravity (9) in feet per second squared}]. NRC NUREG / CR-2772,
Hydraulic Performance of Pump Suction Inlet for Emergency Core Cooling Systems in
Boiling Water Reactors? dated June 1982, included experiments on suctions from tanks
and showed almost no air entrainment with a Fr of 0.8. The experiments also showed
that air entrainment increased dramatically when Fr reached 1.0. The BWR Owners
Group Emergency Procedure Guidelines included guidance on preventing vortexing in
emergency core cooling system pump suctions from the suppression pool. This
guidance included a vortex limit curve based on maintaining Fr less than 0.8.
All of the above references addressed suction pipes that extended into a LanWsump. A
more recent research paper published in 2001 by ASME titled Air Entrainment in a
Partially Filled Horizontal Pump Suction Line described tests on air entrainment. The
tests were conducted at various flowrates, in a horizontal suction pipe that did not
extend into the a tank; a configuration similar to the HPCl suction from the CST at
Brunswick. The papers conclusions about vortexing and air entrainment at high flow
rates were similar to those of the previous references where a suction pipe extended
into a tank.
Brunswick Units 1 and 2 TS Table 3.3.5.1-1 stated that the allowable value for the HPCl
system automatic suction transfer from the CST to the suppression pool was a low CST
level of 2 23 feet 4 inches above mean sea level. (NQTE: That value represented 3 feet
4 inches above the bottom of the CST.) Once initiated, the HPCI suction transfer
involved first opening the suppression pool suction valves (E41-FO41 and F042) and then
closing the CST suction valve (E41-FOO4). The Updated Final Safety Analysis Report
(UFSAR) stated that for each units CST:
...the HPCl and RCIC pumps take suction through a 16-inch line
connected to the tank with a nozzle centerline 2 feet above the tank
bottom. Level instruments will initiate an automatic transfer of the pumps
suction path to the suppression pool suction if level approaches this
connection. For HPCl the setpoint is above the 3.3-foot TS limit and
below the 3.5-foot calibration maximum allowed value. To allow time for
the suction transfer to take place, this setpoint provides a margin of
approximately 10,000 gallons in the tank after the setpoint is reached and
before air will be entrained in the process flow.
The calculation of record that supported the TS allowable value was Calculation OE41-
1001, High Pressure Coolant Injection System Condensate Storage Tank Level Low
Uncertainty and Scaling Calculation [E41 -LSL-N002(3) Loops], Rev. 1, dated March
29, 1999. The team noted that Calculation OE41-1001 stated that its objective was to
determine the allowable value and setpoint for the CST low water level trip function for
the HPCl system. However, the calculation did not include a hydraulic analysis to
determine the allowable value. Instead, it relied on a design basis input from
Engineering Service Request (ESR) 97-00026, Action Item 2, for the allowable value.
3
ESR 97-00026, Action Item 2, stated its objective: ... the analytical limit for the HPCI
and RClC CST low level transfer function is 23 feet 4 inches. Provide a basis for this
analytical limit. The basis should address air voids ... It also stated: This ESR action
item will show that using the TS limit as the analytical limit is acceptable. The ESW
included Condition Report (CR) 97-02379 Task 2 (approved August, 27,1997) as an
attachment. The team noted that the ESW relied entirely on CR 97-02379 Task 2 for
concluding that using the TS limit as the analytical limit was acceptable. However, the
ESR also stated: This CR review was not conducted as a design basis input with
formal testing and design verification.
CR 97-02379 Task 2 stated that its objective was to determine if a vortexing problem
existed in the CST when running the HPCO pump. Task 2 further stated that it was
responding to an operating experience event where a nuclear plant had identified that
they had failed to account for unusable volume In their CST due to vortexing concerns.
It described a scale model test that had been performed by another nuclear plant to
conclude that no vortexing would occur in their CST. However, the CR noted reasons
why this test could not be relied upon as a design input. The CR also contained results
from an informal test performed by the licensee. The CR concluded that, based on the
results of the informal testing and engineering judgement, air ingestion may briefly occur
during the transfer process; however, the air ingestion would be of such limited duration
and such a small percentage that there was no concern for damage to the HPCI pumps.
The team noted that the informal test used a small scale model without determination
that the results would be applicable to the installed CST and HPCl suction, the test was
performed without calibrated instruments, and the test was not independently verified.
The team considered that the informal test was not suitable for use as an input to a
design basis calculation.
Subsequently, action request (AR) 00005402 documented an engineering audit concern
with relying on ESR 97-80026 as a design basis input to a calculation. ESW 01-00322
was then written to respond to AR 00005402. ESR 01-08322 stated that its purpose
was to document the technical resolution of the CST intake vortex formation issue and
to insert appropriate references into design documents. ESR 01 -00322 included an
extensive review of reference documents on vortexing. It included references to LERs
and INPO Event Reports on vortexing issues at other nuclear plants; NUREWCR-2772;
and several research papers on vortexing. The team noted that ESR 01-00322 did not
reference NRC Regulatory Guide 1.82.
ESR 81-00322 agreed with the conclusions of CR 97-02379 and ESR 97-00026 that the
TS allowable value of 23 feet 4 inches was adequate. It concluded that the potential for
a significant air ingestion event was of sufficiently low probability to be considered non-
credible. The team noted that this conclusion was based primarily on the CR 97-02379
informal test and on a research paper by A. Daemi of the Water Research Center in
Tehran, Iran, that had been presented to the American Society of Civil Engineers in
1998. The research paper tested the effect of an intake pipe protruding various
distances into a reservoir and found that a pipe that did not protrude into the reservoir
showed some vortexing but no air entrainment while a pipe that did protrude into the
reservoir would have significant vortexing and air entrainment into the pipe. ESR 01-
00322 considered that, since the NUREG/CR-2272 tests used a configuration where the
4
suction pipe protruded into the tank and the licensees HPCl suction pipe did not
protrude into the CST, the NUREG/CR-2272 conclusions were not applicable to the
Brunswick design. The NRC team noted that the research paper by A. Baemi was
significantly flawed for applicability to Brunswick in that it did not state what flowrates
were used in its tests and apparently used gravity flow. Regulatory Guide 1.82 and
NUREG/CR-2272 indicate that flow velocity is one of the most important factors in
vortex formation. A suction pipe that would have little or no vortexing at low flow
velocities (e.g., gravity flow) could have significant vortexing at higher flow velocities
(e.g., a HPCI pump at 4300 gprn). The team considered that both sources of
information on which the conclusions of E§R 01-00322 were based were not suitable for
use as inputs to safety-related design calculation OE41-1001.
The HPCl pump was designed to automatically start and establish a flowrate of
4300 gpm. Licensee procedures did not contain guidance to reduce that flowrate when
the CST level approached the low level switchover setpoint. Using the NUREG/CR-
2272 methodology, the team calculated that, at a HPCI pump flowrate of 4300 gpm, an
Fr of 0.8 would be reached at a CST level of 5.0 feet and an Fr of 1 .O would be reached
at a CST level of 3.9 feet. Considering the automatic suction transfer actuation setpoint
and the valve stroke times, the HPCB pump suction pipe could be exposed to a suction
Fr in excess of 0.8 (some air entrainment) for about 8.9 minutes and over 1 .O (over 2%
air entrainment) for about 5.0 minutes. Calculations that used the 2001 ASME research
paper equations provided different results: air entrainment in the process flow would
start at a tank level of 3.2 feet and would exceed 2% at tank levels below 3.0 feet. This
would represent a HPCI pump suction pipe exposure to some air entrainment in the
process flow for about 1.8 minutes and to over 2% air entrainment for about
1.1 minutes. The team concluded that the plant design was not consistent with the
UFSAR in that the TS allowable value for the HPCl automatic suction transfer would not
prevent air from becoming entrained in the HPCl process flow.
During this inspection, team and licensee measurements of the installed CST
configuration revealed non-conservative errors of about 1.5 inches in the actual heights
of the Units 1 and 2 CST level switches above the HPCl suction pipes. These would
result in additional non-conservative errors in the HPCI automatic suction transfer
setpoints.
The licensee entered this issue into their corrective action program as AR 102456102456 This
AR included an operability determination and planned corrective actions that were
reviewed by the team. The operability determination concluded that the CST Level -
Low instrument was operable with the existing TS allowable value and related setpoint
and no compensatory measures were needed. This conclusion was based on the
following: 1) HPCl operation during design or licensing basis events would not
challenge the CST Level bow instrument; and 2) Operator actions consistent with
plant procedures would not result in 4300 gpm HPCl flow for the full duration of the
suction transfer. The operability determination did not include an analysis which
assured that the instruments allowable value was adequate to prevent significant air
entrainment during the full duration of a CST bevel - Low setpoint initiated suction
transfer while the HPCl pump was operating at its maximum flowrats of 4300 gpm.
However, the teams interpretation of licensing basis documents indicated that the CST
5
Level - Low function was required to be able to protect the HPCl pump from damage
from any suction hazard that could occur. This inciuded air entrainment in the process
flow due to vortexing that would result if the CST level became low while the HPCI pump
was operating at about 4300 gpm, even if this could only occur outside of a design basis
event.
The licensees corrective actions for this issue were in AR 102456102456 This AB included
only two planned corrective actions. The first corrective action was: Issue a UFSAR
change package to correct the description of HPCB air entrainment potential during
suction swap. Phis was described in more detail in the AB under Section 3,
Inappropriate Acts, item 4: Error 4 was a simple text error by BNP engineering where
the concept was understood (no significant air at the pump) but was not translated into
specific detailed words. The second corrective action was: Issue an evaluation to
update the HPCI CST level switch design basis information to reflect the evaluation
provided in the operability review portion of this AW. The operability determination
portion of the AR concluded that the CST Level - Low automatic HPCl suction transfer
function would not be challenged during design basis events and consequently the TS
allowable value was adequate.
The documented corrective actions in AR 102456102456did not appear to be sufficiently
comprehensive to restore compliance with 10 CFR 50, Appendix B, Criterion 111, Design
Control. The licensees planned corrective actions did not Specifically include revising
the design calculation, OE41-1001. In addition, they did not include assuring that the
CST Level Low suction transfer function will protect the flPCl pump if it is operating at
its maximum flowrate during the transfer. The planned corrective actions identified in
the AR did not include obtaining a certification from the pump vendor that the pump can
withstand a certain amount of air in the process flow for a certain amount of time without
pump damage. [This was subsequently done by the licensee.] The planned corrective
actions identified in the AR also did not include submitting a license amendment request
to the NKC to revise the TS allowable value, remove the CST Level - Low function from
TS, or add an operator action to throttle HPCl pump flow at low CST levels so that the
existing setpoint will be able to protect the pump. This issue will remain unresolved
pending further NRC review of the design basis and operability requirements for the
CST Level - Low suction transfer function. Specifically, the NRC will review whether the
CST Level - Low function is required to be able to protect the HPCI pump from damage
only during design basis events; or if it is required to be able to protect the HPCI pump
from damage due to air entrainment if the level is the CSB becomes low with the HPCI
pump operating at a flowrate of about 4300 gpm, even if this could only occur outside of
a design basis event.
Analvsis: Design Calculation OE41-1001, for the CST Level - Low setpoint and TS
aliowable value was inadequate. The finding is greater than minor because it affects the
design control attribute of the mitigating systems cornerstone objective. It is of very low
safety significance (Green) because the finding is a design deficiency that will not result
in loss of the HPCl function per GL 91-18 (Rev. 1) and the likelihood of having a low
level in the CST that would challenge the CST bevel - Low automatic HPCI suction
transfer function is very low. In addition, alternate core cooling methods would normally
6
be available, including RCIC as well as automatic depressurization system and low
pressure cooiant injection.
Enforcement: 10 CFR 50, Appendix B, Criterion Ill( Design Control, requires in part, that
design control measures shall include provisions to assure that appropriate quality
standards are specified and included in design documents. Contrary to the above
requirements, the NRC identified during this inspection that, from 1999 to August 2003,
licensee Calculation OE41-1001 and associated design documents did not adequately
consider air entrainment in the HPCl pump process flow due to vortexing in the CST for
the current TS value for the CST Level bow setpoint for automatic transfer of the HPCl
pump suction from the CST to the suppression pool. This finding was entered into the
licensees corrective action program as Action Request 102456 and is unresolved
pending further NRC review of the requirements for the CST Level - Low function and of
the licensees corrective actions related to restoration of compliance with Criterion Ill of
18 CFW 50, Appendix E. This finding is identified as UBI 05000325, 324/2003008-01,
Failure to Adequately Consider Vortexing in the Calculation for CST Level for Automatic
Transfer of the HPCI Pump Suction.
