IR 05000528/1980022

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-528/80-22,50-529/80-22 & 50-530/80-22 on 801201-31.No Noncompliance Noted.Major Areas Inspected: Previous Insp Findings,Installed Reactor Vessels Protection & safety-related Piping Installation
ML17296B327
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 03/12/1981
From: Kirsch D, Vorderbrueggen
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17296B326 List:
References
50-528-80-22, 50-529-80-22, 50-530-80-22, NUDOCS 8104130496
Download: ML17296B327 (12)


Text

U.

S.

NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION V

Report No.

50-528/80-22 50-529/80-22 50-530/80-22 Docket Nos.

50-528, 50-529 50-530 License Nos.

CPPR-141 CPPR-142 CPPR-143'icensee:

Arizona Public Service Com an P.

0.

Box 21666 Phoenix, Arizona 85036 Facility Name:

Palo.Verde Nuclear Generatin Station

.Units',

2 and

Inspection at:

Palo Verde Construction Site, Wintersburg, Ar'izona Inspection Conducted:

December 1-31, 1980 Inspectors:

E.

or er ruegg Resident Reactor Inspector pproved by:

F. Kirsch, Acting hief, Reactor Projects

.

ection 1, Reactor Construction Projects Branch ate igne Hl ate 1gne Summary:

Ins ection"on'December'1-'31,'1980'(Re ort'Nos.'50-'528/80-'22; 50-, 529/80-22, and 50-530/80-22

.

~AI d:

R i, d i p

i by h

id

.i p

construction activities including:

followup on a previously identified item of noncompliance; protection of installed reactor vessels hand Unit ],reactor vessel internals; preparations for installation of Unit 1 containment tendons; verificqtion-of containment shell/basemat reinforcing steel for Units ] and 2; instal]ation of safety related piping; resolution of electrical cable tray separation concerns; care and preservation of equipment; and general activities in progress at the site.

The inspection involved 55 inspector hours on-site by one NRC inspector.

Results:

No items of noncompliance or deviations were identifie ) l\\

DETAILS 1.

Persons Contacted a.

Arizona Public Service Com an APS

  • E.

E.

Van Brunt, Jr., Vice President, Nuclear Projects Management

  • J. A. Roedel, Manager, guality Assurance
  • W. E. Ide, Site gA Supervisor G. Pankonin, gA Engineer R.

D. Forrester, gA Engineer

  • J.

M. Allen, Nuclear, Engineering Manager

  • A. C. Rogers, Nuclear Engineering Manager
  • B. S.

Kaplan, guality Systems Supervisor

  • D. B. Fasnacht, Site Construction Manager
  • R. D. Kimmel, Field Engineering Superyisor b.

Bechtel Power'Cor oration'(Bechtel

  • W. J. Stubblefield, Field Construction Hanager
  • D. R. Hawkinson, Project gA Supervisor
  • R. H. Grant, Project gC Engineer C. Nelson, Civil Engineer-Unit

L. Afek, Lead Hechanical Field Engineer R. Hedzi k, Lead gC Engineer-Mech/piping/NSSS W. Sears, gC Supervisor-Administration c.

Western Concrete'Structur'es,

Inc.

K. Guffey, General Superintendent T. Patel, gC Supervisor Other persons contacted during the inspection peri.od included construction craftsmen, inspectors and supervisory personnel.

  • Management meeting attendees.

2.

Licensee Action on Previous'ns ection Findin s 50-528/80-17 01 Closed

'Noncom liance:

Failure to rovide', rescribed maintenance on the motor o erators'for'the Unit main steam an ee water isolation valves The corrective action identified in the licensee's response, dated December 17, 1980, was reviewed and the subject valves were observed in their installed location.

Each valve was totally enclosed by a heavy plastic cover for protection from construction generated dust and dirt.

The inspector verified that the valves and their respective operators had been added to the plant equipment maintenance program and are now being maintained on a monthly basis.

The inspector also reviewed the measures that have been initiated by Bechtel to assure that the equipment maintenance list is complete and that items will not be inadvertently omitted in the future.

