IR 05000528/1979008
| ML17296A554 | |
| Person / Time | |
|---|---|
| Site: | Palo Verde |
| Issue date: | 12/21/1979 |
| From: | Dodds R, Vorderbruggen L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML17296A553 | List: |
| References | |
| 50-528-79-08, 50-528-79-8, 50-529-79-08, 50-529-79-8, 50-530-79-04, NUDOCS 8001280477 | |
| Download: ML17296A554 (16) | |
Text
U ~
S ~
NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT 50-528/79-08
REGION V
50-529/79-08 p
t N
50 530/79
CI'P R-143 Docket No. 50-528, 50-529, 50-530 License No, CPPR-141, CPPR-142, Safeguards Group Licensee:
Arizona Public Service Company P. 0.
Box 21666 Phoenix Arizona 85036 Facility Name:
P and
Inspection at:
Inspection conducted:
October 1-31 1979 Inspectors:
.
E. Vorderbrueggen, Re i nt Reactor Inspector
/Date igned Date Signed Approved By:
R. T. Dodds, Chief, Eng. Support Section Reactor Const.
Im Engineering Support Branch Date Signed ng D
e igned Ins ection on October 1-31, 1979 (Re ort Nos.'50-528 79-08; 50-529 79-08 an Areas Ins ected:
Routine, unannounced inspection of construction activities y the ress ent inspector including:
licensee action on previously identified items; Unit 1 diesel generator installation;. Unit 1 spray pond structure; Unit 2 control building concrete and underground electrical conduit; earth compaction for Unit 3 basemat; Unit 3 tendon gallery reinforcing steel and formwork; Unit 3 reactor pit liner; and miscellaneous work in progress.
The inspection involved 46 inspector hours on-site by one NRC inspector.
Results:
No deviations or items of noncompliance were identified during the inspection period.
RV Form 219 (2)
8 oo z 2o o.dj. V P
DETAILS 1.
Persons Contacted a.
Arizona Public Service Com an
- E. E.
Van Brunt, Jr., Vice President/Project Directop
- J. A. Roedel, Manager, guality Assurance bR.
L. Hand, Site gA Supervisor
- L. W. Price, Site Construction Manager R.
D. Forrester, guality Assurance Engineer N. S. Ruiz, guality Assurance Engineer N. E. Wibel, guality Assurance Engineer
- G. E. Pankonin, guality Assurance Engineer
- R. J.
Kimmel, Site Nuclear Construction Engineer b.
Bechtel Power Cor oration
- W. J. Stubblefield, Field Construction Manager
- D. W. Hawkinson, Project guality Assurance Supervisor
- C. E. Gaither, Assistant Project Field Engineer
- R. M. Grant, Project guality Control Engineer A. Becker, Field Engineer, Civil J.
L. Black, Resident Engineer W. Dubois, Field Supervisor J.
Copp, Laboratory Supervisor 8 - Denotes attendance at the Management Interview on October 19, 1979
- - Denotes attendance at the Management Interview on October 26, 1979 2.
Licensee Action on Previousl Identified Items On May 15, 1979, the licensee notified the Region V office via telephone of a potential 50.55(e) reportable item involving 2-inch and smaller carbon steel, socket weld type valves.
Cracking problems had been encountered in the weld root due to the presence of nickel plating applied by the valve manufacturer to the valve body, including the welding surfaces.
All valves with this nickel plating, 747 in number, were returned to the manufacturer for removal of the plating.
The inspector reviewed NCR No. P-X-477 and Deficiency Evaluation Report No. 79-6 covering this matter.
The licensee concluded that the situation was not reportable on the basis that any cracks would be confined to the weld root due to weld metal dilution, and any failures would be in the form of small leaks rather than guillotine-type breaks.
The inspector had no further questions on this matte.
Unit 1 Diesel Generator - Train A
The activities associated with transferring the Train A emergency diesel generator into the generator building and placing it on its foundation were observed by the inspector.