.I2
Enerav Sources
a.
lnsoection Scow
The team reviewed appropriate test and design documents to verify that the
12.9250 vdc power source fur HPCl system valves and controls would be available and
adequate in accordance with design basis documents. Specifically, the team reviewed
the 125250 vdc battery lead study, 125 vdc battery charger sizing calculation, and
125/250 vdc system voltage drop study, and battery surveillance test results, to verify
that the dc batteries and chargers had adequate capacity for the loading conditions
which would be encountered during various operating scenarios. The team reviewed a
sample of HPCl motor operated valves (MOVs) to verify the adequacy of available motor
output torque, stroke times, thermal overload heater sizing, and valve performance at
reduced voltages. The team also reviewed portions of a voltage study to verify adequacy
of voltage for HPCl solenoid valves l-E41-F025 and -F026 under worst case voltage
conditions. A list of related documents reviewed are included in the attachment.
The team reviewed design basis descriptions and drawings and walked down the HPCl
and RClC systems to verify that a steam supply would be available for pump operation
during a loss of station dc power event. This included review of the steam supply drain
systems and review of a recent modification to the HPCI steam supply drain system.
The team reviewed the HPCl steam supply drain pot flow orifice inspections; the drain
pot level switch logic and calibration records, and the drain pot drain line isolation valves
modification to verify that the HPCl steam supply would be available if needed. The
team reviewed functional valve testing fur the HBCl and RClC turbine exhaust vacuum
breaker check valves to verify adequacy of acceptance criteria and to verify that vacuum
breaker functionality was being maintained.
7
b.
Findinas
No findings of significance were identified.
.I 3
Instrumentation and Controls
a.
Inspection Scope
The team reviewed electrical elementary and logic diagrams depicting the WPCI pump
start and stop logic, permissives, and interlocks to ensure that they were consistent with
the system operational requirements described in the UFSAR. The team reviewed the
HPCI auto-actuation and isolation functional surveillance procedures and completed test
rscords to verify that the control system would be functional and provide desired control
during accident and event conditions in accordance with design. The team reviewed the
calibration test records for the CST low water level instrument channels to verify that the
instruments were calibrated in accordance with setpoint documents. The team also
reviewed the records demonstrating the calibration and functional testing of the HPCI
suppression pool high level instrument channels to determine the operability of the high
level interlock functions of HPCI.
b.
Findinas
No findings of significance were identified.
.I4
Operator Actions
a.
Inspection Scone
The team assessed the plant and the operators response to a Unit 1 initiating event
involving a loss of station battery 18-2. The team focused on the installed equipment
and operator actions that could initiate the event or would be used to mitigate the event.
The team reviewed portions of emergency operating procedures (EOPs), abnormal
operating procedures (AOPs), annunciator panel procedures (APPs), and operating
procedures (OPs) to verify that the operators could perform the necessary actions to
respond to a loss of dc power event. The team also observed simulation of a loss of dc
power event on the plant simulator and walked down portions of Procedure OAOP-39,
Loss of DC Power. The simulator observations and procedure reviews focused on
plant response and on verifying that operators had adequate instrumentation and
procedures to respond to the event. The team reviewed operator training records
(lesson plans, completed job performance measures, etc.) to verify that operators had
received training related to a loss of dc power event.
b.
Findinas
No findings of significance were identified.
8
.I5
Heat Removal
a.
Inspection Scope
The team reviewed historical temperature data for the Unit 2 battery rooms to verify that
the minimum and maximum room temperatures were within the allowable temperature
limits specified for the batteries.
The team reviewed heat load and heat removal calculations for the HPCl and RClC
rooms. The team also reviewed the calculated peak temperature and pressure
responses during high energy line break and loss of coolant accidents for these rooms.
The team reviewed service water temperature and flow requirement calculations for the
HPCl and RClC rooms and fan coolers. These reviews were conducted to verify the
adequacy of design for the room coolers, and to verify that heat will be adequately
removed during a loss of dc power event.
The team also reviewed HPCI and RClC room cooler thermostat calibrations, inspection
and cleaning records, and corrective maintenance history to verify room coolers were
properly maintained and would be available if called upon.
b.
Findinas
No findings of significance were identified.
2
System Condition and CaDability
2 1
Installed Confiauration
a.
Inspection Scope
The team visually inspected the 125/250 vdc batteries and battery chargers, dc
distribution panels, dc switchgear, and dc ground detection systems in both units to
verify that the dc system was in good material condition with no alarms or abnormal
conditions present and to verify that alignments were consistent with the actions needed
to mitigate a loss of dc power event. The batteries were inspected for signs of
degradation such as corrosion, cell discoloration, plate buckling, grid cracks, and
excessive plate growth.
The team waiked down the HPCI and RCIC systems and the CST to verify that the
installed configuration was consistent with design basis information and would support
system function during a loss of dc power event.
The team walked down portions of the HPCI system to verify that it was aligned so that
it would be available for operators to mitigate a loss of dc power event. During this
walkdown, the team compared valve positions with those specified in the HPCI system
operating procedure lineup, and observed the material condition of the plant to verify
that it would be adequate to support operator actions to mitigate a loss of dc power
9
event. This also included reviewing completed surveillance tests which verified selected
breaker positions and alignments.
b.
Findines
No findings of significance were identified.
2 2
Desian Calculations
a.
Inspection ScoDe
The team reviewed the thermal overload sizing calculations for a sample of Unit 1 HPCI
MOVs to verify adequacy of the installed overload relay heaters. The team also
reviewed calculations that assessed the stroke times and motor torque produced at
reduced voltage to verify that they would exceed or meet minimum specified
requirements. The valves and calculations reviewed are listed in the attachment.
The team reviewed design basis documents, probabilistic risk assessment system
notebooks, UFSAR, selected piping and instrumentation diagrams, selected TSs,
system reviews, ARs, and the corrective maintenance history for HPCl and RClC
systems to assess the implementation and maintenance of the HPCI and RCIC design
basis.
b.
Findinas
No findings of significance were identified.
.23
Testing and InsDection
a.
The team reviewed the 125/250 vdc battery surveillance test records, including
performance and service test results, to verify that the batteries were capable of
meeting design basis load requirements.
The team reviewed functional and valve operability testing (stroke times), and corrective
maintenance records for HPCl and RClC selected valves, including the minimum flow
bypass valves, and steam admission valve. This review was conducted to verify the
availability of the selected valves, adequacy of surveillance testing acceptance criteria,
and monitoring of selected valves for degradation.
The team reviewed HPCI and RCIC system operability tests to verify the adequacy of
acceptance criteria, pump performance under accident conditions, and monitoring of
system components for degradation.
b.
Findinas
No findings of significance were identified.
10
.3
3 1
a.
b.
3 2
a.
b.
.33
a.
Selected Components
Component Dearadation
InsDection Scope
The team reviewed in-service trending data for selected components, including the
HPC! and RClC pumps, to verify that the components were continuing to perform within
the limits specified by the test.
The team reviewed the maintenance history of the 125/250 vdc batteries, 125 vdc
battery chargers, and selected 41 60 v alternating current (ac) and 480 vac breakers to
assess the licensees actions to verify and maintain the safety function, reliability, and
availability of the components in the system. The team also reviewed the preventive
maintenance performed on selected 41 60 vac and 480 vac breakers to verify that
preventive maintenance was being performed in accordance with maintenance
procedures and vendor recommendations. The specific work orders and other related
documents reviewed are listed in the attachment.
Findinas
No findings of significance were identified.
Eauipment/Environmental Qualification
Inspection Scope
The team conducted in-plant walkdowns to verify that the observable portion of selected
mechanical components and electrical connections to those components were suitable
for the environment expected under all conditions, including high energy line breaks.
Findinos
No findings of significance were identified.
Eauipment Protection
inspection Scope
The team conducted in-plant walkdowns to verify that there was no observable damage
to installations designed to protect selected components from potential effects of high
winds, flooding, and high or low outdoor temperatures.
The team walked down the HPCI and RClC systems and the CST to verify that they
were adequately protected against external events and a high energy line break.
11
Findinas
No findings of significance were identified.
Oueratinq Experience
lnsuection Scope
The team reviewed the licensees dispositions of operating experience reports
applicable to the loss of de power event to verify that applicable insights from those
reports had been applied to the appropriate components.
Findinos
No findings of significance were identified.
Identification and Resolution of Problems
lnsuection Scose
The team reviewed corrective maintenance work orders on batteries, battery chargers,
and ac breakers to evaluate failure trends. The team also reviewed Action Requests
involving battery problems, battery charger problems, and charger output breaker
problems to verify that appropriate corrective action had been taken to resolve the
problem. The specific Action Requests reviewed are listed in the attachment. The team
reviewed selected system health reports, maintenance records, surveillance test
records, calibration test records, and action requests to verify that design problems were
identified and entered into the corrective action program.
Findinus
No findings of significance were identified.
Other Activities
b.
.34
a.
b.
.4
a.
b.
4.
40A6 Meetinos. lncludina Exit
The lead inspector presented the inspection results to Mr. C. J. Gannon, and other
members of the licensee staff, at an exit meeting on August 29, 2003. The inspectors
confirmed that proprietary information was not provided or examined during this
inspection.
SUPPLEMENTAL INFORMATION
KEY PQINTS OF CONTACT
Licensee
b. Beller, Supervisor, Licensing
E. Browne, Engineer, Probabilistic Safety Assessment
8. Cowan, Engineer
6.
Elberfeld, Lead Engineer
P. Flados, HPCB System Engineer
N. Gannon, Director, Site Operations
M. Grantham, Design
C. Hester, Operations Support
D. Hinds, Manager, Engineering
G. Johnson, NAS Supervisor
W. Leonard, Engineer
T. Mascareno, Operations Support
J. Parchman, Shift Technical Advisor, Operatiofls
C. Schacker, Engineer
6.