This item is close 'o s.

4.

Protection of Installed Reactor Vessels Guarded access control to the Unit 1 reactor pool area continues to limit the entry of personnel, equipment, tools and materials to those which are authorized.

When there is no work activity inside the vessel, a plastic protective cover is kept in place over the vessel flange to prevent the entry of foreign objects and debris.

Nozzle welding operations continued on the Unit 2 reactor vessel.

Nozzle openings not being worked are covered for protection from adjacent construction activities.

Work platforms and ladders inside the vessel are metallic or of treated wood so as to minimize fire hazards.

The top of the vessel is covered to prevent the accidental entry of foreign objects and debris.

The inspector found.that the procedures for protection of the installed reactor vessels were being implemented.

Unit 1 Reactor Vessel'Internals During this reporting period, work continued on the installation of the six sets of shims which attach to the sides of the six core stabilizing lugs on the lower wal,l of the reactor vessel.

These lugs mate with the snubber lugs on the outside diameter of the core support barrel.

The work is being performed. by Combustion Engineering, Inc. under subcontract to Bechtel, with workmen furnished by the Boilermaker craft.

The components are kept covered and protected except when work is actually progressing.

I It appeared to the inspector that the procedures for installation and protection of the vessels were being followed.

Unit 1 Containment Tendon'nstallation

The inspector met with site personnel of. Western Concrete Structures, Inc.,-the contractor for the contai,nment post-tensioning system, to assess their readiness to begin installation of the stressing tendons.

Their gA program and installation procedures have been reviewed and approved by Bechtel, but they have not yet hired the two additional 9C inspectors required to complete their staff.

The buttress traveling platforms are in place and had been operationally checked out.

The tensioning jacks (2) have been tested, but have not yet arrived at the site.

Plans were being finalized to pull in three horizontal tendons between buttresses 1 and 3 for the purposes of craft training and final checkout of the equipmen.

Safet Related Pi in Instal lation

~

~a.

Com onent Installation Activities The inspector observed various installation work activities associated with portions of the chemical and'olume control and safety injection systems at the C level of the Unit 3 auxiliary building.

Particular attention was given to the handling and supporting of system components, correctness of configuration, control of welding records in the work area, use of specified materials, control of weld filler metal, absence of defects on component surfaces, and inspection performance by qualified personnel.

The applicable requirements are specified in WPP/gCI 202.0 (Piping System Installation)

and Specification 13-PH 204 (Field Fabrication and Installation of Nuclear Piping Systems).

No items of -noncompliance or deviations were identified.

b.

In-rocess Weldin Activities The inspector examined two welds in Unit 3 toascertain compliance with requirements of the applicable specifications,'odes, standards, and procedures.

The welds were:

Fit up of Weld No.

W-001 joining spool 001 to motor operated valve HV-531 in line CH-A-424-20" - refueling water storage tank supply to safety injection pump train A.

Partially completed Weld No.

W-OQ6 joining spool, 004 to manually operated valve V-435 in line SI-A-087-10"-LPSI pump A discharge.

A properly filled out Field Welding Check List (WR-5 Form} was present at the work location of each weld with hold points and NDE call-outs specified.

The weld identification, material specifications, and interpass temperature were specified on the WR-5 Form.

The WR-5 provisions were in accordance with the requirements of the ASHE Code,

-Section III, 1974 edition.

Fil1er metal issue slips and,the qualification records of the welders involved were examined and found to be acceptable.

The inspector observed that quality control inspection and supervisory surveillance were being performed as required.

Wpp/OCI 101.0 (Welding Control) along with the two documents identified in paragraph 6.a above, contained the applicable work and inspection requirements for both welds.

No items of noncompliance or deviations were identifie Containment Shell Basemat Reinforcin Steel Reinforcing steel had been omitted from certain localized segments of the circumferential joint between the containment exterior wall and the basemat.

This omission occurred in all three Palo Verde units.

Circumstances associated with this situation were described in IE

Inspection Report

No. 50-528/80-13,

Paragraph

4.

