MONTHYEARJAFP-05-0005, December 2004 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant2005-01-12012 January 2005 December 2004 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant JAFP-04-0186, November 2004 Monthly Operating Report for James A. FitzPatrick2004-12-0707 December 2004 November 2004 Monthly Operating Report for James A. FitzPatrick JAFP-04-0181, October 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-11-10010 November 2004 October 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0166, September 2004 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant2004-10-11011 October 2004 September 2004 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant JAFP-04-0150, August 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-09-14014 September 2004 August 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0122, July 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-08-0606 August 2004 July 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0100, June 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-07-12012 July 2004 June 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0086, May 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-06-14014 June 2004 May 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0066, April 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-05-0707 May 2004 April 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0035, February 2004 Monthly Operating Report for James a FitzPatrick2004-03-10010 March 2004 February 2004 Monthly Operating Report for James a FitzPatrick JAFP-04-0024, January 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-02-12012 February 2004 January 2004 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-04-0004, December 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2004-01-12012 January 2004 December 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0169, November 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2003-12-0808 December 2003 November 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0154, October 2003 Monthly Operating Report for James a FitzPatrick2003-11-0707 November 2003 October 2003 Monthly Operating Report for James a FitzPatrick JAFP-03-0139, September 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2003-10-14014 October 2003 September 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0130, August 2003 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant2003-09-15015 September 2003 August 2003 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant JAFP-03-0115, July 2003 Monthly Operating Report for James A. FitzPatrick2003-08-12012 August 2003 July 2003 Monthly Operating Report for James A. FitzPatrick JAFP-03-0097, June 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2003-07-0909 July 2003 June 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-03-0083, May 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant2003-06-12012 June 2003 May 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant JAFP-03-0067, April 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant2003-05-15015 May 2003 April 2003 Monthly Operating Report for James A. Fitzpatrick Nuclear Power Plant JAFP-03-0068, March 2003 Monthly Operating Report for James A. FitzPatrick, Revision 12003-05-14014 May 2003 March 2003 Monthly Operating Report for James A. FitzPatrick, Revision 1 JAFP-03-0050, March 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2003-04-14014 April 2003 March 2003 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-03-0043, February 2003 Monthly Operating Report for James A. FitzPatrick2003-03-17017 March 2003 February 2003 Monthly Operating Report for James A. FitzPatrick JAFP-03-0022, January 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2003-02-14014 February 2003 January 2003 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-03-0004, December 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2003-01-15015 January 2003 December 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-02-0225, October 2002 Monthly Operating Report for FitzPatrick, Rev 12002-12-12012 December 2002 October 2002 Monthly Operating Report for FitzPatrick, Rev 1 JAFP-02-0226, November 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant2002-12-12012 December 2002 November 2002 Monthly Operating Report for James A.Fitzpatrick Nuclear Power Plant JAFP-02-0211, October 2002 Monthly Operating Report for James A. FitzPatrick2002-11-12012 November 2002 October 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0199, September 2002 Monthly Operating Report for James A. FitzPatrick2002-10-14014 October 2002 September 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0186, August 2002 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant2002-09-13013 September 2002 August 2002 Monthly Operating Report for James a FitzPatrick Nuclear Power Plant JAFP-02-0164, July 2002 Monthly Operating Report for James A. FitzPatrick2002-08-12012 August 2002 July 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0142, June 2002 Monthly Operating Report for James A. FitzPatrick2002-07-15015 July 2002 June 2002 Monthly Operating Report for James A. FitzPatrick JAFP-02-0126, May 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-06-13013 June 2002 May 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0107, April 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-05-13013 May 2002 April 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0086, March 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-04-15015 April 2002 March 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0064, Revised November 2001 Monthly Operating Report for James A. FitzPatrick2002-03-15015 March 2002 Revised November 2001 Monthly Operating Report for James A. FitzPatrick JAFP-02-0063, February 2002 Monthly Operating Report for FitzPatrick Nuclear Power Plant2002-03-15015 March 2002 February 2002 Monthly Operating Report for FitzPatrick Nuclear Power Plant JAFP-02-0036, January 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-02-14014 February 2002 January 2002 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant JAFP-02-0008, December 2001 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant2002-01-15015 January 2002 December 2001 Monthly Operating Report for James A. FitzPatrick Nuclear Power Plant 2005-01-12
[Table view] |
Text
Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
James A. Fitzpatrick NPP P.O. Box 110 Entergy Lycoming, NY 13093 Tel 315 349 6024 Fax 315 349 6480 T.A. Sullivan Vice President, Operations-JAF May 13, 2002 JAFP-02-0107 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station O-Pl-17 Washington, D. C. 20555
SUBJECT:
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Monthly Operating Report
Dear Sir:
Enclosed is the Monthly Operating Report for the James A. FitzPatrick Nuclear Power Plant for the month of April 2002.
If there are any questions concerning this report, please contact Sherard Anderson, Thermal Performance Engineer, (315) 349-6558.