All operations appeared to proceed in a smooth organized fashion, and appropriate supervision of the riggers and millwrights workers involved in the operation was in evidence.
No items of noncompliance or deviations were identified.
4.
Unit
S ra Pond Structural installation activities of the Unit 1 spray pond were examined.
This included the reinforcing steel for the floor slab in the north-west quadrant, form placement for the south-west wall and the center separation wall, reinforcing steel placement for several piping support columns and the lower pump structure, and embed placement in several equipment support pads.
The governing specifications were 13-CN-365, Forming, Placing, Finishing and Curing of Concrete, and '13-CM-375, Placing of Reinforcing Steel.
The applicable drawings were 13-C-SPS-375 through -380, inclusive.
No items of noncompliance or deviations were identified.
5.
Unit 2 Control Buildin Concrete Conditions of severe rockpocketing, honeycoming, and voids around blockouts were found when the forms were stripped from placements 2J022 and 2J023.
These were wall sections in the southwest corner of the control building from elevation 100 to 120 feet.
The conditions resulted from improper consolidation in regions of heavy reinforcing steel congestion, and were documented on Nonconformance Report No. C-J-1542.
The inspector examined the affected areas and observed workmen chipping out the faulty concrete in preparation for making repairs, and later observed that all unacceptable areas had been properly excavated for the repair.
The inspector verified that repair procedures covering situations of..this nature are contained in Section 16.0 of Specification 13-CH-365, Forming, Placing, Finishing and Curing of Concrete.
The inspector had no further questions at this time.
6.
Unit 2 S ra Pond Under round Conduit Banks The inspector examined the placement of a portion of the two (redundant)
conduit banks which are embedded in concrete under the Unit 2 Control and Diesel Generator buildings and which serve the electrical equipment associated with the Unit 2 Spray Pond.
The conduit was being placed in a workmanlike manner using the spacers specified, all in accordance with the requirements specified on Drawing 13-E-ZAC-050, Conduit and Tray Notes, Symbols and Details.
No items of noncompliance or deviations were identifie.
Unit 3 Containment Reactor Pit Liner The completed floor and wall liner plate in the reactor pit for Unit 3 was examined by the inspector.
Numerous welds between the various plate segments, as well as the welds attaching the "B" Series cadweld sleeves to the floor plates, were examined'.
The inspector did not identify any items of noncompliance or deviations from the applicable specification No.
13-CM-370, Erecting the Containment Building Liner Plate System, and Drawings 13-C-ZCS-198 and -199, Reactor Pit Liner and Inserts.
8.
Unit 3 Tendon Galler
"
The reinforcing steel and formwork for the gallery outer wall segment from azimuths 120-degrees to 240-degrees was examined by the inspector.
The forms appeared to be properly tied and braced, with appropriate clearance to provide the minimum concrete cover for the reinforcing steel.
The steel was of the size and spacing specified on Drawing 13-C-ZCS-101, Reinforcing Plan - Reactor Pit and Gallery llalls, and was adequately tied to prevent movement during concrete placement.
The final structure appeared to be free from debris and ready to receive concrete (Placement 3C-0008).
No items of noncompliance or deviations were identified.
9.
Unit 3 Base Mat Earth Com action The inspector observed work activities associated with earth compaction in preparation for installation of the containment base mat.
The backfill material being used appeared to be appropriately fine and of uniform moisture content as required for Class 1 structural backfill.
A review of the testing contractor's records showed that the material was well within the gradation requirements of the specifi-cation (13-CM-300, Excavation and Backfill). It was also observed that the material was being placed within the specified maximum lift sizes.
The inspector watched the test laboratory technician obtain two test specimens and perform the density test as directed by the specified method (ASTM-1556-64 (1974),. Test for Density of Soil in Place by the Sand-Cone Method).
The two specimens were taken at the 54-foot elevation, one at the 205-degree azimuth and 11 1/2-feet inside the gallery wall, and the other at the 100-degree azimuth up against the reactor pit wall.
The test results were well above the specified minimum acceptable value of 95K of maximum dry density as determined by ASTM-D-1557-70, Test for Moisture-Density Relations of Soil.
The technicial qualifications were subsequently verifie The inspector later visited the testing contractor's laboratory and verified that the apparatus (scales, moisture indicator, and sand cone)
used by the technician had current calibration records on file.
Also examined in the laboratory were the compaction density test records for all tests that had been performed to that date (10/24).
All were statisfacotry and were shown to be conservative, based on laboratory testing of the same samples using the absolute dry density method.
No items of noncompliance or deviations were identified.
10.
Plant Tours The inspector toured the construction site several times each week during the inspection report period.
Particular attention was given to work in progress, presence of supervision and quality control inspectors at the work areas, care and preservation of equip-ment, and general housekeeping practices.
No items of noncompliance or deviations were identified during the plant tours.
ll.
blana ement Interview The inspector met with the licensee representatives denoted in para-graph
on October 19 and 26, 1979.
The scope of the inspections and the inspection findings as noted in this report were discussed.
The licensee representatives made no significant comment ~pR AKgg
~cC'
Qi
~O
~**<<~
t UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION V
1990 N. CALIFORNIABOULEVARD SUITE 202, WALNUTCREEK PLAZA WALNUTCREEK, CALIFORNIA94596 JUL 23 Sly Docket Nos.
50-528 50-529 50-530 Arizona Public Service Company P. 0.
Box 21666 Phoenix, Arizona 85036 Attention:
Hr. E.
E.
Van Brunt, Jr.
Vice President, Construction Projects and ANPP Director Gentlemen:
Subject:
NRC Inspection of Palo Verde Units I, 2 and
This refers to the inspection conducted by Messrs.
L. E. Vorderbrueggen, J.
H. Eckhardt, and G. Hernandez of this office on June 11-15, 1979, of activities authorized by NRC Construction Permit Nos.
CPPR-141, CPPR-142 and CPPR-143, and to the discussion of our findings with Nr.
E.
E.
Van Brunt, Jr.,
and other members of your staff at the conclusion of the inspection.
Areas examined during this inspection are described in the enclosed inspection report.
Within these areas, the inspection consisted of selective examinations
.
of procedures and representative records, interviews with personnel, and obser-vations by the inspectors.
No items of noncompliance with NRC requirements were identified within the scope of this inspection.
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part 2, Title. 10, Code of Federal Regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room. If this report contains any information that you believe to be proprietary, it is necessary that you submit a written application to this office, within 30 days of the date of this letter, requesting that such information be withheld from public disclosure.
The application must include a full statement of the reasons why it is claimed that the information is proprietary.
The application should be prepared so that any proprietary information identified is contained r'9O9'0't>'0
.
Arizona Public Service Company JUL 23 8?9 in an enclosure to the application, since the application without the enclosure will also be placed in the Public Document Room.
If we do not hear from you
'
in this regard within the specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be glad to discuss them with you. 'incerely, Enclosure:
IE Inspection Report Nos. 50-528/79-04 50-529/79-04 50-530/79-02 G. S. Spencer, Chief Reactor Construction and
'ngineering Support Branch
U ~ S.
NUCLEAR REGULATORX COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT 50-528/79-04 50-529/79-04
REGION V
50-530/79-02 N
50-528'0-529'0 530 License No CPPR 141 q
142
&
143 'agegnards Group Arizona Public Service Company P. 0.
Box 21666 Phoenix, Arizona 85036
~ Facility Name:
Palo Verde Units 1, 2 and
Inspection at:
Palo Verde Site, Narico a County. Arizona
'I Inspection conducted:
June 11-15, 1979 Inspectors:
L.
. Vorderbrueggen, tor Inspector Date igned
,J.
H. Eckha t. Reactor ector O
ernande Rea tor I ctor proved By:
R. T. Dodds, Chief, Engineering Support Section, Reactor Construction and Engineering Support Branch Summary:
Date igned Date igned Date Signed Ins ection of June 11-15, 1979 Re ort Nos. 50-528/79-04, 50-529 79-04 and 50-530/79-02
~AI d:
I I, df I I
I including:
follow-up of open and unresolved items for Units 1 and 2, follow-up of one item of'oncomopliance for, Unit 2, in-place storage s'urveillance for Unit 1 reactor vessel, pipe supports and restraints in Unit l. and base mat..
installation for Unit 3 reactor building and auxiliary building.
The inspection involved 71 inspector hours onsite by three NRC inspectors.
Results:
No items of noncompliance or deviations were identified during this inspection.
'V Form 219 (2')
DETAILS 1.
Persons Contacted Arizona 'Public Service Com an
- E. E.
Van Brunt, Jr.. Vice Presiden/Project Director
- H. M.- Petro, Construction Manager
,"R. L. Robb, Manager, Nuclear Services
- J. A. Roedel, Quality Assurance Manager
"L. 'll. Price, Field Engineering Supervisor
.
- R. L. Hand, Site Quality Assurance Supervisor G. Pankonin, Quality Assurance Engineer R.
D. Forrester, Quality Assurance Engineer N.
E. Hibel, Quality Assurance Engineer Bechtel Power Cor oration
- W. J. Stubblefield, Field Construction Manager
- A. K. Priest, Project Field Engineer
- D. R. Hawkinson, Project'uality Assurance Engineer
- L. G. Hinkelman, Manager - Domestic Operations
- J.
E. Bayshore, Manager - Quality Assurance
- H. H. Wilson, Project Manager
- H. G. Bingham, Project, Engineering Manager
- H. L. Claxton, Construction Specialist
- D. T. Krisha, Quality Assurance Supervisor
'J.
L. Black, Resident Engineer C. J.
Dun, Assistant Project Field Engineer H. Leuniz, Construction Superintendent
- Boilermakers T. Horst, Lead Field Engineer - Civil M. Patterson, Field Engineer - Piping M.
C. Bentley, Civil Engineer R.
M. Rosen, Quality Assurance Engineer V. F. Duckett, Unit 1 Field Engineer - Mechanical H.
C. Higgins, Assistant Lead Field Engineer - Mechanical S.
Palmrose, Quality Assurance Engineer
~Cb i
. I P.
L. Mallott, Quality Control Supervisor B. Canavan, Plant Manager
- Denotes those attending exit interview.
2.
Construction Status j
f k
The licensee reported that as of May 31, 1979, the approximate completion status of Unit 1 was 41.2Ã, Unit 2 was 15.8/,
and Unit 3 was 1.2%.
The overall project was considered to be 27.1% complet.
Licensee Action on Previous Ins ection Findin s a.
(Closed)
Noncompliance Item (50-529/79-01).
Surveyors were using a drawing for construction which was labeled as being incomplete or unapproved.
The inspector examined Bechtel memoranda and procedure WP/P gCI 3.0 which verified that the corrective action described in the licensee's response of June 5,
1979 to the NRC Notice of Violation had been satisfactorily accomplished.
This item is closed.
b.
(Closed)
Unresolved Item (50-528/79-03/01).
Assembly techniques and inspection criteria pertaining to 'the Unit 1 containment dome liner system.
At the request of NRC, a meeting was held on Nay ll, 1979, in the NRC Region Y office with licensee and Bechtel representatives for the purpose of conducting an in-depth technical discussion of this, matter.
At that meeting, Bechtel presented a summary of fit-up.
problems which were documented by the Resident Engineer subsequent to the 79-03 NRC inspection.
A handout was provided which defined the plate seam locations, and the welding and acceptance status.
