L-04-113, Preparation and Scheduling of Operator Licensing Examinations, NRC Regulatory Issue Summary 2004-10

From kanterella
Jump to navigation Jump to search
Preparation and Scheduling of Operator Licensing Examinations, NRC Regulatory Issue Summary 2004-10
ML042360709
Person / Time
Site: Beaver Valley
Issue date: 08/17/2004
From: Pearce L
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
L-04-113, RIS-04-010
Download: ML042360709 (2)


Text

J?

-FENOC Beaver Vatley Power Station Route 168 FirstEnergy Nuclear Operating Company PO. Box4 Shippingport. PA 15077-0004 L. Williant Pearce 724-682-5234 Site Vice President Fax: 724-643-8069 August 17, 2004 L-04-1 13 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001

Subject:

Beaver Valley Power Station, Unit No. 1 and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Preparation and Scheduling of Operator Licensing Examinations NRC Regulatory Issue Summary 2004-10 The purpose of this letter is to provide the NRC with the response to NRC Regulatory Issue Summary (RIS) 2004-10 for Beaver Valley Power Station Unit No. 1 and Unit No. 2. The RIS requested licensees to voluntarily submit a response using NRC Form 536 to provide data for scheduling and preparation of operator licensing examinations. Please find enclosed NRC Form 536, which addresses our proposed operator licensing examination schedule for calendar year 2005 through 2008.

No new commitments are contained in this submittal. If there are any questions concerning this matter, please contact Mr. Larry R. Freeland, Manager, Regulatory Affairs/Performance Improvement at 724-682-5284.

Sincerel, Attachment c: Mr. T. G. Colburn, NRR Senior Project Manager Mr. P. C. Cataldo, NRC Sr. Resident Inspector Mr. S. J. Collins, NRC Region I Administrator rtoo)

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 07/31/2005 (5-2003) Estimated burden per response to comply with this voluntary Information collection request I hour. This Information collection Is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING OPERTOR ICENINGCommission, estimate to the Records Management Branch (T-6 E6). U.S. Nuclear Regulatory Washington. DC 20555-0001, or by Internet e-mail to Infocollects~nrc.gov. and to the Desk Officer. Office of Information and EXAMINATION DATA Regulatory Affairs, NEOB-10202. (3150-0131), Office of Management and Bud get. Washington. DC 20503. If a means used to impose an Information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person Is not required to respond to, the Information collection.

FACILITY NRC REGION Beaver Valley Power Station Unit No. 1 and Unit No. 2 Docket No. 50-334/50-412, DPR-66/NPF-73 Exams for 2005 are one each for Beaver Valley Unit 1 and Unit 2, scheduled for 2/05, there are no exams scheduled for 2007.

A. PROPOSED EXAMINATION PREPARATION SCHEDULE 2008 PROPOSED NUMBER CY 2005 CCY25 CY l CY ESTIMATED NUMBER OF LICENSEE-PREPARED 1 1 1 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS 0 0 000 0 0 B. INITIAL OPERATOR LICENSE EXAMINATIONS 6

PROPOSED NUMBER CY 2005 CY 200 CY 2008 NUMBER OF REACTOR OPERATORS 6 4 4 NUMBER OF SENIOR REACTOR OPERATORS - INSTANT 3 8 6 6 NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE 0 0 0 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 0 o 0 o PROPOSED DATES PRIMARY DATE 02/28/2005 02/27/2005 12/11/2006 12/15/2008 ALTERNATE DATE 01/15/2007 01/19/2009 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED CY 2005 CY 2007 NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBERDECEMBER ESTIMATED NUMBER OF CANDIDATES NRC FORMI 53 (5-203)

__ _ _ 1MBEI PRINTED ON RECYCLED PAPER