MONTHYEARL-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report L-23-055, Submittal of the Updated Final Safety Analysis Report, Revision 342023-05-23023 May 2023 Submittal of the Updated Final Safety Analysis Report, Revision 34 L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 L-23-053, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-04-14014 April 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-058, 180-Day Steam Generator Tube Inspection Report2023-03-27027 March 2023 180-Day Steam Generator Tube Inspection Report L-23-066, Annual Notification of Property Insurance Coverage2023-03-21021 March 2023 Annual Notification of Property Insurance Coverage L-23-036, Report of Facility Changes, Tests and Experiments2023-03-13013 March 2023 Report of Facility Changes, Tests and Experiments L-23-086, Response to Request for Additional Information for Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair2023-03-0404 March 2023 Response to Request for Additional Information for Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair L-23-087, Supplement to Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair (L-2023-LLA-0027)2023-03-0404 March 2023 Supplement to Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair (L-2023-LLA-0027) L-23-073, Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair2023-03-0101 March 2023 Emergency License Amendment Request for Technical Specification 3.5.2 Regarding One-Time Action for Valve Leak Repair L-23-016, Twenty-Eighth Refueling Outage Inservice Inspection Summary Report2023-02-21021 February 2023 Twenty-Eighth Refueling Outage Inservice Inspection Summary Report L-23-064, Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-02-21021 February 2023 Discharge Monitoring Report, (NPDES) Permit No. PA0025615 L-23-057, Energy Harbor Nuclear Corp Retrospective Premium Guarantee2023-02-20020 February 2023 Energy Harbor Nuclear Corp Retrospective Premium Guarantee L-22-193, Request for Exemption from Specific Provisions in 10 CFR 50 Appendix H2023-02-14014 February 2023 Request for Exemption from Specific Provisions in 10 CFR 50 Appendix H L-22-286, Supplement to Request for an Amendment to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time2023-02-14014 February 2023 Supplement to Request for an Amendment to Consolidate Fuel Decay Time Technical Specifications in a New Limiting Condition for Operation Titled Decay Time L-23-032, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Second Half of 20222023-01-23023 January 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Second Half of 2022 L-22-281, Discharge Monitoring Report (NPDES) Permit No. PA00256152022-12-16016 December 2022 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-246, Response to Request for Additional Information Regarding a Request to Consolidate Fuel Decay Time Technical Specifications to New LCO2022-12-0707 December 2022 Response to Request for Additional Information Regarding a Request to Consolidate Fuel Decay Time Technical Specifications to New LCO L-22-217, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152022-11-21021 November 2022 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-226, Emergency Preparedness Plan2022-11-0404 November 2022 Emergency Preparedness Plan L-22-222, Cycle 29-1 Core Operating Limits Report2022-10-31031 October 2022 Cycle 29-1 Core Operating Limits Report L-22-228, Independent Spent Fuel Storage Installation Changes, Tests, and Experiments2022-10-26026 October 2022 Independent Spent Fuel Storage Installation Changes, Tests, and Experiments L-22-200, Response to Request for Additional Information Regarding a 180-Day Steam Generator Tube Inspection Report Fall 2021 Refueling Outage2022-10-21021 October 2022 Response to Request for Additional Information Regarding a 180-Day Steam Generator Tube Inspection Report Fall 2021 Refueling Outage L-22-232, Withdrawal of a License Amendment Request Associated with Fire Protection Program Changes2022-10-21021 October 2022 Withdrawal of a License Amendment Request Associated with Fire Protection Program Changes L-22-238, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152022-10-20020 October 2022 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-227, Revised August 2022 Outfall 