L-17-008, ISFSI - Emergency Plan Implementing Procedure Update

From kanterella
Jump to navigation Jump to search
ISFSI - Emergency Plan Implementing Procedure Update
ML17250A719
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 09/07/2017
From: Ginn M
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
DC L -17-079, DIL-17-008
Download: ML17250A719 (10)


Text

Pacific Gas ,and Electric Company.;9 Michael A. Ginn Diablo Canyon Power Plant Manager P.O. Box 56 Emergency Planning Avila Beach, GA 93424 805.545.6300 Internal: 691 .6300 Fax: 805.545.6265 September 7, 2017 PG&E Letter DC L-17-079 PG&E Letter DIL-17-008 U.S. Nuclear Regulatory Commission 10 CFR 50.54, 10 CFR 72 .32 ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Docket No. 72-26, Materials License No. SNM-2511 Diablo Canyon Independent Spent Fuel Storage Installation Emergency Plan Implementing Procedure Update

Dear Commissioners and Staff:

In accordance with 10 CFR 50.54, and including the requirements of 10 CFR 72.32 for the Independent Spent Fuel Storage Installation, Pacific Gas and Electric Company (PG&E) is providing a summary of the analysis of changes to Emergency Plan (E-Pian) Implementing Procedures EP RB-8, "Instructions for Field Monitoring Teams."

The associated enclosures are listed below:

Enclosure Title 1 Diablo Canyon Power Plant Emergency Plan Implementing Procedures, Revision Numbers for Emergency Plan Implementing Procedures 2 Summary of the Analysis of Changes to Emergency Plan Implementing Procedure EP RB-8, Revision 28, "Instructions for Field Monitoring Teams" PG&E evaluated the changes for a reduction in effectiveness, as defined in 10 CFR 50.54(q), and concluded that the changes do not reduce the effectiveness of theE-Pian, and that theE-Pian continues to meet the requirements in Appendix E to 10 CFR 50 and the planning standards of 10 CFR 50.47(b).

Therefore, prior NRC approval of the associated changes was not required.

PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.

A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

Document Control Desk PG&E Letter DCL-17 -079 September 7, 2017 PG&E Letter DIL-17-008 Page 2 If there are questions regarding this update, please contact me at (805) 545-3446.

  • _y_ A G---

Michael A. Ginn Emergency Planning Manager armb/4 743/50938177 Enclosures cc/enc: William C. Allen, NMSS Project Manager Scott A. Morris, NRC Region IV Administrator (Acting)

Christopher W. Newport, NRC Senior Resident Inspector Balwant K. Singal, NRC Senior Project Manager Senior Emergency Preparedness Inspector (RGN-IV/DR)

A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek

Enclosure 1 PG&E Letter DCL-17 -079 PG&E Letter DIL-17-008 DIABLO CANYON POWER PLANT EMERGENCY PLAN IMPLEMENTING PROCEDURES Revision Numbers for Emergency Plan Implementing Procedures

Enclosure 1 PG&E Letter DCL-17 -079 PG&E Letter DIL-17-008 DIABLO CANYON POWER PLANT EMERGENCY PLAN IMPLEMENTING PROCEDURES Proc. No. Rev. Title OM10.1D1 16 Maintaining Emergency Preparedness OM10.DC1 8 Emergency Preparedness Drills and Exercises EP G-1 44 Emergency Classification and Emergency Plan Activation EP G-2 50 Interim Emergency Response Organization EP G-3 59 Emergency Notification of Off-Site Agencies EP G-4 30 Assembly and Accountability EP G-5 14 Evacuation of Non-Essential Site Personnel EP OR-3 10 Emergency Recovery EP RB-1 8 Personnel Dosimetry EP RB-2 8 Emergency Exposure Guides EP RB-3 7 Stable Iodine Thyroid Blocking EP RB-4 5 Access to and Establishment of Controlled Areas Under Emergency Conditions EP RB-5 8 Alternate Personnel Decontamination Facilities EP RB-8* 28 Instructions for Field Monitoring Teams EP RB-9 15 Calculation of Release Rate EP RB-10 19 Protective Action Recommendations EP RB-11 14 Emergency Offsite Dose Calculations EP RB-12 11 Plant Vent Iodine and Particulate Sampling During Accident Conditions EP RB-14 9 Core Damage Assessment Procedure EP RB-14A 2 Initial Detection of Fuel Cladding Damage EP RB-15 15 Post Accident Sampling System EP RB-16 14 Operating Instructions for the EARS Computer Program EP R-2 34 Release of Airborne Radioactive Materials Initial Assessment EP R-3 9 Release of Radioactive Liquids EP R-7 17 Off-Site Transportation Accidents EP EF-1 53 Activation and Operation of the Technical Support Center EP EF-2 40 Activation and Operation of the Operational Support Center EP EF-3 44 Activation and Operation of the Emergency Operations Facility EP EF-4 20 Activation of the Off-Site Emergency Laboratory EP EF-9 12 Backup Emergency Response Facilities EP EF~10 17 Activation and Operation of the Joint Information Center EP EF-11 2 Alternate Emergency Response Facilities I Incident Command Post (ICP)