Stackhouse, Systems
H. Wall, Manager, Maintenance
K. Ward, Technical Services
_D
NRC (attended exit meeting)
E. DiPaoio, Senior flesident Jnspector
J. Austin, Resident Inspector
LIST OF ITEMS OPENED, CLOSED AND DISCUSSED
Opened
0500032~,324/2003008-~~ UBI
Failure to Adequately Consider Vortexing in the
Calculation for CST Level for Automatic Transfer of
the HPCI Pump Suction (Section 7 R21.17. b)
Attachment
2
LISP OF DOCUMENTS REVIEWED
Procedures
OAI-115, 125/250 VPC System Ground Correction Guidelines, Rev. 6
OAOP-36.1, boss of Any 41 60V Buses or 48OV E-Buses, Rev. 25
OAOP-39.0, Loss of DC Power, Rev. 16
001-01.02, Shift Routines and Operating Practices, Rev. 31
001-50, 125i250 VDC Electrical Load List, Rev. 25
OOP-50.1, Diesel Generator Emergency Power System Operating Procedure, Rev. 55
OPM-ACU500, Inspection and Cleaning of the RHWCore Spray Room Aerofin Cooler Air Filters
1APP-,445, Annunciator Procedure for Panel A-05, Rev. 46
IAPP-UA-23, Annunciator Procedure for Panel UA-23, Rev. 45
1 EOP-01 -RSP, Reactor Scram Procedure, Rev. 8
f OP-19, High Pressure Coolant Injection System Operating Procedure, Rev. 58
16P-50, Plant Electrical System Operating Procedure, Rev. 64
1OP-51, DC Electrical System Operating Procedure, Rev. $0
2APP-A-01, Annunciator Procedure for Panel A-81, Rev. 44
OPIC-TMRQ02, Calibration of Agastat 7020 Series Time Delay Off Relays, Rev. 18
OPM-BKR001 , ITE 4KV-line Breaker and compartment checkout, Rev 27
OPM-BKR002A, IT K-line Circuit Breakers, Rev 31
OPM-TRB518, HPCI & WClC Steam Inlet Brain Pot Flow Orifices Inspection, Rev. 3
Drawinqs
1-FP-60085, High Pressure Coolant Injection System Unit 1, Rev. J
Contract No. 71-2162, Dwg. No. 1, General Plan for Condensate Storage Tanks by Brown &
D-02523, High Pressure Coolant Injection System Unit 2, Sh. 1 & 2, Rev. 52 & 45
8-02529, Reactor Core Isolation Cooling System Unit 2, Sh. 1 & 2, Rev. 52 & 36
8-25023, Sheet 2, Unit 1 High Pressure Coolant Injection System Piping Diagram, Rev. 45
D-25023, Sheet 1 I Unit 1 High Pressure Coolant Injection System Piping Diagram, Rev. 54
F-03044, Units 1 & 2 480 Volt System Key Qne Line Diagram, Rev. 38
LL-7044, Instrument Installation Details Units 1 & 2, Sh. 15, Rev. 10
Calculations
OE41-1001; High Pressure Coolant Injection System - Condensate Storage Tank Level - Low
9527-8-E41-06-F; NPSH Requirements - HPCI and RCIC; dated March 26, 1987
BNP-E-6.033, AC/DC MOV Thermal Overload Sizing Calculations, Rev. 3
BNP-E-6.062, 125i250 Volt DC System Voltage Drop Study, Rev. 3
BNP-E-6.074, 125i.250 Volt DC Battery Load Study, Rev. 2
BNP-E-6.079, 125 Volt DC Battery Charger Sizing Calculation, Revision
BNP-E-6.109, Unit 1 Stroke and Motor Torque Calculations for 250VDC Safety-Related MOVs,
BNP-E-8.013, Motor Torque Analysis for AC MQVs, Rev. 4
and Coolers, Rev. 7
Root, lnc; Rev. C
Uncertainty and Scaling Calculation (E41 -bSL-N002(3) Loops), Rev. I , dated March 29, 1999
Rev. 5
3
BMP-EQ-4.001, Temperature Response in RHR and HPCl Rooms Following LBCA with
BNP-MECH-E4I -F002, Mechanical Analysis Report to Verify Minimum Torque Availability,
BNP-MECH-RBER-001, Reactor Building Environmental Report, Rev. OA
W A C Flow Rates, Rev. 0
M-89-0021; HPCllRCIC NPSH with Suction from the CST; Rev. 0, dated November 27, 1989
PCN-G0050A, RHR Room Cooler Allowable Service Water Inlet Temperature, Rev. 2
Desian Basis Bocuments
DBD-19, High Pressure Coolant Injection System, Rev. f 1
DBD-51, DC Electrical System, Rev. 5
Enaineerina Service Requests
ESR 97-0026; Provide a Basis for the Analytical Limit for the HPCl and RCIC CST bow bevel
ESR 98-00067; HPCI/RCIC Reserve Capacity in CST; Rev. 1, dated February 17, 1998
SI? 99-00404; #PCI/WCIC Drain Pot Piping Boundary Changes; dated February 25,2000
ESR 01-00322; Document the Technical Resolution of the CST Intake Vortex Formation Issue;
ESR 99-00405, HPCl Design Conversion To Fail Open for E-41-F028/29, Rev. 0
Updated Final Safetv Analvsis Reuort
UFSAR Section 54.6,
Reactor Core Isolation Cooling System
UFSAR Section 6.3, Identification of Safety Related Systems - Emergency Core Cooling
UFSAR Section 7.1.1.2, Emergency Core Cooling Systems
UFSAR Section 8.3.2, BC Power Systems
UFSAR Section 9.2.6, Condensate Storage Facilities
Improved Technical Soecifications
Section 3.5.1, ECCS - Operating
Section 3.5.3, RCIC System
Section 3.8.4, DC Sources - Operating
Section 3.8.6,
Battery Cell Parameters
Section 3.8.7, Electrical Distribution Systems s Operating
TS Bases Section 3.5; Emergency Core Cooling Systems and Reactor Core Isolation Cooling
Reduced
Rev. 3
Transfer Function; dated November 24, 1997
dated September 25,2001
Systems
System
List of Valves lnsoected
1-E41-F0011 HPCl Steam Supply Valve
l-E41-F006, HPCI Main Pump Discharge Valve
1-E41-F007, HPCl Main Pump Discharge Valve
?-E41+008, HPCI Test Bypass to CST Valve
4
1-41-F011, WPCl Redundant Shutoff to CST Valve
1-E41-F012, HPCl Test Line Miniflow Valve
1-E41-F04lI HPCI Suppression Pool Suction Valve
1-E41-F042, HPCE Pump Suction Valve
Completed Maintenance and Tests
OPT-09.2, HPCI System Operability Test, completed 06/29/03, 04/03/03, 01/10/03, 08/20/03,
OPT-20.10, Testing of Valves E4l-FO96, E44 -FO99, 51 -F063, E51 -F064, completed 04/24/02,
OPT-10.1 1, RClC System Operability Test, completed 06/06/03, 03/14/03, 12/20/82, 07/31/03,
OPT-09.3, HPCl System ~ I65 Psig Flow Test, completed 04/20/03, 03/26/01, 03/29/02,
OPT-09.7, HPCl System Valve Operability Test, completed 09/25/03, 05/02/03, 02/07/03,
05/01/03, 04/01/03
OPT-10.1 .El, RClC System Valve Operability Test, completed 09/04/03, 0411 0103, 07/03/03,
04/09/030PT-10.1.3, RClC System Operability Test - Flow Rates at 150 Psig, completed
0311 8/QO, 03/29/02, 03/23/01, 04/02/03
05/29/03,04/04/03
03/08/02, 0311 0/03,04/22/02
05/08/03, 04/03/03
03/23/00
Completed Work Orders (WOs) and Work Requests (WRs)
WO 49443-01, HPCl Turbine Restricting Orifices Inspection, completed 0311 3/01
WO 49442-01, RClC Turbine Restricting Orifices Inspection, completed 03/15/01
WQ 45998-01, HPCl Turbine Supply Steam Drain Pot Hi Level Switch Calibration (Unit 2),
WQ 192543-01, HPCl Steam Supply Valve 2-E41-F001 Repairs due to Leakage Past the Seat,
WO 4581941. HPCl Turbine Sugnlv Steam Drain Pot Hi bevel Switch Calibration (Unit I),
completed 02/06/01
completed 03/31/03
..
~
completed 1 i/25/Oi
WO 46107-01, Calibration of RHR Room Cooler Thermostats, completed 11/09/80
WO 53172-01; Inspection & Cleaning of iqe RHR Roorrl Cooler, cotnpleted 03/05/02
WO 50171-01, Inspectioil R Cleartiny of the HI-iR Room Cooler, completed 03/05/02
WR AFQO 001, HPCI Turbine Supply Stem Drain Pct Hi Level Switch Calibration (Uqit 2),
WR AlTl 001, HPCI Turui!ie Supply Steam Drain Po! Hi Level Switch Caliwation (Unit 1).
WR ABPD 063, Calibration of PCIR Room Cooler Thetmostars, completed 09/13/00
WR ABPD 002. Caiibratiori of HHH Room Cooler Thermosta!s, completed 08/25/97
WR AGEB 002, Calibratiop of HHH Room Cooler Thsrmosats, comple;ed 08/21/97
WR AlWK 004, Inspectian & Cleaning of the HI-IH Rocm Cooler, completed C3/09/02
WWJO ANRROOl, 1A-1 Ba:teries, 125 VDC, Perfcrmacice Capaci!y Test
WW:O
ANTKGOI, 1A-2 Bat:er:es, 'I25 VUC, Performarice Capacity Test
WWLO ANSN001, 1 B-1 Batteries, 125 VDC, Performarm? Capacity Test
WR/;O
ANSTOOl, 10-2 Batteries, 125 VDC, Performance Capacity Test
WO 0004C;46SOI, 28-1 Batteries, 125 VDC, Performance Capacity Test
WO 0004546C3:, 28-2 Batteiies, 125 VDC, Pertormance Capacity Test
completed 06/07/96
cmpieted 08/03/95
5
WO 0004546301,2A-I Batteries, 125 VDC, Performance Capacity Test
WO 0004546601,2A-2 Batteries, 125 VBC, Performance Capacity Test
WO 0004635001, 18-2 Batteries, 125 VDC, Service Capacity Test
WO 0004635101, 1A-1 Batteries, 125 VDC, Service Capacity Test
WO 0004634901, 1 B-1 Batteries, 125 VDC, Service Capacity Test
WO 0004634801, 1 B-2 Batteries, 125 VDC, Service Capacity Test
WO 0017812801, 2B-2 Batteries, 125 VDC, 28-2 Service Capacity Test
WO 0017569601, 28-1 Batteries, 125 VDC, 2B-1 Service Capacity Test
WB 8019450581,2A-l Batteries, 625 VDC, 2A-1 Service Capacity Test
WO 0017414101,2A-2 Batteries, 625 VDC, 28-2 Service Capacity Test
WO 0040923401,OMST-BAW11 W, 525 VDC, Weekly Test
WO 5040495901, OMST-BATTI 1 W,
125 VDC, Weekly Test
WO 0040496001,OMST-BAW11 W, I25 VDC, Weekly Test
WO 0040734401, OMST-BATTI 1 W,
125 VDC, Weekly Test
WO 003991 4901, 15-1 & 18-2 OMST-BATTI 1 Q Quarterly
MI0 0031256501, 18-1 & 1 B-2 OMST-BATTI 1 Q Quarterly
WB 80309501 01,15-1
& 1 B-2 QMST-BATTI 1 Q Quarterly
MI0 0028265501, SB-1 & 1 B-2 OMST-BATTl I Q Quarterly
WO 0038119301, ?A-1 & 1A-2 OMST-BATTIIQ Quarterly
WO 0031639601, SA-1 & 18-2 OMST-BATTI I Q Quarterly
WO 0031256401,lA-1 & 1A-2 OMST-BATTIlQ Quarterly
WO 0028260601, 1A-1 & 18-2 OMST-BATTI 3Q Quarterly
W B 0030391 401.2A-1 & 2A-2 OMST-BATTI 1 Q Quarterly
WO 0530391 501,2B-1 & 28-2 OMST-BATTI 1 Q Quarterly
WO 0031256201,2A-l & 2A-2 OMST-BATTI 1Q Quarterly
WO 0531256301,2A-I & 28-2 OMST-BATTI 16 Quarterly
WO 0031256601,2!3-1 & 28-2 OMST-BATTI t Q Quarterly
WO 0031256701,2B-I & 28-2 OMST-BAW1 1 Q Quarterly
WO 0004680801, HPCl Auto-Actuation and Isolation Logic System Functional Test
WO 0067956801, HPCl Auto-Actuation and Isolation Logic System Functional Test
WB 003971 1701, 1 MST-HPCi27Q and RCIC CST Low Water bevel Instrument Catibration
WB 0031316101, 1 MST-HPC1270 and RClC CST Low Water Level Instrument Calibration
WO 0539317801,2MST-HPC127Q and RClC CST Low Water Level Instrument Calibration
WO 0031323101,2MST-HPC127Q and RClC CST Low Water bevel Instrument Calibration
WO 0038679201, HPCI Suppression Pool High Level Instrument Channel Calibration
WO 0031264601, HPCl Suppression Pool High Level Instrument Channel Calibration
I HPCl Suppression Pool High Level Instrument Channel Calibration
WO 0004589001, Calibrate 14541 -FSHL-NO06 in accordance with OPIC-DP-SO01
WO 0007165106, Replace HPCl pump discharge line flow switch
WO 00431 63606, Perform single cell charging on 1-1 A-2 Cell #43 IAW BSPP-BAT010
WO 0043161306, Perform single cell charging on 1-18-1 Cell #13 IAW BSPP-BAT010
WO 0042888401, 1-1 B-1 125 VBC Battery Cell # 13 has a low voltage reading
WO 0044659406, Perform single cell charging on 1A-2 Battery Cell # 1
WO 0037821401, 18-2 Battery Cell ?# 53 has a cell voltage of 2.124, minimum voltage is 2.1 3
WO 0033286001, 1-1 8-2 Battery corrosion found on positive terminal of battery cell # 52
