APPENDIX U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
NRC Inspection Report:
50-458/85-72 Construction Permit:
CPPR-145 Docket:
50-458 Licensee:
Gulf States Utilities (GSU)
P. O. Box 2951 Beaumont, Texas 77704 Facility Name:
River Bend Station Inspection At:
River Bend Station, St. Francisville, Louisiana Inspection Conducted: October 9-11, 1985
' "*
n. 2 -tf Inspector:
-
Nemen Terc, Emergency Preparedness AnaTyst Date Emergency Preparedness and Safeguards Programs Section Approved:
Ah J2-3-Rf L. A. Yandell, Chief, Emergency Preparedness and Date Safeguards Programs Section Inspection Summary Inspection Conducted October 9-11, 1985 (Report 50-458/85-72)
Areas Inspected:
Routine, unannounced inspection of emergency procedures appraisal findings identified in NRC Inspection Report 50-458/84-34. The inspection involved 20 inspector-hours onsite by one NRC inspector.
Results: Within the one area inspected, no violations or deviations were identified.
Three significant findings were closed and 13 improvement findings were closed.
This leaves no significant findings and 16 improvement findings for followup in a future inspection.
0601020870 051219 PDR ADOCK 05000458 G
- -
- -
.
.
.
-
_ _ -
.
_ _ - _ _ -
.
-
_ _
_. -
.
. _ _
i
,
DETAILS
.
1.
Persons Contacted G.Su D. Bloermandaal, Senior Emergency Planner
- J. Cadwallader, Supervisor, Emergency Planning T. Crouse, Manager, Quality Assurance D. Davenport, Plant Security Supervisor
- J. Deddens, Vice President, RBNG, GSU
>
T. Dexter, Security Training Coordinator
'
C. Fantacci, Senior Health Physicist T. Gildersleeve, Nutech Consultant
- K. Hodges, Quality Assurance Systems Engineer
- G. King, Plant Services Supervisor
- R. King, Licensing Engineer W. Odell, Manager, Administration D. Simpson, Nutech Consultant
- R. Taylor, Quality Assurance Engineer C. Wells, Emergency Public Information Coordinator
)
.
- Indicates persons who attended the exit meeting.
.2.
Significant Appraisal Findings - (Appendix A)
'
(Closed) (458/8435-01):
The inspector determined that interfaces between the emergency planning group and the plant manager were adequate.
(Closed) (458/8435-05):
The inspector verified that the staff augmentation drill was conducted on October 2, 1985.
Results indicated that all Emergency Response Facilities were staffed promptly.
!
(Closed) (458/8435-73):
The inspector verified that 17 additional loud speakers had been installed and tested to ensure that personnel within the protected area would hear emergency warnings and instructions.
^
No violations or deviations were identified.
3.
Appraisal Improvement Items - (Appendix B)
,
(Closed) (458/8435-03):
The inspector noted that the Emergency Plan was revised in July 1985 to describe the makeup, responsibilities and i
authorities of the Emergency Planning Group and the Facility Review Committee.
.(Closed) (458/8435-08):
The inspector noted that the Emergency Plan Implementing Procedures EIP-2-002 through EIP-2-005 defined the authorities and assignments of the emergency response organization.
.
-
- -
...
_ _. _ _.
-
.,
,
(Closed)(458/8435-38):
The inspector verified that door bells were installed at the entrance points of the Emergency Operations Facility.
(Closed)(458/8435-59):
The inspector noted that emergency verification telephone numbers to the control room were made available to offsite authorities.
(Closed)(458/8435-66): 'The inspector verified that a new revision of procedure EIP-2-001, " Classification of Emergencies," specified substan-tial reviews by the River Bend Station Facility Review Committee and key station managers.
(Closed) (458/8435-74):
The inspector noted that the NRC initial Notification Form had been incorporated in revision 4 of EIP-2-006,
" Notifications."
'
(Closed)(458/8435-75):
The inspector verified that authentication schemes were adequate.
(Closed)(458/8435-76):
The inspector held discussions with the licensee l
,
staff pertaining to the rationale behind their radiological environmental
'
program and concluded that their policy of optionally removing thermolu-minescent dosimeters during accidents was adequate.
(Closed)(458/8435-78):
The inspector verified that 8 pci Cs-137 check sources were in kits to be used for offsite monitoring during accidents.
(Closed)(459/8435-80):
The inspector verified that current emergency implementing procedures made consistent use of emergency titles.
(Closed) (458/8435-81):
The inspector noted that procedure EIP-2-014,
"Offsite Radiological Monitoring" directed users to use " closed" versus
"open" window readings in order to determine whether airborne samples were being collected within the radioactive plume.
(Closed)(458/8435-97):
The inspector noted that the first emergency preparedness audit by an independent organization was conducted in August 1985 and that it included discussions with plant personnel.
In oddition, the quality assurance inspector group participated in the
,
observation of drills and exercises.
,
,
No violations or deviations were identified.