Polaroid photographs showing typical misfit and stiffener distortion were also displayed.
The problems identified and discussed included:
(1)
Overlapping of adjacent plates (2)
>fide gaps between adjacent plates (which exceed the root gap criteria)
(3)
Vertical gaps between adjacent plates (as much as two inches in one case)
(4)
Buckled stiffener plates and angles due to jacking loads
.
(5)
Bent liner plate (6)
Broken tack welds Bechtel pointed out that the stiffener system functions as the concrete anchorage 'for the liner plate system and, with the liner plate, acts as the form 'for subsequent concrete placement.
r Sample calculations were presented by Bechtel which demonstrated that the loads being applied for liner segment assembly were well within the allowable stress levels specified in the governing Subsection CC'3720 of ASNE Section III, Division 2.
The calculations were con-sidered to be conservative because of the physical limitations asso-;
ciated with the construction equipment involved in the assumption Conservative calculations in regard to plate bending criteria, and planar bending of the liner plate system due to jacking loads applied.
across a complete weld seam near the apex, were also discussed.
It was seen that for a maximum outer fiber strain of 3%%d (ASNE Section III, Division 2, Subsection CC 4521.2.1, allows up to 5% before heat treat-ing is required),
a minimum bending radius of 5.4 inches is allowed.
Bechtel stated that there were no bends in the dome liner plate that
'ere not well in excess of 5.4 inches radius.
HRC questioned the effect of stress concentration at the end of a partially completed seam weld when jacking loads are applied in the. same direction as the plane of the liner plate.
Bechtel stated that such stress concentra-tion is precluded by the assembly techniques i.e.,
seam tack welding and temporary cross-seam bridging members.
In any event, however, the final vacuum box testing of the seams for, leak tightness would detect any 'cracks which would then be repaired, according to Bechtel.
Receiving inspection was also discussed.
'The supplier performs the dimensional checks in his fabrication shop.
Upon arrival at the jobsite, inspection.is made for shipping damage only.'o dimensional checks'are made at that time; however, there are 'dimensional checks
'made at the assembly jig'.
The condition of the received plate was poor at the beginning but has been improving, according to Bechtel.
r It was Bechtel's stated intention to perform the folloicing functions in completing the fit-up of the Unit
dome liner plate subassemblies:
(1)
Replace buckled and damaged stiffeners.
(2)
Bend plates back to the required shape.
(3)
For overlapping plates, cut the plates back to achieve the required root gap.
~
~
(4)
For wide gaps, the liner plate is to be buttered to achieve 3/4-inch root gap, and rebeveled for final welding.
(5)
A 15-inch template check would be performed.
Also, the Resident Engineer would be closely involved in the follow-up and review of this work and, before final welding to the "dollar plate."
he would'perform a final acceptance inspection.
Hith regard to specifically stated concerns of the HRC, the following agreements between the participants were reached:
(1)
Specification 13-CH-370 would be revised to include the criteria of 2/3 fy for stresses due to construction broads, and for plates bent to a radius of 6-inches 'or greater.
Calculations 'were to be made to translate the stress'nto terms which construction can
use, such as, 6-ton come-a-longs at specified spacings.
Such information would be included as an attachment to Specification.
13-CIA-370.
l (2)
Engineering direction regarding welding sequence is not required.
The erection limitations currently in Specification 13-CM-370, and the additional limitations that are planned to be added, are
'ufficient to assure an installation which is well.within the ASME Code stress level boundaries.
'L (3)
The Resident Engineer represents home office engineering and has been involved with the superintendents from the beginning of the erection of the containment building liner plate system.
He has been and will continue to be involved with the follow-up of the work and corrective actions, in coordination with the design engineering team in Downey.
(4)
Specification 13-CM-370 would be revised within a month.
The Resident Engineer would hold a meeting with, Construction per-sonnel to familiarize them with the upgraded provisions, and to assure that the points of concern were properly understood.