~ I-1A-1 Battery corrosion found
WO 0033285301, l-IAP-125VDC-BAT. Replace Cell # 4 on Battery 1A-2
WO 001 6351401, Equalize 1-1 8-2-1 25VBC-BAT IAW OPM-BAT004
6
WO 0014092401, 1-152 Cell # I needs to be replaced due to low specific gravity reading
WO 0006930901, Using ESR 00-00345 and WO Task knstructions, Replace Cell # 54 in I-1B-
WO WRiJO 99-ADIK1, Troubleshoot and assist operations in ground hunting for 18 Battery
WO 0043131301, 1-1A-2-125VDC-CHRGW investigate breaker tripkharger voltage card
WO WWJO 99-AFEC1, Replace floatlequalize toggle switch on I-$A-1-125VBC-CHWGR
WO WWJO 99-AFED1, Replace floaffequalize toggie switch on 1 -lA-2-125VQC-CHRGR
WO WWJO 99-AFEEI Replace floatlequalize toggle switch on 1-1 B-1-125VDC-CHRGR
WO WWJO 99-AFEE2, Place 1-1 B-I-125VDC-BAT on equalize
WO WWJO 99-AGKAI, Investigate problem with 1-18-2-125VDC-CHRGR
WO WWJO 99-AGKA2, Troubleshoot ground on 1-1B-2 Battery Charger during Unit 1 outage
WO WWJO 99-AFEF1, Replace floatlequalize toggle switch on 1-1 8-2-125VDC-CHRGR
WO WWJO 98-ACNW 1, Troubleshoot and Repair 1-1 B-2-125VDC-CHRGR
WO 0033286301, Perform OMST-BAWI SQ to remove corrosion from battery terminals
WO 0033286201, Perform OMST-BATTI 1Q to remove corrosion
WO 0027849301, 2-2A-1-125VDC-BAT, Petform DLRO measurements
WO 0027849201,2-28-1 -125VDC-BAT, Perform DLRO measurements
WQ 0016331601, 2-2B-I-125VDC-CHRGR has no output voltage please investigate and repair
WO 001 3345101, The corrected specific gravity was less than the required 1.205 tolerance
WO WWJO 99-ADMLI, Place 125 VDC Battery Banks 2A-1,2A-2,2B-II 2B-2 on equalize
WO WWJO 00-ADJS1, Replace Cell # 27 in 2-2A-2-125VDC-BAT
WO WWJO 00-ADEEf , Clean off electrolyte on cell #27 of 2-28-2 Battery
WQ WWJO 99-AAGJI, 2-28-2-125VDC-BAT individual ceil voltage out of tolerance
WO WWJQ 00-AARJ1, Troubleshoot 2-28 battery bus ground
WO WWJO 99-ACRSI , Replace floatlequalize toggle switch on 2-2A-2-125VDC-CHRGR
WO WR/JO 99-ACSWI, Replace floatlequalize toggle switch on 2-2A-1-125VDC-CHRGR
WO 001 11 66201, Replace floaffequalize toggle switch on 2-28-1-125VBC-CHRGR
WO 0017170101, Specific gravity on Cell #56 of battery 1B-2 out of tolerance
WO WWJO 99-AAGEd. I-lB-2-125VDC-BAT Cell #37 voltage low
WWJQ ASLEOOI ,I
-E6-AV4-52, 5175 480 VAC Distribution System, Substation Breaker PM
WWJO ADUEQOl ,l-Es-AU9-52, 5175 480 VAC Distribution System, Substation Breaker PM
WWJO
ADKC007 ,1 -EB-AXI-52,5175 480 VAC Distribution System, Substation Breaker PM
WWJO 99-ACPTI ,2-2CB-C56, 5175 480 VAC Distribution System, Substation Breaker
WR/JO 00-ABHD2,1-1CA-C05, 5175 480 VAC Distribution System, Substation Breaker
WWJO 00-ABDH1 ,1 -1 CAC05, 5175 480 VAC Distribution System, Substation Breaker
WWJO ACDUOO-i, 2-2A-GKO-72, 5240 125 VDC Battery Charger System, Circuit Breaker
WWJO ACDXOOI, 2-2A-GK3-72,5240 125 VDC Battery Charger System, Circuit Breaker
WR/J0 AAKOOOI, 2-2CB-656-52, 5240 125 VDC Battery Charger System, Circuit Breaker
WO 0005034401, PM on 1 -E2-A#1
WO 0017871402, In-situ Test of Mag Latch for 1-E6-AV4-52
125VDC-BAT while batteries remain on line
BUS IAW OAl-I 15 and IOP-51
replacement
Maintenance
Maintenance
Maintenance
Functional Test
Functional Test
Maintenance
7
W B 0030223001, Overload Relay Setting Change
WO 0019871802, In-situ Test on 143-AV4-52
WO 0029973501, Circuit Breaker Tie Between Unit Substation E5&E6
WO 0017868201, in-situ Test of Mag Latch of E5E6 Tie Breaker
WO 0005033201, PM on I-E2-AH1
WO 0012789501, Breaker Operator Replacement
WO 0005030701 PM on Breaker 1 -dB-GMI -72
WO 5005009301, PM on Breaker 1-1B-GM4-72
WO 0029610701 I PM OR Breaker 2-25-GM1-72
WO 0029609301, PM on Breaker 2-25-GM4-72
WO 0013432712, Test/Replace Breaker 2B-l-125VDC-Charger AC CKT
Comcdeted Surveillance Procedures. Preventive Maintenance (PM). and Test Records
OPT-12.6, Breaker Alignment Surveillance, Rev. 42, Completed 8/2/03, 8/9/03, 8/16/03, 8/23/03
Action Reauests (ARs.
087358, Deficiencies related with valve 2-E41-F001
CR 97-02379; Determine if Vortexing Problem Exists in the CST When Running the HPCl
AB 00005402; Vortexing in CST Needs More Formal Analysis than CR 97-02379; dated
AR 00098654,125 VDC 1A-2 Battery Charger Main Supply Breaker Trip
AR 00047078, 1 B-2 Cell # 56 Failed Specific Gravity
AR 00091O76, Positive Plate Discoloration and Expansion
AR 00071079, 16-2 Battery cells have positive piate discoloration and expansion
AR 00058078, Battery $A-2 has low voltage cells
AR 00053109, Visual signs of degradation on 213-1 battery
AR 00083997,2A-I Battery Cell #31 cracked cell top
AR 00085750, 1B-2 Battery Cell #53 has a low voltage
AB 00044684, 15-2 Batteries are A(1) under new Maintenance Rule criteria
AI? 00052618, BC MOV Thermal Overload Heater Sizing
AI? 00076440, BESS Caiculatiofls Self Assessment 50952
Action Reauests Written Due to this lnsnection
101924, Update periodic maintenance program to add periodic replacement of diaphram in
Pump; dated August 27, 1997.
December 30,1998.
valve E41-PCV-152, dated 08/14/03
102321, Valve E41-FC42, reduced voltage strike time calculation basis, dated 08/14/03
102456, CST Vortexing Documentation Discrepancies; dated 08/20/03
103005, Note in OPT-09.2 Referring to Auto Closure of HPCl Steam Line Brains (F029 and
F028) should have been removed by ESR 99-00405, dated 08/26/04
8
103106, Correct procedure inconsistencies in preventative maintenance Procedure
OQM-EfKR001, ITE 4KV Breaker and Compartment Checkout, dated 08/27/03
103252, Procedure Enhancement to OPT-09.3, Rev. 50, HPCl System - 165 Psig Flow Test.
Add Procedural Guidance to Ensure that HPCl Minimum Flow isolation Valve E41-FO12 Goes
Closed After Proper Flow Setpoint is Reached, dated 08/28/03
103256, Procedure Enhancement to OPT-09.2, Rev. 1 11, HPCl System Operability Test. Add
Procedural Guidance to Ensure that HPCl Minimum Flow Isolation Valve E41-FO12 Goes
Closed After Proper Flow Setpoint is Reached, dated 08/28/03
103299, Provide procedural guidance as io when a Shift Technical Advisor should activate their
post, dated 08/28/03
Lesson Plans/Job Performance Measures (JPM)
Lesson Plan CLS-LP-51, BC Distribution, Rev. 0
Lesson Plan CkS-LP-402-G, Electrical Failure Related AOPs (AQP-32.0, AOP-22.0, AOP-36.1,
AOT-OJP-JP-O51-AOI, DC Ground Isolation for P, N , and P/N, Rev. 1
AOT-OJT-JP-302-GO1, Loss of BC Power - Transfer of DC Control Power, Rev. 2
Miscellaneous Documents:
Brunswick Nuclear Plant Probabilistic Safety Assessment
RSC 98-24, Reactor Core Isolation Cooling System Notebook, Rev. 0
RSC 98-23, HPCl System Notebook, Rev. O
HPCI System Periodic Review, dated 02/20/03
RClC System Periodic Review, dated 02/20/03
Maintenance Rule §coping and Performance Criteria, System 1001, ECCS Suction Strainer
Vendor Manual FP-3808, Battery Charger, Rev. G
Specification 137-002, 125 Volt Battery Chargers, Rev. 9
Engineering Evaluation BNP-DC-03, Overload Heater Resizing for Valves 1-E41-F00II FOQ6,
and AQP-39.0). Rev. 0
FOOT, and FOO8, Rev. 0
BCT-09-2083 W3:41
PPl
B R U N S W I C K R E G BFF
9104573014
P . 1 6
AII 106230-10 Operability Review
Page 1 of 20
AR 102,456 was written to address documentation discrqsancies with respect to pottntkl air
entrainment in the con,ndensate storage tank (CST)
~ ~ p p l y
line due to vortex a1 the suction nozzle
prior to completion of the H E 1 pump suction auto transfer on low CST level.
An initia? operability evduation concluded that the low CST WCI level insbmmentathn ia still
operable. Due to additional questions and concerns, a more detailed operability evaluation was
desired. 'This evaluation provides additional detail. When more detail was added tQ the review,
some unneeded conservatism were no longer applied and the end results actudly improved,
The issue in question, foe both Units 1 and 2, is whether the setpoint for the Technical
Specification (TS) Table 3.3.5.1-1 Function 3.d. HPCI Condensate Srmge Tank Level -Low
insmentation is appropriate. This instrumentstion is required when the plant is in MODE 1
and a h when in MODES 2 and 3 with reactor stem dome pressure water than 150 pig.
TS Bases B 33.5.1 discusem the PIPGI Condensate Storage Tank Level-Low function:
LOOW
level in the CST indicates the unavairability of an tldequste supply of makeup water
from this normal source. Normally 6he suction valves between HpeI and the CST are open
and, upon receiving a HPCI initiation signal, water for KPCI injection wouldbt taken from
the CST. However, if the water level in the CST falls below a psesclecteci level, fimt the
8 U p p S d O n p o l suction valves automatically open, and then the CST suction valve
automatically cio&es. This ensures that an adequate supply of makeup water is available to
the MlpcI pump. To prevent losing suction to the pump, the suction valves are interlwked
sion pool suction valves m ~ ~ t
bc open before the CST suction valve
automatically chses. The Function is implicitly assumed in the accident and transient
analyses (which take credit for HPCI) since the analyses assume that the HPCI suction
s o w is the suppression pool.
The Condensate Storage Tank Level-Low signal is initiated from two level switches. The
lo& ie arranged slack that either level switch cxn cause the suppression pool suction valves
to open and the CST suction valve to close. The Condensate Storage Tank Level--Low
FURC~~DII
Allowable Value is high enough to ensure adequate pump suction head while water
is being takrn faom the CST.
Two channels of the Condensate Storage Tank Level-Low Function are nquired to be
OPERABLE only When HPCI is required to be OPERABLE to en8uTe that no single
insmmenr failure can preclude HPCi swap to suppression pool source.
H41-ULNW and Mi-LSL-NOQS are TS required instrumentation and are designated 8s Q
Clslla A (safety related). Elquipmcnt datnbase (H>B) describes the active function as P~wv&% a
signal to the WPCI logic when the condensate storage tank level is low. This opens valves E41-
FM1 and E41-FQ42 to dlow WPCl pump suction from the suppnssion p~o!."
This review was performed in accordance with EGR-NGGC-0019,
Engineering Operability
Assessment, and makes dime reference to NRC Inspection Manual, Part 9900: Technical
Guidance STS1Oo.TG and STS IOOPSTS. It supports the determination that the deficiencies
are. dacumentation problems only and that no oprability coneem exists.