  • Revised Document Page 1 of 1

Enclosure 2 PG&E Letter DCL-17 -079 PG&E Letter DIL-17-008 Summary of the Analysis of Changes to Emergency Plan Implementing Procedure EP RB-8, Revision 28 Instructions for Field Monitoring Teams

Enclosure 2 PG&E Letter DCL-17-079 PG&E Letter D IL-17-008 Summary of the Analysis of Changes to Emergency Plan Implementing Procedure EP RB-8, Revision 28 Type of Change and Reason for Original Content, Revision 27 Content Change, Revision 28 Change Step 5.4 Step 5.4 Change #1 - Modified existing content.

Clarify the position in charge of authorizing Kl to 'on-site' field monitoring teams.

Potassium iodide (KI) should only be Potassium iodide (KI) should only be taken taken when authorized by the controlling when authorized by the Shift Manager (SM),

facility. Site Emergency Coordinator (SEC), or Additional evaluation detailed in the Emergency Director (ED). 50.54(q) 2017-29 screening evaluation.

Various Steps: Various Steps: Change #2 - Modified existing content.

- Changed all references of "E-140", -Changed all references of "E-140" to Changing the instruments to RadEye GXs "ASP-1", "HP 210", "HP 260", "HP 270" "count rate instrument" is a process change. Changing the and "H809C". references of the specific instruments

- Changed all references of "ASP-1" to used is an administrative change.

"dose rate instrument" Removed specific terminology for

-Changed all references of "HP 21 0" to Radiation Protection equipment to allow "shielded pancake probe" for implementation of RadEye GX

- Changed all references of "HP 260" to instruments in the FMT kits.

"pancake probe"

- Changed all references of "HP 270" to "dose rate probe"

- Changed all references of "H809C" to "Air Sampler" See 50.54( q) 2017-28 for further information on this change.

6.3.5 6.3.5 Change #3 - Modified existing content.

1 of 5

Enclosure 2 PG&E Letter DCL-17 -079 PG&E Letter DIL-17-008 Type of Change and Reason for Original Content, Revision 27 Content Change, Revision 28 Change lE you do not have a TLD and/or PED, lE you do not have a TLD and/or PED, Added additional information on how to THEN Self Issue and don a TLD, THEN Self Issue and don a TLD per EP RB- "self-issue" a TLD which is an AND Obtain a Personal Electronic 1, enhancement.

Dosimeter (PED), power on, and don AND Obtain a Personal Electronic Additional evaluation detailed in the near the TLD for accessible reading. A Dosimeter (PED), power on, and don near 50.54(q) 2017-29 screening evaluation.

job aid for PED operation is in FMT the TLD for accessible reading. A job aid for binder. PED operation is in FMT binder.

Step 6.4.1.c Step 6.4.1.c: Change #4 - Removed existing content.

Ensure the response switch is either in Step deleted The RadEye GX does this automatically the "slow" position (for measuring low and does not have a response switch.

gamma exposure rates) or "fast" position See 50.54(q) 2017-28 for further (for measuring high gamma exposure information on this change.

rates)- NOT in the "integrate" position.

Step 6.4.1.e Step 6.4.1.e Change #5 - Removed existing content.

Check that the high voltage is Step deleted The RadEye GX is pre-set to the proper approximately 900 volts. volts.

See 50.54(q) 2017-28 for further information on this change.

Step 6.4.1.f and 6.4.2.d Step 6.4.1.d and 6.4.2.d Change #6 - Modified existing content.  !

