MONTHYEARL-24-004, Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007)2024-04-30030 April 2024 Independent Spent Fuel Storage Installation - Responses to NRC Requests for Additional Information on the Diablo Canyon Independent Spent Fuel Storage Installation License Renewal Application (Cac/Epid 001028/L-2022-RNW-0007) L-23-005, Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007)2023-08-10010 August 2023 Independent Spent Fuel Storage Installation License Renewal Application, Revision 1 (Cac/Epid No. 001028/L-2022-RNW-0007) L-22-003, Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation2022-03-0909 March 2022 Independent Spent Fuel Storage Installation - License Renewal Application for the Diablo Canyon Independent Spent Fuel Storage Installation L-22-004, Independent Spent Fuel Storage Installation, Biennial Submittal of Changes to Diablo Canyon Independent Spent Fuel Storage Installation Technical Specification Bases2022-02-16016 February 2022 Independent Spent Fuel Storage Installation, Biennial Submittal of Changes to Diablo Canyon Independent Spent Fuel Storage Installation Technical Specification Bases L-21-010, Independent Spent Fuel Storage Installation, Decommissioning Funding Plan2021-12-14014 December 2021 Independent Spent Fuel Storage Installation, Decommissioning Funding Plan L-21-003, Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report for 20202021-03-0101 March 2021 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report for 2020 L-20-003, Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report for 20192020-03-0202 March 2020 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report for 2019 L-18-013, Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Implementing Procedure Update2018-10-0404 October 2018 Independent Spent Fuel Storage Installation - Submittal of Emergency Plan Implementing Procedure Update L-17-014, Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update2017-12-21021 December 2017 Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update L-17-008, ISFSI - Emergency Plan Implementing Procedure Update2017-09-0707 September 2017 ISFSI - Emergency Plan Implementing Procedure Update L-13-009, Response to NRC Letter Dated May 20. 2013, Diablo Canyon Power Plant Independent Spent Fuel Installation Storage Inspection Report 05000275-13-008, 05000323-13-008, 07200026-13-001 of Notice of Violation2013-06-17017 June 2013 Response to NRC Letter Dated May 20. 2013, Diablo Canyon Power Plant Independent Spent Fuel Installation Storage Inspection Report 05000275-13-008, 05000323-13-008, 07200026-13-001 of Notice of Violation L-2011-512, Diablo Canyon, Submittal of 2010 Annual Discharge Monitoring Report2011-02-28028 February 2011 Diablo Canyon, Submittal of 2010 Annual Discharge Monitoring Report L-09-009, Response to NRC Request for Information Pertaining to Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) License Amendment Request 08-0012009-11-23023 November 2009 Response to NRC Request for Information Pertaining to Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) License Amendment Request 08-001 L-2009-517, Diablo Canyon - Receiving Water Monitoring Program 2008 Annual Report2009-04-30030 April 2009 Diablo Canyon - Receiving Water Monitoring Program 2008 Annual Report L-09-001, Independent Spent Fuel Storage Installation, Notification in Accordance with 10 CFR 72.80, Other Records and Reports, Prior to First Storage of Spent Fuel2009-01-30030 January 2009 Independent Spent Fuel Storage Installation, Notification in Accordance with 10 CFR 72.80, Other Records and Reports, Prior to First Storage of Spent Fuel L-03-008, Additional Questions Related to Supplemental Blasts & Explosions Responses to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application2003-06-13013 June 2003 Additional Questions Related to Supplemental Blasts & Explosions Responses to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application L-03-007, Supplemental Slope Stability Design Mitigation Features Information to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application2003-05-0606 