ATTACHMENT 2
AR 106230-10 Operability Review
Page 2 of 20
The definition ofOPERABLBO?ERAB~LITY
is contained in Chapter 1 of the plant's
Technical Specifications which states:
A system, subsystem, division, component, or device shall be O?ERABLB OT have
OPmAI4ILITY when it is capable of perfoming its specified safety funCtion(s) and when
dl necessary attendant instrumentation, controls, normal or emergency elect13cd p e r ,
cooling and seal water, lubrication, and other auxiliary equipment that are required for the
system, ~ubsystern, division, component, or device to perfom its specified safety function(@
ate also capable of pefloming their related support function(s).
For the H E 1 CST Level-Low instmmenratioa to be OPERABLE, the chawlaels must be in
calibration and the CST Level-Low Function Allowable Value must bc high enough Io ensm an
sdquate 8upply of water is available for all MPCI system specified functions. The preaence of
vwtexing in the CST wm not initially factored into the setpoint development. This evalunlticm
demonstrates that the current TS Allowable Value for the instmentation setpaint ie appropriate
for all HPC1 system specified fUnCtiQn9 with the effects of the CST suction vortexing
phenomenon considered.
As stared in M C
Inspection Manual, Part 9900: Technicai Guidance, STSlOOP.Sri'S, 3.3
Specified Function(s):
%e definition of operability refers to capability to perfom the "specified functione," The
SpeciEied bclim(s) of the system. subsystem, train, component, or device (hereafter
refed to a!? system) is that specified safety function(8) in the cumnt licensing basis for the
facility.
In addition to providing the specified safety function, a system is expected to perform a
designed, test&, and maintained. When system capabiiity is de
to a point where it
cannot periWm with reasonable assurance of reliability, the system ahould be judged
inopefable, even if at this instantaneous pint in time the system could provide the specified
safety function.
AB stated in NRC h6pction Mwual, Pan 9900: Technical Guidance, STSIOOP.STS, 2.1
C m n t Licensing Bassis:
Cunent licensing basis (CLB) is the set of NRC requirements applicable to a spific plant,
and a licensee's written commitments for =wring compliance with and operation within
applicable NRC requirements and the plant-specific design basis (including all
modifications and additions to such commitments over the life of the license) that an?
docketed and in effect. The CLB includes the NRC ngulations contained in IO Cm Parts
2,19.2D, 21,30,40,50, SI, 55,?2,73,100 and appendices thereto; orden: license
conditions; exemptions, and Technical Specifications (TS). It also includes the plant-
specific design basis infomation defined in 10 CFR 50.2 a5 documented in the rnmt m n t
Find Safety Analysis Repon (FSAR) as required by 10 CFR S0.71 mad the licmsm's
comiome~ts remaining in effect that were made in hketed licensing c~mspondence such
88 licensee respanscs to NRC bullctins, generic Ictcers, and enforcement Bctions. BS well as
licensee eomrnitnaents documented in NRC safety evaluations or licensee event repone.
P . 1 7
O C T - 8 9 - 2 0 0 3 03:42 P M
B R U N S U I C K RE4 eFF
9184553814
P. 1 B
AR 106230-10 Operability Review
Page 3 of 20
A5 stated in NRC Inspection Manual, Part 9908: Technical Guidance, STS100.Ki, ScctiOn 1.0,
C.S. Principal Criteria, the following are the principal criteria for technical speGification
operability rquirem~ts:
a, The system oprability requirements should ke consistent with the safety ana)ySiS Of
b. The system operability quirernemts, including related regulato~ requirements, my be
c. Design-basis events are plant specific and regulatory requirements may have plant-
d. The system opesability quiremen& that are based on safety analysjs of spcific desip-
specific desipbases events and regulatory requirements.
waived B I ~ a consequence of swified action statements.
spedflc considerations related to technical specification operability.
bmis events fer one mode or condition of operation may not be the same for ail modes 0%
conditions of operation.
e. The system qxrability requirements extend to necess~sy support systems regardless of the
existence or absence ~fsttpp~n
system quiroments.
f. lphe operability of necessary support systems includes regulatory requimnentli. It doca
not include consideration of the Dccumnce of multiple (simultaneous) &sign buls
events.
Also applicable to this discussion is NRC Inspection Manual, Part 990: Technic& Guidme,
STSlO(9.TG. Section 1.0, D. Conclusion:
Many systems and components perform dual-function roles with ?egard to midart
mitigation and Foe events for which safe plant shutdown is required. The cotrcct application
of operability quirenuents for them systems and components requins additiond reliance on
a knowlededge of design bssis events. Thus, it is essential for the proper application of
technical specification operability requirements, to know the applicable design-basis events
for the facility.
.
OCT--BS-2883
83:42 P W
B R U N S W I C K R E G FIFF
9104573014
P. 19
AR 196230-10 Ojknrbility Review
Page 4 of 20
The specified functions for the IfpcI spstem for the purposes of this operability evduatim are as
follows:
F-B:
HPCI LoeA Licensing Basis Function
The Oriri$inal mI design and limnsing basis requirements were established such th$K HecI was
a part of the integrated ECCS group of systems that provide a LOCA response capability
consistent with the requirements of 1QCFw50.46.
OR March 29 1989, CP&E submitted an evaluation to the NRC for revised L E A licensing basis
rand to update the demonstration of conformance to the ceiteria provided in iOCPR50.46, a6
modified by SECY-83-472, Emergency Core Coolant System Analysis Methods. This
evduati~n, Brunswick S t e m Electric Plant, Units 1 & 2, SAFEWGESTR-LOCA bnas-of-
Coolant Accident Anfdysie, NEDC31624P, assumed less performance from ECCS systems to
allow for relaxation of some selected requirements,
On May 17,19&9,6P&L submitted a written response to 0 verbal NRC request for additional
information. I"XC Question 2 was given as:
Relative to relaxations of input values (Table AI), what ate all of the nlaxatims between
the new analysis and the analysis of record (Le., the current analysis).
The respnse to Quwtim 2 grovided a tiable which included the following:
r n M
ANALYSIS OFRECORD
NEW ANALYSIS
HPCI hump Minimum Flew
4250 gpm
0 gPm
On June I, 1989, the NRC iaswd a Safety Evaluation for the CP&L submittal. This SER
included "tsstly the staff notes that significant system or component assumptions included no
offsite pawet, RO high pressu~ coolant injection system, two SRVIADS valves out of servkc
and a SRV setpint tolerance of 3% The assumptions are acceptable." It also p v i d d t h e
fdowing "On this basis. the analysis contsined in the GE report can be Used to @rdde
B nvkd
LOCA licmnsing basis for both Brunswlck units, and can be referenced in futuro submittals."
The HK.1 p u f o m c e requirements were discussed more recently in NEDG-33039P, The
Safety Andysis Report for Brunswick Units 1 and 2 Extanded Power Uprate (pUsAI6), that WBB
part of the 08M/01 120% power uprate submittal. The report included the fdowing
"Ori@inally, the HITI system was primarily for the mitigation of small break ILEA8 where the
depressurization function [Automatic Depressurization System (ADS) I SRVa] WW assumed TO
fail. Fw BSEPP, the depressurization function is Fully redundant, and no accidenr mitigation
credit is taken for the HPCI system."
On the bmis of the 1989 NRC SER, the cutrent safety related L N A licensing basis prrformance
criteria for KPCI at BSEP is 0 gpm. Given the above, the potential for air enrPainmnt 81 the
CST suction nozzle during HpcI operation is not a concern with respect to the ECCS
rcquircments of 1OCFR50.46 and no further discus5bn of this function will be prOVi&.
O C T - E 9 - 2 0 E 3
03:42
P M
B R U N S W I C K R E G FlFF
9 1 R 4 3 7 3 0 1 4
._
AR 106238-10 Operability Review
Page 5 of 20
F
m
Piefed Response to a 1" Line Break Function
Although not Wuired for the BSEB JAXA licensing basis as discwssed in Function 1 above,
BSEP d w s consider HPCI operation to be the preferred method of responding to very srnd line
breaks. VFSAR 6.3.1.2 and 6.3.3.5 have the following statements which go along with this
fundon:
One high pressure cooling system is provided, which is capable of maintaining (he water
level above the top of the core and preventing ABS actuation for small b~aks.
and
For the HPCI, a criterion was used (in addition to the criterion that it d e p x c ~ s ~ ~
p p r l y in conjunction with the low pmsure systems) which prevents cfaddlng headng
far h a k s less than a 1-in. pipe when functioning alone, This wm done to ensum
maincen@rmce of level at rated vessei pressure for the more probable leaks thst might occur
QVCT plant life. Since I-in. lines predominate, this provided a good basis for such a
criterion. This flow io also orders of magnitude in excess of leakage that would occur for
cracb approaching critical size in large pipes.
The abve IJFS.4.R 8tatetnCntS provided the basis for the following portion of the PWSAR
described WPCI funnctim: "me primary remaining purpose of the FECI system is to maintain
reactor level above the top of the active fuel (TAR and prevent ADS actuatim for line breake up
tQ I" in dim*."
ESR 99-0062 evaluated the ability of W I to meet the above requirements in response t0
response t h e testing concerns. This ESR documented that less than l@lO gpm of makeup flow
was required in response to a 1" line break,
B a d on the above this is an explicit function associeted with :he BNP specific HPCI Licensing
h i s .
Function 2 88 described above does not inherently exclude the possibility of HPCl suction
transfer m !OW CST level. Evaluation of the potential for air entrainment at the CST suction
noule duhg HPCI Qperaaion for this function will be evaluated a8 Case 1
.
OCT--89--2803
83243 Bbl
B R U N S W I C K R E G eFF
-
-
-~
9104573814
P . 2 1
AR 104230-10 Operability Review
Page 6 of 20
Function 3: Backup to RCIC Function
WPCH also h a a design requirement that it be capable of providing a backup to the non safety
related RCE fuwtiOR for loss of feedwater and vessel isolation events. Technical Specifications
require that RGIC be able to inject water to the vessei at 400 gpm over the same m g e of vessel
pressme as is specified for WCI. The RCIC functional nquiwnents specified in UPSAR 5.4.6
include:
The RCIC system operates automatically to maintain sufficient coolant in the reactor
veswl to prevent overhesting of the reactor fuel, in the event of reactor isolation
accompanied by loss of feedwater flow. The system functions in a timeiy manner so that
integrity of the rgxtioactive material bamer is not compromised.
This is a transient response function and is not a Safety Related function. Technical
Specification aquirements have been maintained because of the contribution to the
reduction of overall plant risk provided by RCIC.
After the 105% Power Uprate, analysis showed that the original RCIC performslace
quhmenbs (4W gpm starting 30 seconds after initiation) would result iIl a lowest level
Inside rtme shmud of no less than 5.4 ft above the top of active fuel. Even with relared
perfomnce requirements of 360 gpm starting 66) seconds after initiation, the lowest
level Insick the shroud would be no less than 4.7 ft above the top of active fuel. Either
nspon8e ia aeccptable.
RCIC operetion can prevent the need for ABS biowdown and low preressupe ECCS
injection following a loss of feedwater.
Transient rcsponse graphs in NEF1Bc-30106-P (the GE basis for changing the MSIV isolation
setpoint from LL2 to LId that provrded LTSAR Figure 15.2.6-3) and GE-NE-187-26-1292
(Power Upate Transient Analysis for Bmnswick Steam Electric Plant) indicate water level may
drop far enough to c w e LL3 actuation (level olttside the shroud between 33.3' and 35.3' above
vessel zero). For thie event, operators would inhibit A D S a5 directed in EBPs due to the large
margin between the LJ3 setpoint and top of active fuel, the lack of LQCA indications and the
slow fate of level decrease. A slow downward trend would follow as the mass of steam flew for
decay heat removal via SRV actuations initially exceeds the RCXC makeup flow. At 15 to 20
minutes into the event, the level trend would stabilize and then later start to increase a8 the RCIC
makeup matches and then exceeds the steam flew for decay heat removal.
