Online Reference Portal for Review of Mitigation Strategies Submittal in Response to Order EA-12-049
ML13217A430
Person / Time
Site: Beaver Valley, Davis Besse, Perry
Issue date: 08/05/2013
From: Halnon G
FirstEnergy Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
EA-12-049, L-13-254, TAC MF0841, TAC MF0842, TAC MF0961, TAC MF0962
Download: ML13217A430 (2)


Text

76 South Main Street FhstEnergyNuclear Opetating Company Akron, Ohio 44308 August5,2013 L-13-254 ATTN: DocumentControlDesk U.S.NuclearRegulatory Commission Washington, DC 20555-001

SUBJECT:

BeaverValleyPowerStation,UnitNos.1 and2 DocketNo.50-334,LicenseNo.DPR-66 DocketNo.50-412,LicenseNo.NPF-73 Davis-Besse NuclearPowerStation DocketNo.50-346,LicenseNo. NPF-3 PerryNuclearPowerPlant DocketNo.50-440,LicenseNo. NPF-58 OnlineReference Portalfor Reviewof Mitioation StrateqiesSubmittalin Response to OrderEA-12-049 (TAC Nos.MF0841,MF0842.MF0961, andMF0962)

By letterdatedFebruary27,2013[Agencywide Documents Accessand Management System(ADAMS)AccessionNo.M113064A2431, FirstEnergyNuclearOperating Company(FENOC)submittedoverallintegrated plansin responseto OrderEA-12-049 (Mitigation Strategies) for BeaverValleyPowerStation(BVPS),UnitNos.1 and2, Davis-Besse NuclearPowerStation(DBNPS), andPerryNuclearPowerPlant(PNPP).

By letterdatedJuly3, 2013(ADAMSAccessionNo.ML13183A216), the Nuclear Regulatory Commission (NRC)staffrequested thatan onlinereference portalbe established to improvethe efficiency of the NRCreviewof thissubmittalanddescribed conditions for useof the onlinereference portal.The conditionsareto be maintained throughout the durationof the reviewprocess.The NRCstaffalsorequested written confirmation of agreement withthe termsandconditions.

FENOChasestablished the requested onlinereference portaland herebyagreesto the termsandconditions setforthin the July3,2013letter.FENOCalsounderstands that documentsnecessary to supportthe NRCstaffsafetyevaluation of the submittalwillbe identified by the NRCstaffandformallyrequested to be submittedon the NRCdocket.

BeaverValleyPowerStation,UnitNos.1 and2 Davis-Besse NuclearPowerStation PerryNuclearPowerPlant L-13-254 Page2 Thereare no regulatory commitments containedin this letter.lf thereare anyquestions or if additionalinformationis required,pleasecontactMr.ThomasA. Lentz,Manager-FleetLicensing, at 330-315-6810.

Sincerely, GregoryH. Halnon cc: Director,Officeof NuclearReactorRegulation (NRR)

NRCRegionI Administrator NRCRegionlll Administrator NRCResidentInspector (BVPS)

NRCResident Inspector(DBNPS)