V ~yolu 4 IAL-4OLI T. A. SULLIVAN TAS:B .RD:SA:tmb Enclosure Xxy
cc: Regional Administrator U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. Guy Vissing, Project Manager Project Directorate I Division of Licensing Project Management U.S. Nuclear Regulatory Commission Mail stop OWFN 8C2 Washington, DC 20555 JENG JAFP Files RMS (JAF)
RMS (WPO)
ENTERGY NUCLEAR NORTHEAST JAMES A. FITZPATRICK NUCLEAR POWER PLANT OPERATING DATA REPORT REPORT MONTH: APRIL 2002 Docket No.: 50-333 Unit Name: FitzPatrick Date: May 6, 2002 Completed By: S. Anderson Telephone: (315)349-6558 OPERATING STATUS
- 1. Unit name: FitzPatrick
- 2. Reporting period: 4/01/2002 - 4/30/2002
- 3. Licensed thermal power (MWT): 2536
- 4. Nameplate rating (gross MWE): 883.0
- 5. Design electrical rating (net MWE): 816
- 6. Maximum dependable capacity (gross MWE): 839
- 7. Maximum dependable capacity (net MWE): 813
- 8. If changes occur in capacity ratings (Items 3-7) since last report, give reasons:
- 9. Power level to which restricted, if any (net MWE):
- 10. Reasons for restrictions, if any:
NO. DATA REQUESTED THIS YR-TO-DATE CUMULATIVE MONTH 11 Hours in reporting period: 719 2,879 234,575 12 Number of hours reactor was critical: 719 2,879 176,039.1 13 Reactor reserve shutdown hours: 0.00 0.00 0.00 14 Hours generator on-line: 719 2,879 170,900.9 15 Unit reserve shutdown hours: 0.00 0.00 0.00 16 Gross thermal energy generated (MWH): 1,812,454.4 7,216,874.7 388,946,384.3 17 Gross electrical energy generated (MWH): 621,950 2,478,070 131,558,210 18 Net electrical energy generated (MWH): 602,105 2,399,380 126,744,150 19 Unit service factor: 100 100 72.86 20 Unit availability factor: 100 100 72.86 21 Unit capacity factor (using MDC net): 103.00 102.51 74.49 22 Unit capacity factor (using DER net) 102.63 102.13 66.21 23 Unit forced outage rate: 0.00 0.00 11.14
- 24. Shutdowns scheduled over next 6 months (type, date, and duration of each): Refuel Outage 15 October 7, 2002
- 25. If shutdown at end of report period, estimated date of startup: N/A
- 26. Units in test status (prior to commercial operation): FORECAST ACHIEVED Initial Criticality:
Initial Electricity:
Commercial Operation:
ENTERGY NUCLEAR NORTHEAST JAMES A. FITZPATRICK NUCLEAR POWER PLANT OPERATING DATA REPORT REPORT MONTH: APRIL 2002 Docket No.: 50-333 Unit Name: FitzPatrick Date: May 6, 2002 Completed By: S. Anderson Telephone: (315)349-6558 DAY NET AVERAGE DAILY DAY NET AVERAGE DAILY POWER LEVEL POWER LEVEL 1 842 17 841 2 842 18 745 3 843 19 818 4 842 20 840 5 843 21 840 6 843 22 841 7 843 23 841 8 842 24 841 9 842 25 841 10 841 26 840 11 842 27 840 12 842 28 839 13 842 29 840 14 842 30 840 15 842 31 16 842
REPORT MONTH: APRIL 2002 Docket No.: 50-333 Unit Name: FitzPatrick Date: May 6, 2002 Completed By: S. Anderson Telephone: (315)349-6558 NO. DATE TYPE DURATION REASON METHOD OF LICENSEE SYSTEM COMPONENT CAUSE and CORRECTIVE HOURS SHUTTING EVENT CODE CODE ACTION TO PREVENT DOWN THE REPORT RECURRENCE REACTOR NO.
.1 +/- ________ 1 1 __________ 1 _________________ 1 ____________ +/- 4. 1 F: FORCED REASON: METHOD: EXHIBIT G: Instructions for preparation of S: SCHEDULED A. Equipment failure (explain) 1. Manual data entry sheets for Licensee Event Report B. Maintenance or Test 2. Manual Scram (LER) file (NUREG-0161)
C. Refueling 3. Automatic Scram D. Regulatory Restriction 4. Continued E. Operator training and license examination 5. Reduced load F. Administrative 9. Other G. Operational error (explain)
H. Other (explain)
-t REPORT MONTH: APRIL 2002 Docket No.: 50-333 Unit Name: FitzPatrick Date: May 6, 2002 Completed By: S. Anderson Telephone: (315)349-6558 OPERATIONAL
SUMMARY
The FitzPatrick plant - with the exception of minor derates for rod adjustments - operated at or near rated power during the month of April 2002 except for the following:
- April 15, 2002 - 0901 The plant commenced a load reduction to 98% power to support installation of monitoring equipment and clamping of the scoop tube on the 'B' Reactor Water Recirculation pump speed controls. The plant was returned to full power at 1035.
- April 17, 2002-0355 The plant commenced a load reduction to 98% power to support restoration of 'B' RWR speed controls. The plant was returned to full power at 0432.
- April 18, 2002 - 0821 The plant commenced a load reduction to approximately 70% power to support a scheduled control rod sequence exchange and main turbine control valve testing. Work was completed at 1357 and power ascension began at 1400. The plant returned to full power at 1720 on April 19. The total duration of this load reduction was slightly less than 33 hours3.819444e-4 days <br />0.00917 hours <br />5.456349e-5 weeks <br />1.25565e-5 months <br />.