The above UFSAR statements are consistent with the following portion of the P S A R dessnbed
HPCI function: "'Kc HPCI system also serve6 as a backup to the Reactor Core Isolation Cooling
(RCIC) system to provide makeup water in the event of a loss of feedwater flow transient. For
the loss of feedwater flow transient, which assumes closure of the Mslin steam halation ValVeP
(MSrVs), the currentty specified WCI system minimum injection rate of 3825 gpm would
pvide sufficient makeup water to maintain the level inside the shroud well above TAP. DMwg
tfiis transient event, the SRVs would open, then cycle, and the WCI system would quickly retwm
the reactor water level to P~WIIIR~, or to the reactor high water level trip (i.e., kvel 8 shutoffh"
Note that the 3825 gpm vaiue used above is 90% of the original design Row and is the value that
BE would have specified for HPCI in the SAIFEWGESTR-LQCA evaluation had K K I
operatton b
n
credited. A high HPCI flow rate is appropriate only fer the ATWS function not
. O C T - - Y 9 - 2 0 0 3
53:43 PPI
B R U N S W I C K R E 6 QFF
9 1 0 4 5 7 3 8 1 4
P.22
AR 106230-10 Operability Review
Page 7 of ZQ
the backup to RCIC function. A flow rate of 400 gpm is the ticensing basis flow rat0
requirement for the HPCI Backup to RCIC Function.
Based on the above,this HETI function is an expiicit fUIICtiOR associated with ?-he BNP specific
IIPCURCIC Licensing basis.
Function 3 as described above does not inherently exciude the possibility o f m l SWtia
transfer on low C§T level. Evaluation of the potential for air entrainment at the CST suction
nozzle during NPCI operation for this function will be evaluated as Case 2. Case 3 and Case 4.
Function 4: SB6 Function
Although not pan of the original HPCI design basis, the HPCI system has been credited fW
providing makeup water during B postulated Station Blackout (SBO) event. The most recent
SBO evdu~tion required HPCI to deliver approximately 86,080 gallons of CST water to the
Reactor in a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> time m o d . This is an average flow wte of only 3.58 gpm. The peak flow
requirement for this event can be estimated as the decay heat removal plow rate nonndy
provided by RCIC at 4QO gppm combined with an assumed 61 gpm win: pump seal leak or 461
kpm.
Although the W S A R did not explicitly describe the above " C I function, this function waa an
essential pan of the SBO evaluation th&t was described at the summary level in the PWSAR.
B
d
on the above this WCI function is an implied function associated with the BNP specific
SBQ Licensing basis.
Since RHB operation is not assumed for the initial SBO response, significant Suppression Pwl
heating is anticipated. Due to HPCI system process fluid temperacue limitations, the event
explicitly excludes allowing CST depletion. This requirement establishes a limit on the highest
allowed actuation of the low CST level HLPCL instruments.
Function 5: Appendix R Function
Although not pant of the original FPCX design basis, the I;IpcI sysfem has been credited for
providing makeup water during a postulated Appendix R event. Appendix R evaluations
squired W
I
to deliver CST water to the Reactor for decay heat removal when manually
started after a number of other manual operator actions are completed. RCIC has a similar
Appendix R function. The use of RCIC for the similar Appendix R event was found to q u i r e a
peak flow rate of 500 gpm.
Although the MJSAR did not explicitly describe the above W
I
function, this funCtiOn i5
essential for Appendix R compliance. Appendix R compliance a uprated conditions is descrjbctl
at the summary level in the PUSAR. Based on &e above this HKX function is an implied
function apsociatd with the BNP specific Appendix R Licendng basis.
SirrPiliv to the SBO event, the Appendix R event is evaluated over a specific time penOd. The
mal required makeup inventory for this event will not exceed the required makeup for thc SBO
event. Suppression pool temperature is expected to exceed the allowed temperaturn for #pcI
operation, CST depletion is not a required assumption for this evenr.
"
OCT-B9-288%
83:44 PPI
B R U N S W I G K R E G BFF
~-
9 1 0 4 5 7 3 6 1 4
P. 2s
AR 106230-10 Operabillry Review
Page 8 of 20
pction 6: HPCB Rod Drop Function
I-PCI may be used for vessel inventory makeup following a rod drop accident. Although a
03/IY02
Extended Power Uprate RAI response documented that neither HBCI nw RCIC
operation is required for a rod drop event, HPCl usage would be expected if RCIC is not
available. The nquired makeup during this event is based on decay heat alone where either
HPCI or RCIC operation would be sufficient. This function is essentially the game as the
Backup to RCIC function that is addressed in the C w 2, Case 3 and Case 4 cvdulaiione.
Function 7: HPCI ATWS Function
When the 120% power uprate site specific ATWS evaluation was performed, KPCI operation
WBS assumed. The operation of HPCI during iin ATWS is based entirely on manual operator
actions including inhibiting the auto start at Low Level 2, manually allowing WCX to start just
prior to reaching the desired level, and then promptly adjusting the flow controller secpolnt a8
ne%clled to control level in B n m w band.
Although the FUSAR did not explicitly describe the above HPCI function, this hn~tim
was an
essential pdin afthe ATWS evaluation &hat was described at the susnmtppy level in the PUSAR.
Baaed on the above this MPGI function is an implied function associatd with the BNP specific
ATWS Licensing basis.
This event is also an event where Suppmssion Pod temperatun% are expected to exceed the limit
for w?cI operation. ASSKIW~
WCI operation for an ATWS response will be for a relatively
short duration and the event does not amme CST depletion.
O C T - W S - ~ ~ W ~
m:44 P M
BRUNSWICK R EG A F F
-
9 1 8 4 5 7 3 8 1 4
P. 24
AR 106230-10 Operability Review
Page 9 Qf 20
The h w CST level setpoint does not need to provide any pmtection for LOCA even&. It do=
provide yrotectios when either an operator action in accordance with existing procedures,
suppflsiiwr pool level reduction is credited, or when early MSIV Closure is Rat assumed.
For all LOCA response wen&, operator actions to drain the suppression pa01 or to jumper the
high suppsion pool level FPCf instntments would not be allowed by proceduns. The " C I
sactian transfee occurs based on high suppression pool level and the CST inventory is n e w fully
depleted. No air ~ x h e s
the HPCI pump and all HPCI performance is consistent with UFSAR
descriptions.
The Tech Spec hstrumen! function is however required for HPCI when it is pmviding the
backup to RCIC function. This funstton can requin extended NPCI operation, either at a
reduced flow rate or intermittently. The potentid fw an acceptabte operator action in reccordence
with existing procedmo (educing suppression pa01 level) could result in pump damage if the
stpoint is not adequate. Additionally, if early MSIV closure does not occur, a loss of feedwater
event may result in CST depletionc For this backup to RCK function, opcrarer actians for
mnudIycmtrolling vesseS level late in the event are appropriate. Etthtr the WCI flow rata
would be reduced acceptably or HFC6 would be operated at full flow for only 60 seeonds. For
dhe full faow caw, no air would Each the pump during the last injection with CST suction and
the WCI suction swap would then be completed prior to the next HPCI injection. This proVides
the Protechicpn that is nm&d to prevent continued "Cl operation with the suction lined up to a
depleted CST.
1 TS Table 3.3.5.1-1. Function 3.e. #pcI Suppression Chamber ~vel-High
Instrumentation Channels are operable (otherwise, WCI pump suction would be aligned
to the suppfession P I ) . NP@I auto transfer on high suppression pool kvel starts at the -
24 inch Tech Spec limit.
2 Cofhmak Stomp Tank level is being maintained at a minimum of 10' in accordance
wiKh UPSAR 9.262 requirements. See Attachment 1 for CST volumes at variom Icveb.
3 WCI auto transfer on low CST level start5 at the 23' 4 Tech Spec limit.
4 S u p s s i o n p
l
Ievel is assumed to start at the -31 inch Tech Spec low level limiL
5 w"cI suction valves operate with maximum stroke times allowed during sUndat9Ce
testing.
6 The HPCI system will respond to automatic signals at Tech Spec specified serpoints, and
OpMatora will operate the plant in accordance with existfng design basis, training and
prOCC&*S.
7 If NPCf actuates automatically (Le,, due to low reactor water kwl)
RCIC will also
actutatc if available.
8 CRlp is nDt taking suction from the CST as the bottom of the suction nozzle supplying
CRD is more than 9' above the bottom of the tank.
9 Ne sources ~ k e
ndding waiet to the GST and no actions are taken to refill the CST.
10 The plant is at noma full power, 2923 MWt.
I
OCT-09-2083 83:45 P M
B R U N S U I C K R E G A F F
9104Ei73014
AR 106230-10 Operability Review
Page $0 of20
e IIpeI is providing the Pafemd Response to 1 Line Break function
0 Operators may or may not manually control vessel level
Requind manual operation of RHK is assumed in accordance with proccdurcs
Case 1, HPCI and RClC will inject QR low wactor water !eve1 (LL2, 105). If not manually
secured due to the standad post trip 170 to 200 level control band procedure requiremenl,
WBCI and RCIC will trip when level reaches the high feactor level trip setpoint at 206. Level
will then continue to cycle between 105 and 286 if RO operator actctrons are assumed 01: 190
and 200 if operatom RE performing normal event response actions. Level control assumptions
do nor affect the outcome of this case.
Since this event involves a small break LWA, significant drywell heating and pssurizatim
would mur. Operatom would place at least one loop of WI-IR in suppres8ion pool cooling at 18
minutes consisknslt witlh existing BSEP Licensing basis assumptions (ref. UFSAR 6.2.2.3). RWR
would also be used for containment spray if drywell pressure approaches or exceeds 11 pBig, but
containment spray operation would be terminated prior to resetting the Group 2 isolation
instrumentation that actutltes at 2 psig. With drywell pres5ure above 2 psig, no flow path is
available for reducing suppression pool ievel due to the isolation of Ell-FW md Ell-FW9.
With RHR in auppmsioil pool cooling and the reactor not depressurized via SRVs, suppnssion
peol ternpeRlture8 would not increw to a value where overriding the HPCI high suppreselon
pol level transfer inemmentation is allowed.
Continued operation of KPCI and/or RCJC rends to depressurize the vessel 8s it nmoves steam
from the reactor and 8s it injects low temperature wster into the vessel. Although it is possible
that cmtinued HFCI operation could reduce vessel pressure to below the C I isolation 8etpdnt
prim to my automatic auction transfer for larger small breaks, this is not expected for the 1 line
break king considend here.
The HPCI suction transfer will stm after 94,330 gallons of water Is injected based on high
suppression pwl level, not low CST level (see Attachment 2 for supporting &tds).
The CST
lswl would k at least 8.0 inches above the top of &e CST suction nozzle after the transfer k
complete. A recent industry paper, JBOC200UPWR-190010,
presents the best published
information applicable to this appIication that BNP has been able to find. Although the plant
review indicates that the nominal equation provides a conservative estimate for our CST, the
bounding eqUQtiOn for 0% air from JPGC2001/PWR-1$010,
Equation 10, was used in this case
for conservatism:
Sa% I
1.363*FrA0.261 where Fr = V1(32.2*(d/12)0.5 and S = (d+Lll/d
d
Pipam
n o w
Velocity
Fr
S-0%
L14%
I5
1.23
4 7 0
8.53
1.345 1.473
7.09
(in)
(frA22)
(gem)
Wet)
(in)
This shows that no airentrainment at the CST nozzle will occur far CrrSR I.
P.25
O C T - - 8 9 - 2 0 0 3
0 3 2 4 5 PPl
B R U N S U I C K R E G QFF
9184573814
P. 26
AR 106230-10 Operability Review
Page1lofaO
0 HPCI is providing the Backup to RCIC function
0 h p t MSIV closure occurs
e No cperstor actions assumed other than the required initiation of suppression pool
cooling
For Cwe 2, WBCI operation alone will bc considered as RCiC unavailability is part of the CBBC
definition. Wl will auto start on low reactor water level (LU, l05"). "(3 will Wip W
h
level reaches the high reactor level trip setpoint at 206". Level will then continue to cycle
between 105" and 286".
This event does not involve a small break LOCA, but it may involve a loss of drywell cooling.
Drywell heating and pressurization to above 2 peig may or may not occur. Operatma would
place & feast one loop o f M in suppression. pool cooling a1 10 minutes. With RHR in
suppression pool cooiing and the reactor nut depressurized vie SRVs, suppssion pool
temperatures would not increase fo a value whea overriding the HPCI high suppression p
l
level transfer instrumentation is allowed. Note that if RHR suppression pool cooling is not
5tute5, " C I would eventually be operating with the suction lined up to the suppression
and the supppessim pool water remperanurc above the value allowed for Hp@I operation.