The matter

was

verbally reported to Region

V by the licensee

on July 1,

1980

as

a potential

50.55(e)

item and their final written report 'was submitted

on November 6, 1980.

At the licensee's

request,

a meeting

was held

in the Region

V office on November 20,

1980 between

the licensee,

their technical

consultant

(Bechtel).and

NRC personnel.

The meeting

was intended to answer

any remaining questions

that Region

V personnel

might have about the physical situation,

and the nature

and validity

of. the analysis

which showed that the structural

adequacy of the

containment buildings had not been

compromised.

Since the licensee's

conclusion of structural

adequacy,

based

on the

licensee's

analysis,

rests

on the premise that the "as-built" steel

reinforcing in the area of interest

does

indee'd

conform to the

specified material

and configuration requirements,

the inspector

attempted to verify that fact through

a review of the relevant

installation documentation for the three units.

Documents

examined

included reinforcing steel material certifications,

cadweld splice

inspection reports,

cadweld splice tensile test repor ts, concrete

preplacement

checklists,

nonconformance

reports

and construction

progress

photographs.

The areas,

as designated

by the concrete

placement

numbers,

are

C012 and

C013 for the building basemat,

and

C100 for the

exterior wall.

(Each placement

number is preceded

by its unit number,

i.e.,

1C012 for Unit 1, 2C012 for 'Unit 2, etc.)

All reinforcing steel

was of the type specified

(pSTH./615

Gr'gde 60).

The cadweld splice

gC inspection reports

were in order and

showed

a reject rate less

than

1 percent (all rejects

were replaced}.

Cadweld

tensile test reports

showed

no breaks

below 90,000 psi - the majority

being in the range of 95,000 to 105,000 psi.

All concrete

preplacement

check lists identified no such descrepancies

and each

one listed the

noncomformance

reports pertaining to that placement.

All nonconforming

conditions identified in the reports had'een

corrected in 'accordance

with approved

measures.

The corrective actions

had

been

examined

and approved

by the assigned

gC inspectors.

The construction,. progress

photographs

displayed

no conditions that would indicate that the

installations

were deviating from the intended design.

From the documents

reviewed,

the inspector

concluded that the containment

basemat-exterior

wall junction,

on each of the three units,

had

been

built in accordance

with the design

document ~

s.

El ectri cal

Racewa

Se ar ati on

During surveillance

and audit activities

by the licensee's

site

gA personnel,

in connection with electrical

raceway installation,

it was found that clarification and additional details

were

needed

on the electrical

drawings in order to assure that the separation

requirements

of Regulatory

Guide 1.75 would be satisfied.

The inspector

discussed

this matter with the licensee

and reviewed the action taken

by Bechtel to assure that the installation will meet specified

requirements.

The Bechtel actions

included

a review of all drawings

and unique identification of all cable trays that must have covers

or barriers installed,

issuance

of a Design

Change Notice

(DCN 49)

to clarify separation

distance

requirements for conduit,

and reinspection

and walkdowns of installed raceway prior to signoff of the

EE580 raceway

installation card.

A new procedure

was also being developed pertaining

specifically to installation

and inspection of fire barriers,

tray

covers

and conduit sealing.

The inspector

had no further'questions

on this matter at this time.

9.

Plant Tours

Several

times during this reporting period the inspector toured the

plant site to observe

general

housekeeping

conditions

and the care,

handling

and preservation of equipment.

Particular attention.was

given

to: the handling of heavy pipe spools

and valves during welding fit-up;

presence

of covers over installed equipment for. protection from adjacent

work activities; adequate

caps

over pipe openings

not being worked on;

and adequacy of dunnage

under stored valves,

pipe spools

and other

components.

No welding electrode

stubs

were found lying around the

various work areas.

No deviations or items of noncompliance

were, identified.

10.

Mana ement Meetin

s

On December

5, 1980 and January

9,

1981 the inspector met with the

licensee

representatives

identified in Paragraph

1 to sgmmarize

the

scope of the inspection activities and revi'ew the inspection.findings,

as described in'his repor )

~/