I Obtain the nominal 11JCi Cs-137 source Obtain the nominal 11JCi Cs-137 source jig The source is now located in both the on-jig from the FMT equipment cabinet in from the FMT kit. site and off-site FMT kits as opposed to Warehouse B or the drawer in the EOF the equipment cabinets.

FMT kit area. No additional evaluation is required.

Step 6.4.1.g Step deleted Change #7 - Removed existing content.

2 of 5

Enclosure 2 PG&E Letter DCL-17 -079 PG&E Letter DIL-17-008 Type of Change and Reason for Original Content, Revision 27 Content Change, Revision 28 Change Turn the instrument range selector switch The RadEye GX auto scales and does not to X1 have or need a range selector switch.

See 50.54(q) 2017-28 for further information on this change.

Step 6.4.1.i and 6.4.2.g Step 6.4.1.f and 6.4.2.f Change #8 - Modified existing content.

2. If the instrument does not meet the 2. lEthe instrument does not meet the Editorial change with no change of intent.

acceptance criteria, inform the FMT acceptance criteria, Reformatted and consolidated steps for Communicator and tag faulty instruments THEN perform the following: clarity.

or components to show they are out of service. a. Inform the FMT Communicator

3. Obtain another meter and repeat this b. Tag the faulty instruments or components I No additional evaluation is required.

operational check section. to show they are out of service

c. Obtain another instrument
d. Repeat step 6.4.1 (6.4.2).

Step 6.4.2.e: I Step 6.4.2.e: Change #9 - Removed existing content.

Turn the instrument range selector switch 1 Step deleted The RadEye GX auto scales, so no to X10 selector switch necessary.

See 50.54(q) 2017-28 for further information on this change.

New Content I Note for step 6.5.6: Change #1 0 -Added new content.

Perform a negative pressure check after A negative pressure check should be donning respiratory protection . performed whenever a respirator is donned. This requirement is referenced in OM6.1010 and is addressed in initial and 3 of 5

Enclosure 2 PG&E Letter DCL-17-079 PG&E Letter DIL-17-008 Type of Change and Reason for Original Content, Revision 27 Content Change, Revision 28 Change requal training. This step is added as a reminder and is not creating any additional requirements.

No additional evaluation is required.

Step 6.8.3 Step 6.8.3 Change #11 - Modified existing content.

Purge the air sample cartridge of noble !E not using a silver zeolite cartridge, THEN Purging noble gasses is not necessary gas purge the air sample cartridge of noble gas when using silver zeolite cartridges.

as follows:

Additional evaluation detailed in the 50.54(q) 2017-29 screening evaluation. : Off-Site Field Monitoring Attachment 1: Off-Site Field Monitoring Change #12- Modified existing content.

Locations Map Locations Map Updated and improved map.

No additional evaluation is required.

Old Map New Map : On-Site Field Monitoring Attachment 3: On-Site Field Monitoring Change #13- Modified existing content.

Locations Map Locations Map Updated and improved map.

No additional evaluation is required.

Old Map New Map : On-Site Field Monitoring Attachment 4: On-Site Field Monitoring Change #14 - Modified existing content.

Locations Descriptions Locations Descriptions Corrects the description of two on-site ESE A: 50 yards up on Hillside Drive road ESE A: 150 yards up on Hillside Drive, near FMT sample locations.

near ditch end of road No additional evaluation is required.

SEA: On Reservoir Road by ditch, east SEA: 50 yards up on Hillside Drive, near 4 of 5

Enclosure 2 PG&E Letter DCL-17 -079 PG&E Letter DIL-17-008 Type of Change and Reason for Original Content, Revision 27 Content Change, Revision 28 Change end of parking lot #8 drainage ditch Step 6.4.1.d Step 6.4.1.c Change #15 - Modified existing content.

Turn the instrument on and perform a Turn the instrument on and ensure there is The Rad Eye GX performs a battery check battery check - replace batteries if sufficient battery level - replace batteries if upon startup and periodically while in necessary. necessary. uses. The instrument will alert the user if new batteries are necessary.

See 50.54(q) 2017-28 for further information on this change.

Step 6.4.2.c Step 6.4.2.c Change #16 - Modified existing content.

Turn the instrument on and perform a Turn the instrument on and ensure there is The RadEye GX performs a battery check battery check - replace batteries if sufficient battery level - replace batteries if upon startup and periodically while in necessary. necessary. uses. The instrument will alert the user if new batteries are necessary.

See 50.54(q) 2017-28 for further information on this change.

5 of 5