Minutes of the meeting would be issued and kept in the file.
(5)
Past records would be reviewed to find NCRs which indicate shipping damage observed during receiving inspection.
These NCRs will be evaluated to determine if any plate was bent to radius less than 5.4 inches, thus incurring strains greater than 3%.
A final report of this evaluation and resolution is to be provided to the HRC.
(6)
Resumption of fit-up and welding work on the Unit
dome liner plate system would not occur until the specification changes contemplated in (1) above are implemented, and the indoctrina-tion meeting identified in (4),above was conducted.*
E During this inspection, the action taken relative to the commitments made at the May 11th meeting was examined.
Changes to Specification 13-CM-370 had been appropriately formalized by Specification Change Notice No.
1687 dated May 14, 1979.
Meeting minutes,.with a listing of attendees, were on file for the construction personnel indoctrina-'ion sessions conducted by the Resident Engineer on May 14 and 15, 1979..
Additionally, the Resident Engineer was maintaining a detailed
'-'-'-".
.
log'f his inspection/direction activities involving the Unit
dome liner work.
The liner plate receiving inspection NCRs had been
collected'and'ere undergoing evalua'tion by Bechtel.
The liner work
- These two measures were accomplished and work was resumed with NRC Region V
'concurrence on May 15, 197 c ~
in progress on the Unit 1 containment dome was examined by. the inspec-'or and appeared to be in accord with the specification requirements; there was no evidence of excessive forces being employed or matet ial distress in any of the components.
-
.
In consideration of the remedial action which has been accomplished by the licensee in regard to the erection of the Unit 1 containment dome liner plate system, this issue is considered closed.
(Closed)
Follow-up Item (50-529/79-03/02).
A concern was raised with respect to the identification and repair of cracks in Unit 2
=tendon gallery.
At the time of this inspection, Hunts Contracting Company had completed repair of cracks identified by Bechtel's Resident Engineer and docu-mented in NCR No.
1341.
The cracks were repaired with epoxy injection in accordance with Specification 13-CF-014.
The inspector examined the work performed and discussed with cognizant engineers the criteria.
used in determining which cracks were repaired and which were accepted
"as-is."
Based on this and a review of NCR No. 1341, it appeared that the questions raised by the inspector had been adequately answered.
This item is closed.
d.
(Closed)
Open Item (50-529/79-03/03).
Hire-cloth sieves at Batch Plant testing laboratory appeared to be out of tol erance.
The licensee provided results of tests performed with the sieves in
~
question and a master set of sieves.
The tests were performed per ASTM C136-71 and indicated a 0.01 difference in Fineness Modulus between the two tests.
Comparison to a master set of sieves is an approved method for certifying working sieves.
This item is closed.
4.
Unit 1 Polar Crane Su ort Girders During an audit of Marathon Steel Company, the fabricator of the polar crane support girders, the licensee found that the continuous 1/2-inch fillet weld whi.ch connects the vertical 1 1/2-inch vertical plate to the plate which makes up the top flange of the girder was interrupted at'the location of each 3/4-inch thick stiffener plate.
This fabrication,
'rror was considered by the licensee as potentially reportable under-the requirements of 10 CFR 50.55(e);
therefore,'Bechtel was directed to analyse
'he situation.
The inspector examined Deficiency 'Evaluation Report No. 79-2;
'ated April 27, 1979, which documented the cause.
the corrective actions
'
.
taken, and the results of the technical analysis.
The analysis indicated that the weld interruption at the stiffener locations would not adversely affect the capability of the girder to perform its intended functio.
Unit 1 Reactor Vessel Surveillance The inspector verified that measures for protecting the reactor vessel and maintaining its internal cleanliness were being followed and that the Bechtel Quality Assurance group was performing surveillance in this regard in accordance with the approved program.
6.