May 2003 Supplemental Slope Stability Design Mitigation Features Information to Additional NRC Questions for Diablo Canyon Independent Spent Fuel Storage Installation Application L-02-010, Independent Spent Fuel Storage Installation Submittal of License Application Amendment 1 (TAC L23399)2002-10-15015 October 2002 Independent Spent Fuel Storage Installation Submittal of License Application Amendment 1 (TAC L23399) L-02-008, Independent Spent Fuel Storage Installation Supplemental General & Financial Information2002-06-0707 June 2002 Independent Spent Fuel Storage Installation Supplemental General & Financial Information L-02-006, Part 1 of 2, Diablo Canyon Independent Spent Fuel Storage Installation - Submittal of Diablo Independent Spent Fuel Storage Installation Safety Analysis Report Reference Documents2002-05-23023 May 2002 Part 1 of 2, Diablo Canyon Independent Spent Fuel Storage Installation - Submittal of Diablo Independent Spent Fuel Storage Installation Safety Analysis Report Reference Documents L-2002-528, (DCPP) Submittal - Receiving Water Monitoring Program 2001 Annual Report2002-04-30030 April 2002 (DCPP) Submittal - Receiving Water Monitoring Program 2001 Annual Report L-2002-526, Pacific Gas and Electric Company First Quarter 2002 Report on Discharge Monitoring at Diablo Canyon Power Plant2002-04-20020 April 2002 Pacific Gas and Electric Company First Quarter 2002 Report on Discharge Monitoring at Diablo Canyon Power Plant L-2002-514, 2001 Annual Report on Discharge Monitoring2002-02-28028 February 2002 2001 Annual Report on Discharge Monitoring L-2002-504, Third Quarter 2001 Report on Discharge Monitoring at Diablo Canyon Power Plant2002-01-17017 January 2002 Third Quarter 2001 Report on Discharge Monitoring at Diablo Canyon Power Plant 2024-04-30
[Table view] |
Text
Pacific Gas and Adam S. Peck Diablo Canyon Power Plant Electric Company* Site Vice President Mail code 104/6/605 P.O. Box 56 Avila Beach, CA 93424 805.545.6675 Internal: 691.6675 PG&E Letter DIL-22-004 ATTN: Document Control Desk Director, Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Materials License No. SNM-2511, Docket No. 72-26 Diablo Canyon Independent Spent Fuel Storage Installation Biennial Submittal of Changes to Diablo Canyon Independent Spent Fuel Storage Installation Technical Specification Bases
References:
- 1. PG&E Letter DIL-18-004, Biennial Submittal of Changes to Independent Spent Fuel Storage Installation Technical Specification Bases, dated March 1, 2018
- 2. PG&E Letter DIL-20-001, Biennial Submittal of Changes to Diablo Canyon Independent Spent Fuel Storage Installation Technical Specification Bases, dated February 25, 2020
Dear Commissioners and Staff:
Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) Technical Specification (TS) 5.1.1, Technical Specifications (TS) Bases Control Program, provides a means for processing changes to the ISFSI TS Bases. ISFSI TS 5.1.1.d states that changes to the ISFSI TS Bases shall be provided to the NRC on a frequency consistent with 10 CFR 72.48(d)(2), which specifies that the submittals be made at intervals not to exceed 24 months.
The purpose of this letter is to inform you that Pacific Gas and Electric Company (PG&E) has not made any changes to the Diablo Canyon ISFSI TS Bases (other than removal of revision bars) since the submittal in March 2018 (Reference 1).
The same information was also communicated in February 2020 (Reference 2).
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-
- 04) in this letter.
A me m b e r of the STARS Alliance C a l l a wa y
Document Control Desk PG&E Letter DIL-22-004 Page 2 If you have any questions regarding this submittal, please contact Mr. James Morris, Regulatory Services Manager, at (805) 545-4609.
Sincerely, Adam S. Peck February 16, 2022 Site Vice President Date rntt/50962769-03 cc: William C. Allen, NMSS Project Manager Neil H. Day, NRC Acting Senior Resident Inspector Samson S. Lee, NRC Senior Project Manager Scott A. Morris, NRC Region IV Administrator Diablo Canyon Distribution A me m b e r of the STARS Alliance C a l l a wa y