Conhued o p h n of IipCI tends to depressurize the veasel as it removes s t e m fmm the
reactor and 8s it iaajecte low ternpalure water into the vessel. Although it is possible that
Continued mI operation could reduce vessel pressure to below the HPCI isolation setpoint
prior tn any automatic suction transfer for small breaks, this is not expected for the case being
considerect here.
With MSIV closure, all coolant removed from the vessel will be discharged tD the mpp,ssion
p l
via SRVs and the HPCK turbine exhaust. For this case, the suction transfer Will start after
only 43,160 gallons of water is injected to the vessel based on high suppression pi level. The
volume would be less than for Case 1 as the lower elevation of the drywell does not collect my
water. Also the qqulnd submergence would be less than for Case 1 since only HPCI operation
is assumed. The margin for avoiding air entrainment is therefore increased and the event would
be acceptable.
___
~-
-
P. 2 s
OCT--89-2BBS
03:46 P M
B R U N S W I C K R E G A F F
9164573Ef14
AR 106230-10 Operability Review
Page 12 of 20
- pcI is providing the Baekekup to RCIC function
m Prompt MSIV closure occuls
Qpmtors initiate suppression pool cooling
e Operators perform suppression pooi level contml in accordanhe with proceduns
e Operators eventually perform vessel level control in accordance with procedures
WCI operation alone will be considered as RCIC unavailability is part uf the case definition.
=I
will auto start on low reactor water level (LL2, lO5). HPCI will trip when level %aches
the high reactor Ievd trip setpoint at 206. kvel may continue to cycle between 105 and 206
until such time that operators have had time to assess plant conditions and complctc any other
m m important actions. Additional discussion of manual actions to control level in the spified
170 to 2oh) ievef contpol band will be pmvided below.
This event does not involve R smaH bfeak LOCA, but it may involve a loss of drywell cooling.
Drywell heating and pmsurization to above 2 psig may or may not occur. opmttors would
place at least one Imp of RHB in suppression pool cooling consistent with existing BSEP
licensing basis assumptions. With RHA in suppression pool cooling and the reactor not
depnssutized via SRVs, suppression pool tempecnrtures would no? increase to a value w h m
oveniding the Hpcy hi& suppression pool level transfer instrumentation is allowed.
The coolant removed from the vessel will be discharged to the suppression pool via SRVs and
the HPCI turbine exhaust and the lower elevation of the drywell will not fill with water. For chis
case it will be assumed that prim to reaching the high suppression pod Hg61 level instrument
Setpoint, dfpel1 pressure has been controlled or restored such the manually reducing
suplprcssion pol level is possible. It wa8 estimated that this would occur at between 0.8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />
and 1.8 h o w into the event depending on starting suppression pod IeveI.
For this case CST depletion at some time after 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> of intermittent HPCI operation needs to
be considered. Prior to considering the plant level response, it is appropriate to take a close look
at the cumnt BSEP design basis for the instrument in question.
The original licensing bssis for the switch did not provide an explicit descripien of the plant IeVd
condtions as&wiated with actustion. It simply indicated that the switch would actuate on 10W
CST level to onsure that an adequate supply of makeup water is available to the HPCI pump.
The original licensing basis for the switch went with an original design basis that specified the
nominal trip setpoint be at a value that corresponds to 10,000 gallons capacity. The
documekd design basis did not specify a flow rate and it did not specify the refmnce point foF
the capacity. The documented design basis also did not link this setpoint to any stroke time
limits on the WPCI suction valves. There is no indication that a margin for unccrtsdnties such 86
temperature effects, suction vortexing, seismic concerns, e&. had to be Considercd.
Aftcr evaluating OE item PS 5 109, BSEP changed the design basis for the switches in 1997. The
combination of ESR 97-WO26 and ceiculation 0E41-1001 documented that setpoint was
acceptable when continuous HPCI plus RCIC oQeraticn at 4700 gpm considered This
determination WBS made based on engineering judgment. The stroke time limits for the HPCi
9164973W14
O C T - % 9 - 4 0 0 3
83:46
P M
B R U H S W I C K R E G A F F
P. 2%
AR 106230-10 Operability Review
Page 13 ofu)
suction valves were also updated and linked to the transfer function. UncesOainties were
ewssed.
Dudng an intarnal system review in 1999, it w a determined that a more defendable basis for the
vottex aspect of setpint WEIS needed and AR 5402 was generated. ESR 01-00322 was issued in
2001 88 a c k c t mult of this AR. ESR 01-QO322 updated the switch design as allowed by
1QCFR5Q.59 and was issued in accordance with CB&L procedures foe a design c h g e . The
EX noted that the Hpcl system level functional requirements did not include actuation of the
switch at the flow rates pnviousty consi&d. It documented that the highest applicable event
respnsc flow rate requirement far WCI was approximately Io00 gpm. It noted that the HPCI
operating procedure instructs operators to adjust HPCI flow after stanup to mainfain stable
rcactw vessel levd within the normal range. It established that fer the HPCl system to be
operating at a high flow rate where significant air entrainment would occur due to the lack of
adequate reactor level control mmua! actions is conriderad non credible.
AK greater than 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> into an event where E
1
is pmviding the backup to RCIC function, it is
apppriate to Consider operam actions with respect to vessel level control. The following
guidance in the UBSAR is applicable to this discussion:
UFSAR 5.4.6 inclwdes:
Following any reactor shutdown, steam generation continues due to decay heat. hitidy,
the rate of stem $enemtion can be as much as six percent of rated flow. Thc s t e m
normally flow8 to the main condenser through the turbine bypass a,
if the emdenser is
isolated, through the relief valves to the suppression pool. The fluid removed from the
reactor vmsel either can be furnished entirely by the feedwater pumps or can be partially
funti6ked by the control rod drive (CRD)
system, which is supplied by the CRD feed
pumps. Lf makeup water is required to supplement these sources of water, the RCIC
turbine-pump unit either start?, automatically upon receipt of a reactor vewi low water
level signal (Bigurn 7.3.3-2) or is started by the operator from the Centhol Room by
fernot~ mmud controls. R e szme low level signal also energizes the high prcssun
coolant injection system. The RCIC system delivers its design flow approximately 30 8&c
after actuation.
WFSAR 6.3.2.8 System Operation includes the following:
The ECCS have been designed to atart automatically in the event of an accident that
threatens the adequacy of core cooling. Manual operations are required to Wntain long
term cooling.
The description that follows details the opedon of the systems needed to achieve initial
con m l h g followed by containment cmling and then followed by extended c m
cooiing for a long term plant shutdown for the case of a non-opcrable main feedwater
system. The manual operations deseribcd we generally similar to those s t q u i d in the
event of a LOCA. The discussion below also includes the operation ob the non-ECCS,
non-safety relate$ RClC system. This system is designed to operate dueng loss Of
feedwater events, but is not relied upon to mitigate any accidents.
P . 2 9
OCT-09-2003 03:46 P M
B R U N S W I C K R E G R F F
9 1 0 4 5 7 3 B 1 4
AR 186230-10 Operability Review
Page 14 of 20
Following 8. loss of feedwater and reactor scram, a low reactor water level signal ( h e 1
2) will automatically initiate a signei which places the HPCl and RCIC Systems into the
reactor coolant makeup injecrion mode, These systems will inject water into the Vemel
until a high water level signal automatically trips the system. Following a high reactor
water level trip, the HPCI and RCIC Systems will automatically ninitiate when =tor
water level agdn &creases to low water Level 2,
Later in WSAR 6.3.2.8, the discussion includes:
The aperator can manually initiate the C I and RCIC systems fmm the ConrrOl Room
befere the b e l 2 automatic initiation level is reached. ahe OperW3 has the Option of
manual control or automatic initiation and can maintain xactor water level by throttling
system flow rates.
The applicable operator actions asissodated with reacror vessel level mtrol level for the non
safety dated Backup to RCIC function iire the manual starting of HPCI, the adjusting of the
HBcl flow rate and the stopping of HPCI. The staning and stopping of WCI arc manual actions
that also kave associated automatic actions. # p c I does not have pin automatic feature to adjust
the flow rate to control vessel level within the procedurally specified 170 to 200 range.
NRC gddrmce wm reviewed with respect to Operator actions. As described in M C IN 97-78,
GL 41-18 rev. 1 states:
it is not appropriate to take cndit for manual action in place of automatic action f a
protection of safety limits to consider equipment operable. This does not preclude
opcpator action to put the plant in P safe condition, but operator action canna be a
substitute for automatic safety limit protec~im.
It is notable that the OL text was specifically far automatic safety limit protection and not any
automatic WtkiR s@ecifid in tkc FSAR or Technical Spccificatiorms.
Ttie text of IN 99-78 then goes on to quote the following from ANSI-58.8:
Nuclear safety-related operator actaons or sequences of actions may be p c r f a r m e d by an
operator only whepe a single operator crror of one manipulation does not Tesult in
exceeding the &sign requirements for design basis events.
Again the text rsfers to safety-relaled operator actions and not UFSAR described actions for a
non safety related function. The text of Cy 97-76 then goes on to discuss that it is pctentid%ly
acceptable to rely on operator actions, but that the requirements of 1WFR50.59 eppiy, and @or
NRC approval is applicable when an Unreviewed Safety Question (WSQ) is involved. A
IoCpR50.59 review of the changes of
the changes did not constitute a WSQ.
If it is desind to conservatively neglect the manual actions associated with starting and stowing
HPCI due 10 the associated automatic features, then the ESR 01-00322 design basis for the
switches yuire.8 that tRe manual action for adjusting the HPCI flow controller (&er flow in
automatic mc&
or speed in manual mode) is assumed ro reduce flow such that significant air
entrainment doe$ not occur.
01-00322 was performed and it was identified that
OCf--03--ZBB%
03:47
BM
B R U N S W I C K R E G FIFF
9104573014
P.30
AR 106230-10 Operability Review
Page IS of 20
Using JPGCXt01/PWR-19010 Equation 8, it was determined that 2% air entminment at cbe CST
nozzle would be expected at 3000 gpm when LI reaches 2.6. With m assumed average HPCI
flow of 3ooO gpm, the 2% entrainment would start at 1 I7 seconds afta level switch actuation.
With a 45 second transpoet time, significant air entrainment would not reach the HPCI pump
bedm the lf4 seconds suction tmnsfer is complete. With a flow rate requirement that will be no
mose than 400 gpm, it would be reasonable to assume that the injection flow rate would bc 3000
gpm or less for the last injection from the CST. This assumption is not contrary to any
regulatory guidance fer this non safety related function, is consistent with WSAR descriptions
for sptem operetion and is applicable given the switch desigo basis.
Regwdlcss of whether 01 not the manual actions of starting and stopping HFCI am credit4
these actions
very likely and need io be considered for completeness. Ef an operator decides
that he d~ not want to adjust the HPCI flow rate, he can maintain the specified vessel level by
npeatedy starting I%pCI at 2 170 and then securing MPCI at 5 ZOO whiIe leaving the flow
controller Bet for 4300 gprn. Operating history was reviewed &J undemnd the plant response to
a full flow cI[ injection. Only one HWI injection was found that was at full flow for l a g
enough to determine the expected plani response, As documented in AR 102456-10 Atta&ment
5, JJ Unit 2 HPCI scram response injection on 8/16/90 increased level from 123 to 153 in just
less than 60 seconds. This short response takes less time than would be first expected BB the
increase in indicated 8evd is caused by both the inventory mskeup md level swell cwRlsed by
the C I steam flow induced vessel pressure reduction. Since level increased 30 in 6Q seconds,
this is an a m a t e duration fer assumed RCIC backup HPCI full flow injections while
opemtom arc maintaining vessel level between 170 and 200.
A
h
4 horn, if 8.4300 gpm injection were tu Stan witk CST level at just above slevatkm 23
4,
air entrainment could stafl at L1= 5.3.7 inch based on JP(jc2QQ1/PWR-19010 Equation 6, (31
seconds into the injection, see Attachment 3 for details). It would require 62 seconds of HK.1
injection for air to travel the 228 to the pump, Since only 60 S W Q ~ ~ S
of injection is expscted,
no air will reach the pump.
Any postulated #pCI full flow rate injection for this case with CST level starting at just above
elevation 234 will result in no air reaching the pump during that speeific injection. The Wpcl
suction swap would then be completed prior to the next HPCI injection. This provides the
protection that is nw$ed to prevent continued HPCI operation with the suction l i d up M a
depktsd CST.