Unit 3 Concrete ualit Records The inspector reviewed the quality records (i.e.:
preplacement and
~ post-placement inspections, curing cards, batch plant tickets, compressive strength test results, etc.) for Unit 3 concrete placements 3C010 Reactor Pit base mat and 3A004, -5, -6 Auxiliary Building base mat for compliance with WPP/QCI 53.0, Concrete Placement and WPP/QCI 54.0, Concrete Postplace-ment.
No deviations from the applicable acceptance criteria were.identified by the inspector.
7.
Unit 1 Diesel Generator Foundation The inspector observed work in progress for the two diesel generator foundations for Unit No. I. It was determined that the work was being installed in accordance with current specifications and drawings.
A review of receipt and inspection records for the foundation anchor bolts disclosed that material certifications were missing for the A449 bolts specified on drawing number 13-C-ZGS-110.
Licensee personnel indicated that the mater'ial certification would be available for review during the next inspection.
This item is open pending review of the material certification.
(50-528/
79-04/Ol)
8.
Safet Related Pi e Su or ts and Restraints a.
Review of ualit Assurance Im 1ementin Procedures and Work Procedures b.
The following pipe support and restraint documents were reviewed to ascertain adequacy of audit program, material control, field change control, inspection, and documentation.
(1)
Specification 13-PH-209,
"Specification for Nuclear Pipe Supports" (2)
WPP/QCI-201.1,
"Nuclear Pipe Hangers and Supports Installation" '-.
'o deivations or items of noncompliance were identified.
I Observation of Work and Work Activities 4,
The following completed and accepted pipe supports installed in Unit 1 auxiliary building were selected for examination:
~sssem Chemical and Volume Control Essential Cooling Hater Fuel Pool Cooling and Cleaning Safety Injection Su ort Number 1CH142H006 1CH320H006 lEM023H024-1PC022H012 1SI079H005 1S I105H001 1S I144H005 1S I194H008 Pi e Diameter, in.
3
10
3
The supports were all of a fixed design, quality class g, seismic category 1,
and ASNE Section III, Class 2 or 3.
They were compared with the applicable'pipe support assembly drawings to ascertain pro-per location, welding, pipe clearances, and as-built configuration.
All of the supports appeared satisfactory with the exception of support number 1SI079H005.
The weld size for this support was not as specified in the drawing in that one leg of the fillet weld of the pipe saddle to saddle base was only 1/4 inch, whereas the draw-specified a 3/8 inch fillet weld.
This weld was a shop weld installed by Pullman Power Products (the piping supplier)
and was,an ASHE Class
weld.
Other welding on this support (both Pullman and Bechtel field welding) as well as on the other pipe supports examined appeared satisfactory.
This item is considered.unresolved pending examination of a larger
,
sample of Pullman welds during a future inspection to determine if a generic 'problem with fillet weld size. exists (50-528/78-04/02).
Review of ualit Assurance Records The guality Assurance records associated with the pipe supports listed in Paragraph 8.b, above, were reviewed.
The records included construc-tion inspection plans for all of the supports examined, and welding and NDE records for the five supports that had ASHE welds.
All records appeared satisfactory with the exception of the records for support number 13SI144H005.
This support assembly included two stainless steel lugs welded to the pipe.
The construction inspection plan indicated that the welds f'r both lugs (weld numbers 2 and 3)
had been liquid penetrant tested.
However, the LP test report did not indicate that
a LP test had been performed on weld 2.
These records had been signed and approved.
The licensee indicated that these records would be re-reviewed and a
LP test performed on weld 2 if no evidence cou'ld be produced to indicate that a
LP test had previously been performed.
'his is considered an open item (50-528/78-04/03).
9.
Exit Interview The inspectors met with licensee representatives (denoted in Paragraph 1)
at the conclusion of the inspection on June 15, 1979, and summarized the scope and findings of the inspection, including the items discussed in Paragraphs 7 and 8.
h
'
C