Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Implementing Procedure Update
ML18292A714
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/04/2018
From: Ginn M
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
DCL-18-077, DIL-18-013
Download: ML18292A714 (2)


Text

Pacific Gas and Electric Company...,

Michael A. Ginn Diablo Canyon Power Plant Manager P.O. Box 56 Emergency Planning Avila Beach, CA 93424 805.545.3446 Internal: 691.3446 Fax: 805.545.6265 October 4, 2018 PG&E Letter DCL-18-077 PG&E Letter DIL-18-013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Docket No. 72-26, Materials License No. SNM-2511 Oiablo Canyon Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update

Dear Commissioners and Staff:

Pacific Gas and Electric Company (PG&E) submitted PG&E Letter DCL-18-074/DIL-18-012, "Emergency Plan and Implementing Procedures Update,"

dated September 26, 2018, in accordance with 10 CFR 50.54(q)(5) and the

  • requirements of 10 CFR 72.32, providing the NRC with changes made to the E_mergency Plan without prior NRC approval. That submittal provided the most current revision (Revision 5.02) of DCPP's Emergency Plan, Appendix D.

This letter includes, for information, Revision 5.00 of the Emergency Plan Appendix D "Emergency Action Level Technical Basis Manual," which was approved by the NRC in License Amendments 231 and 233. This manual is provided in the*

Enclosure. =

This submittal does not contain any privacy and proprietary information in accordance with NRC Generic Letter 81-27, "Privacy and Proprietary Material in Emergency Plans."

PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter. . *'"' ***

If there are questions regarding this submittal, please contact me at (805) 545-3446.

A-x45

u/ll~szi rJ/. . t-A member of the STARS Alliance 1UfVI ~>

Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

\

Document Control Desk PG&E Letter DCL-18-077 October 4, 2018 PG&E Letter DIL-18-013 Page2 Sincerely, Michael A. Ginn Emergency Planning Manager armb/4743 Enclosure cc/enc: William C. Allen, NMSS Project Manager Kriss M. Kennedy, NRC Region IV Administrator ChristopherW. Newport, NRC Senior Resident Inspector Balwant K. Singal, NRC Senior Project Manager Senior Emergency Preparedness Inspector (RGN-IV/DR)

A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

Text

Pacific Gas and Electric Company...,

Michael A. Ginn Diablo Canyon Power Plant Manager P.O. Box 56 Emergency Planning Avila Beach, CA 93424 805.545.3446 Internal: 691.3446 Fax: 805.545.6265 October 4, 2018 PG&E Letter DCL-18-077 PG&E Letter DIL-18-013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Docket No. 72-26, Materials License No. SNM-2511 Oiablo Canyon Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update

Dear Commissioners and Staff:

Pacific Gas and Electric Company (PG&E) submitted PG&E Letter DCL-18-074/DIL-18-012, "Emergency Plan and Implementing Procedures Update,"

dated September 26, 2018, in accordance with 10 CFR 50.54(q)(5) and the

  • requirements of 10 CFR 72.32, providing the NRC with changes made to the E_mergency Plan without prior NRC approval. That submittal provided the most current revision (Revision 5.02) of DCPP's Emergency Plan, Appendix D.

This letter includes, for information, Revision 5.00 of the Emergency Plan Appendix D "Emergency Action Level Technical Basis Manual," which was approved by the NRC in License Amendments 231 and 233. This manual is provided in the*

Enclosure. =

This submittal does not contain any privacy and proprietary information in accordance with NRC Generic Letter 81-27, "Privacy and Proprietary Material in Emergency Plans."

PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter. . *'"' ***

If there are questions regarding this submittal, please contact me at (805) 545-3446.

A-x45

u/ll~szi rJ/. . t-A member of the STARS Alliance 1UfVI ~>

Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

\

Document Control Desk PG&E Letter DCL-18-077 October 4, 2018 PG&E Letter DIL-18-013 Page2 Sincerely, Michael A. Ginn Emergency Planning Manager armb/4743 Enclosure cc/enc: William C. Allen, NMSS Project Manager Kriss M. Kennedy, NRC Region IV Administrator ChristopherW. Newport, NRC Senior Resident Inspector Balwant K. Singal, NRC Senior Project Manager Senior Emergency Preparedness Inspector (RGN-IV/DR)

A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek