| | Title | Significance | Cross cutting aspect |
|---|
| 05000482/FIN-2008006-01 | Twenty-One Examples of Failure to Follow Seismic Requirements of Scaffolding Procedure | Green | H.14 |
| 05000482/FIN-2008006-02 | Failure to Take Corrective Action For Missed Compensatory Measures | Green | P.3 |
| 05000482/FIN-2008006-03 | Failure to Take Corrective Actions For Missed Operability Evaluation | Green | P.3 |
| 05000482/FIN-2008006-04 | Failure to Take Timely Corrective Action To Establish Monitoring Frequency of AFW Pump Governor Null Set Drift | Green | P.3 |
| 05000482/FIN-2008006-05 | Failure to Take Timely Corrective Action to Correct Annunciator Feed Configuration Deficiencies. | Green | P.2 P.1(a) |