003 & 004 NPDES Discharge Monitoring Report (Dmr), Revised Daily Effluent Monitoring Report Forms for Outfalls 003 & 004 and Corrective Action Letter from Eurofins2022-10-0303 October 2022 Revised August 2022 Outfall 003 & 004 NPDES Discharge Monitoring Report (Dmr), Revised Daily Effluent Monitoring Report Forms for Outfalls 003 & 004 and Corrective Action Letter from Eurofins L-22-219, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152022-09-26026 September 2022 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-22-204, Submittal of Evacuation Time Estimates2022-09-0707 September 2022 Submittal of Evacuation Time Estimates L-22-137, Request for Fire Protection Program Changes2022-09-0606 September 2022 Request for Fire Protection Program Changes L-21-238, License Amendment Request for Addition of Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident2022-08-31031 August 2022 License Amendment Request for Addition of Analytical Methodology to the Core Operating Limits Report for a Full Spectrum Loss of Coolant Accident L-22-188, Response to Request for Additional Information Regarding Steam Generator Inspection Report- Fall 2021 Refueling Outage2022-08-22022 August 2022 Response to Request for Additional Information Regarding Steam Generator Inspection Report- Fall 2021 Refueling Outage L-22-191, Spent Fuel Storage Cask Registration2022-08-17017 August 2022 Spent Fuel Storage Cask Registration 2023-09-14
[Table view] |
Text
FENOC FENOC Beaver Valley Power
~~~~~~~~~~~~
Station 168 PO. Box 4 FirstEnergy Nuclear Operating Company Shippingport, PA 15077-0004 L. WYilliatm Pearce 724-682-5234 Site Vice President Fax: 724-643-8069 May 14, 2003 L-03-037 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001
Subject:
Beaver Valley Power Station, Unit No. 1 and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Reply to Request for Additional Information Regarding Risk-Informed Inservice Inspection Program Relief Request On July 24, 2002, the FirstEnergy Nuclear Operating Company (FENOC) submitted a relief request to allow implementation of a Risk-Informed Inservice Inspection (ISI)
Program as an alternative to the current ASME Section XI requirements for piping at Beaver Valley Power Station (BVPS) Unit 1 and Unit 2. The NRC, following an initial review of this submittal, issued a Request for Additional Information (RAI) on December 30, 2002, regarding the FENOC relief request. Information in response to the RAI (Items # 1 - 16) was submitted via letter L-03-016 dated February 18, 2003.
On February 6, 2003, a second RAI was issued by the NRC. A response to this additional issue (Item # 17) is enclosed.
There are no new regulatory commitments identified in this document. If there are any questions concerning this matter, please contact Mr. Larry R. Freeland, Manager, Regulatory Affairs/Performance Improvement at 724-682-5284.
L. William Pearce Enclosure c: Mr. T. G. Colburn, NRR Senior Project Manager Mr. D. M. Kern, NRC Sr. Resident Inspector 5(J Mr. H. J. Miller, NRC Region I Administrator
Enclosure 1 Reply to Request for Additional Information Regarding Beaver Valley Power Station (BVPS) Units 1 and 2 Risk-informed Inservice Inspection (RI-ISI) Program Relief Request The Request for Information, dated February 6, 2003, provided the following additional item to be addressed:
A. UNITS 1 AND 2
- 17. In the enclosure to the July 24, 2002, application, Table 3.7-1 indicates that the expert panel moved a number of piping segments that have risk reduction worth (RRW) values greater than 1.005 from high safety significant (HSS) to low safety significant (LSS) based on theirjudgement. For example, in Unit 1, Table 3.7-1 reports that the charging (CH) system has 26 segments with RRW greater than 1.005. The table also reports that, in the CH system, 7 segments with RRW between 1.005 and 1.001 were placed in HSS. This indicates that the total number of HSS segments is expected to be 26 plus 7, or 33 segments. However, the total number of HSS segments in the CH system is reported as 28. In the same table, the safety injection (SI) system is reported to have 34 segments with RRWs greater than 1.005 but a final of 30 Segments are defined as HSS. Similar examples can be identified in Table 3.7-1 for Unit 2.
The NRC staff recognizes that Topical Report, WCAP-14572, Revision 1-NP-A, allows the expert panel to use deterministic information to place segments with RRW values greater than 1.005 in the LSS category; however, page 143 of the topical report states that HSS "segments should not be classified lower by the expert panel without sufficient justification that is documented as part of the [RI-ISI]
program. The expertpanel should be focusedprimarily on adding piping to the higher classification." Justification for the reclassification of HSS segments to LSS should include a description of the specific characteristics that support the expert panel's decision that the safety-significance of the segment is lower than the results of the quantitative evaluation and guidelines indicate. Sufficient detail is also needed such that the impact of future plant modifications on the characteristics selected by the expert panel when determining the safety-significance can be systematically evaluated to ensure continued applicability of the assigned classification.
Based on a review of previous submittaIs, there are two types of results from the quantitative analysis that expert panels have modified in order to reclassify segments from HSS to LSS. These results involve: 1) human actions responding to the pipe failure; and, 2) material and operation characteristics of the segment.
In order to expedite the review of the July 24, 2002, application, the type of information required to support the NRC staff review is provided below.
Reclassifying a HSS segment as LSS is often based on discarding a "without human action" RRW when that RRW is the only RRW that is greater than 1.005.
This reclassification is based on a high degree of confidence by the expert panel (continued) that the operators could appropriately recover from the event. A basis for the decision would include a description of the information available to the operators to identify the failed functions, systems or component caused by the pipe failure; the procedures the operator would follow; the time available for the operator to recover; the time required by the operator to diagnose and recover the failed functions; and the equipment available to recover from or mitigate the failures.
Note that the ASME Standard for Probabilistic Risk Assessment (PRA) for Nuclear Power Plant Applications only discusses proceduralized actions and non-proceduralized, skill-of-the-craft actions for use in PRA.
Reclassifying a HSS segment to a LSS segment is often based on discarding the pipe frequency estimate that is, in tum, based on material or operational characteristics input into the Structural Reliability and Risk Assessment code. A basis for the decision should include an identification of those properties that resulted in the original HSS designation, the change in those properties that the expert panel determined more appropriately characterize the actual state of the structure, system, or component, and a discussion why the properties the expert panel developed are expected to reduce the safety-significance of the segments from HSS to LSS.
Therefore:
(a) Clarify if the expert panel reclassified segments from HSS to LSS and, if so, identify how many segments were reclassified from HSS to LSS.
(b) Provide the justification documented as part of your RI-ISI program for each segment (or group of segments if the justification may be grouped) that was reclassified from HSS to LSS. For example, some documentation should be in the expert panel's meeting minutes. If the documented justification does not include the information discussed above, please provide the level of justification discussed above.
BV Response:
The expert panel reclassified a total of 121 segments at BVPS (64 at Unit 1 and 57 at Unit 2). Thirty-five (35) segments were reclassified from high safety significant (HSS) to low safety significant (LSS). Eighty-six (86) segments were reclassified from LSS/MSS (medium safety significant) to HSS.
The majority of the downgraded segments were reclassified due to credible operator action. The expert panel documentation contains justification for each segment.
However, the documentation does not contain the detail requested, since WCAP-14572 did not require this level of detail. The level of detail needed for a sufficient justification is a generic issue that is currently being addressed by the Westinghouse Owners Group (WOG) and the NRC (Reference 1). A more detailed response to this RAI will be provided, as applicable, once the resolution of this generic issue is obtained.
(continued)
Reference:
- 1. Letter from Robert Bryan, Jr. (Chairman, Westinghouse Owners Group) to Samuel J. Collins (NRC), NRC Requests for Additional Information (RAls)
Associated with Plant Specific Applications of the Methodology in WCAP-14572-NP-A, Rev. 1, "Westinghouse Owners Group Application of Risk-Informed Methods to Piping Inservice Inspection Topical Report," dated April 21, 2003.