OCT--D?-2005
03:47
P N
B R U H S W I C K R E G F1FF
9104573614
8.31
AR 106230-10 Operability Review
Page 16 of 20
- HgCI is providing the Backup to RCIC function
h m p t MSIV ciosupe does nat occur
Opemton initiate suppression p o t cooling
. Opmtops eventually perform ve5sel level contd in accordance with preceduren
CI operation done wit! be considered as RCIC unavailability is part of the ease definition.
C I will auto start on low reactor warer level (LL2, 105). HPCI will trip when level reaches
the high m o r Ievel trip setpoint at 2W. bvel may continue to cycle between 105 an8 206
until such time that opereton have had time to assess plant conditions and complete any ether
more important actions. Manual actions to controi level in specified 170 to 2QO kvel control
band would probably take place early in the event. However, it is not needed to sssurne them
actions until after 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> into the event.
This event dws not involve a small break LOCA, but it may involve a loss of CrOyweH cdlng.
Drywell heating and pressurization to above 2 psig may or may not occur. Operators would
place a! lewt one loop of RHR in suppmsion pool cooling at f 0 minutes. With RHR in
suppreasion pool cooling snd the reactor not depressurized via SRV6, suppression pool
tempemtiares would not inmase to a value where overriding the WCI high suppression poot
level transfer Insmmmtation is allowed. Note that if RHR suppression p
l
coaiing is not
started, WCI would eventually be o p t i n g with the suctien lined up to the suppssim pod
and the suppmsim pool water temperature above the value allowed for C I operation,
Continued operation of HPCI tends to depressurize the vessel BS it removes steam from the
reactor and 88 it inject8 low temperature water into the vesscl. Although it ia possible that
continued HPGI operation could reduce vessel pressufe to below the C f isolation setpoint
prior to any automatic suction transfer for small breaks, this is not expected for the case being
considered here.
Much of the coolant leaving the vessel will be discharged to the main condenser in this cwe.
One potential initiator for this event would be a loss of condensate system pnssurc boundary
inte@ty ar loss of condensate sysrern flow path. For this case it is appropriate to assume that
the high suppmsim pool KPCI level instrument setpoint is not reached prior to the CST
depletion that would be expected after 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> into the event.
AH p m e t e r s aasoeisted with the suctim transfer are the s m e as for Case 3. Either the IPCI
flow rare would be reduced acceptably or HPCI wouid be operated at full flow for Only 60
seconds. For the full flow cwe, no air would reach the pump during the last injection with 6ST
suction and the HPCK suction swap would then be completed prior to the next Hp(31 injetion.
This provides the protection that is ncedd to prevent continued HpeI opratim with the sUCtiim
lined up to a depleted em.
-~
'
KICT-09-2B83
0 3 : 4 8
PPI
B R U N S W I C K R E G BFF
9 1 0 4 5 7 3 0 1 4
AK 106230-10 Operability Review
Page I7 of 28
mere are no specific limitations. As long as operators comply with p e d u r e requirements as
they m gained to do, ?he setpoint is adequate to supp~fl the PfPCI licensing basis functions and
can be consided operable with no compensatory actions.
Technical Specification 3.5.1, Table 3.3.5.1
Technicd Specification B
w
B 3.3.5.1
WSAR 5.4.6,6.2.2.3,6.3.1.2.1.6.3.2.8,6.3.3.5.5,9.2.6.2
EGR-NGGe-0019,
Engineering Operability Assessment
N]RC Inspection Manual, Part 9900: Technical Guidance §TSlOO.II% and sm
100P.STS
h%C Infomath Notice 97-76 dated 10/23/97: Crediting of Operator Actions in Place
of Automatic Actions and Modifications of Operator Actions, Including Response Times
rev. 1
- SAE.WGE§TR-LOQcA Analysis Submittal, dated March 29 1989
h?ZW31624P. Brunswick Steam Electric Plant, Units II & 2. SAFBWOESTR-LOCA
hsa-sf~Qulanr Accident Analysis
S W G E S T R - L W A Analysis Response to Request For Additional Infomation, datal
May 17,1989
NRC approval ledter and SER for SAFEWGESTR-LOGA ANALYSIS, BRUMSWICK
STEAIW ELECTRIC PLANT, UNITS 1 AND 2, dated lune 1.1989
m Bmnswick Unite 1 and 2 Extended Power Wprate submittal dated O8/09101
- NEDC-33039P, 'Ke Safety Analysis Report for Brunswick Units 1 and 2 Extended
Power Wprate
- Ex&
Pwcr Uprate Kcspensc to Request For Additionel Infomation, dated 03/12@2
c m2001/BwR-19010
0 rn-02626
AB102456
- ESR 95-61733 Rev. 0 AI 15
BSR99-00062
P . 3 2
O C l - - B 9 - - 2 0 0 3
0 S 1 : 4 8 P M
B R U N S W I C K R E G FlFF
9 1 0 4 5 7 3 8 1 4
P . 3 3
AR 106230-10 Operability Review
Page 18 of 20
Attachment 1
General inputs of CST volume determinations are as
foollows:
input
Tank OD from
Tank shell thickness, 1st ring
Tank shell heigth, 1st ring
Tank shell thickness, ring 2, 3 & 4
t-tPCVRC!C nozzle (N-1) centerline
HkCt/RCi6 nozzle (N-1 j thickness
HPCVRCIC nOZle (N-1) SIZ&
HPGllRClC noule (N-1) ID
Volumes to specific levels
Normal Low bevel per OP 31 2
Level needed for routine OPT-09.2
01-03.6 & UFSAR 9.2.6.2 req'd level
Nominal drain down via CRD
MZ (CR[a/cond) i% N9 [CS)
Nozzel bottom
Top of first ring
HPCI lnstr Max Setpoint adjusted for AR 102466102466
HPCI lnstr Nom Setpoint adjusted for AB 102456
HBCl lnetr Min Setpoint adjuijlasted for AW 102456
HPCl lnlstr T/S adjusted for AR 102456102456
RCIC lnstr Max Setpoint adjusted for AR 102456102456
RCIC lnatr Nom Setpoint adjusted for Af? 102456
RCIC lnstr Min Setpoint adjusted for AR 102456102456
8616 lnstr TIS adjusted far AR 102458102458
HPCilRClC Sucd Top
HPCllRC1C Suct
Centerline
APP UA-04 5-7
Source
FP 2626
FP 2626
FB 2626
FP 2626
FP 2626
FP 2628
FP 2626
FP 2626
Height
(in)
40.0
39.5
39.0
38.5
36.0
35.5
35.0
34'5
31.5
24.0
Height
(ft)
23.50
20.00
12.00
10.00
9.50
9.38
7.75
3.333
3.292
3.250
3.208
3.000
2.958
2.81 7
2.875
2.625
2.000
Value
52 ft
0.279 in
7.75 ft
0.25 in
2ft
16 in
0.5 in
15 In
Volume Volume
(e%) (gallons)
49,824 372712
42,403 317198
25,441 190310
21,208 158588
20,140
1 50667
16,428 12295O
7,066
52860
6,978
52205
6,890
52539
6,801
50878
6,360
47574
6,271
46914
6,183
46253
6,095
45592
6,566
41628
4,240
31716
19,875 i
481375
Note distances above are referenced to the tank bottom at plant eievarlon 20'
1.5'
bl from fop of nozzle ID to HPCl Tech Spec 7.0
Volume, 10' to HPCl max setpoint
14,134 155727
Volume, 1 0 to HPCI Tech Spec
14,389 107710
Volume, 23.s' to HPCl Tech Spec
43,023 321834
Volume, 20 to HPCl Tech Spec
35,602 266320
Volume, 16' to HPCI Tech Spec
27,221
202876
.-*.I
-
9 1 84 5 7 38 1 4
,
OCT--89--2BE3
03:49 PPl
B R U N S W I C K REG R F F
AR 106230-10 Operability Review
Page 19 of 20
Attachment 2
EBB 6541733 Rev. 0 AI 15 was used to document the HPCI Suppression Pool HI Level
Instment bwis. The values and methods of this document were used to determine the
Containment Inventory increase assuming small break, HPCI plus RClC operation at
4700 gpm until the HPCl Suppression Pool Hi auto transfer Tech Spec level of -24" Is
react4 assuming no operator actions.
With Torus level starting at
The Torus inventory wouM be
With Torus level ending at
The Torus inventory would be
Torus inventory increase
~iyweil spill over volume (rnax. no misc structures)
E n d w d volume
Plui sump volume
Minus pedestal
volume
Total Injection volume
Or
HPCi injection flow rate
Minimum standby total inventwy in CST (1 0')
Tank volume at Hi Torus Transfer start
Tank afeR near bottom
Tank Level at HI Torus Transfer
Or
Top of HPCi nozzle ID (FP-02826)
Nozzle subinergence (U )
Ushg llmithg wive stroke rimes and no credit for flow r$duction prim to
end cf valve travel the level duction for the transfer will be 85 fOllOWS:
E41-F041/!%42 stroke tlme
TOM transfer time
HPCl flow durlng transter
C ~ T
wlurne at end d valve motion
Tank Level
Nozzle submergence (U)
E41 -F004
EilrOk8 flille
- 31 in
87140 eu ft
-24 in
9a90 cuft
43160 gallons
5770 cun
7306 GU R
loo CUB
585 cuft
m1 cuft
l a 1 1 CUR
94330 gal
4700 QPm
158588 gallcns
84257 gallons
8599 ft*
2120 w2
48.83 in
31.50 in
17.13 In
4.05 ft
70 8Bc
76 8 s
154 see
12063 galllons
52194 gallon8
6978 w
39.50 in
8.00 In
P . 34
AR iOg230-10 Operability Review
0
1
2
3
Q
$0
11
12
19
16
16
16
$7
18
.~
18
20
21
22
l.1
7.00
8.95
8.88
8.84
8.78
8.73
6.87
6.67
6.81
6.48
8.34
6,'ZLl
8.24
8.18
8.13
&OB
6.M
5.87
5.91
8.86
6.81
6.75
5.64
6.88
6.53
5.48
8.43
5.37
5.52
5.26
6.21
5.16
6.W
5.05
4.w
4.84
4.88
4.e3
4.77
4.72
4.67
6.81
4.63
4.69
1.43
b.38
424
4.29
4.23
4.18
4.12
4.07
6.01
3.98
3.91
3.86
3.W
I M )
3 . a
8.82
e.@
8.m
3.80
Pa¶
1
1
1
1
1
I
1
1
1
1
1
1
1
1
9
1
1
1
1
1
1
1
1
1
I
11
1
?
1
1
1
1
1
1
1
1
1
1
t
1
FWA
vel
7 . g
722
7.22
7.22
7.22
7.22
7.22
7.22
7.22
7.22
7.22
7.22
?.?.E
7.22
7.22
7.22
7.22
7.22
7.11
7.22
7.22
7.22
7 . P
7.22
7.21
7.22
7.22
7.22
7.92
7.22
7.22
7.22
7.22
7.22
7.21
9.22
7.72
7.22
722
?.a
7.22
7.22
722
7.22
7.22
7.7.2
7.22
7.22
7.22
7.22
7.22
7.8
7 . a
722
7.22
7.22
7,zz
7.22
7.22
7.E
7.22
72.2
7.22
FO42
POS
0 . m
0.013
Q.028
0.038
0.061
0.064
0.0V
0.080
0.103
0.115
0.128
0.141
0.154
0.187
0.179
0.1%
0305
0.218
0.Pl
0.244
0.288
0 . m
0.2W
0.308
0.321
0.333
0.346
0.358
0.372
0.386
0.M
0.410
0.423
0.436
Q.448
0.462
0.474
0.447
0.903
0.513
0.528
0.538
0.681
0.664
0.477
0.580
0.m
0.816
0,m
0.641
0.654
0 . W
0.879
0.692
a.ms
8.718
0.73t
0744
0.75e
0.789
0.782
8.7115
0.258
Air
DlSt ffl)
?
14
22
28
38
4a
51
50
55
72
78
87
Bl
1Qd
1 08
1t6
123
130
13?
$44
152
18%
186
173
160
186
9%
202
208
217
224
291
91045930114
Page 20 of 20
P. 35