Insp Rept 50-458/85-72 on 851009-11.No Violation or Deviation Noted.Major Areas Inspected:Emergency Procedures Appraisal Findings Identified in Insp Rept 50-458/84-34
ML20151N394
Person / Time
Site: River Bend Entergy icon.png
Issue date: 12/02/1985
From: Terc N, Yandell L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20151N381 List:
References
50-458-85-72, NUDOCS 8601020870
Download: ML20151N394 (3)


Text

--

.

APPENDIX U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report: 50-458/85-72 Construction Permit: CPPR-145 Docket: 50-458 Licensee: Gulf States Utilities (GSU)

P. O. Box 2951 Beaumont, Texas 77704 Facility Name: River Bend Station Inspection At: River Bend Station, St. Francisville, Louisiana Inspection Conducted: October 9-11, 1985 Inspector: ' "* - n . 2 -tf

Nemen Terc, Emergency Preparedness AnaTyst Date Emergency Preparedness and Safeguards Programs Section Approved: Ah L. A. Yandell, Chief, Emergency Preparedness and J2-3-Rf Date Safeguards Programs Section Inspection Summary Inspection Conducted October 9-11, 1985 (Report 50-458/85-72)

Areas Inspected: Routine, unannounced inspection of emergency procedures appraisal findings identified in NRC Inspection Report 50-458/84-34. The inspection involved 20 inspector-hours onsite by one NRC inspecto Results: Within the one area inspected, no violations or deviations were identifie Three significant findings were closed and 13 improvement findings were closed. This leaves no significant findings and 16 improvement findings for followup in a future inspectio PDR ADOCK 05000458 G PDR

. - _ _ - . _ _ - _ _ - . - _ _ _ . - . . _ _

,

i

DETAILS

. Persons Contacted G.Su D. Bloermandaal, Senior Emergency Planner

  • J. Cadwallader, Supervisor, Emergency Planning T. Crouse, Manager, Quality Assurance D. Davenport, Plant Security Supervisor
  • J. Deddens, Vice President, RBNG, GSU

>

'

T. Dexter, Security Training Coordinator C. Fantacci, Senior Health Physicist T. Gildersleeve, Nutech Consultant

  • K. Hodges, Quality Assurance Systems Engineer
  • G. King, Plant Services Supervisor
  • R. King, Licensing Engineer W. Odell, Manager, Administration D. Simpson, Nutech Consultant
  • R. Taylor, Quality Assurance Engineer

)

C. Wells, Emergency Public Information Coordinator

. * Indicates persons who attended the exit meetin . Significant Appraisal Findings - (Appendix A)

'

(Closed) (458/8435-01): The inspector determined that interfaces between the emergency planning group and the plant manager were adequat (Closed) (458/8435-05): The inspector verified that the staff augmentation drill was conducted on October 2, 1985. Results indicated that all Emergency Response Facilities were staffed promptl !

(Closed) (458/8435-73): The inspector verified that 17 additional loud speakers had been installed and tested to ensure that personnel within the protected area would hear emergency warnings and instructions.

^

No violations or deviations were identified.

, Appraisal Improvement Items - (Appendix B)

(Closed) (458/8435-03): The inspector noted that the Emergency Plan was revised in July 1985 to describe the makeup, responsibilities and i authorities of the Emergency Planning Group and the Facility Review Committe .(Closed) (458/8435-08): The inspector noted that the Emergency Plan Implementing Procedures EIP-2-002 through EIP-2-005 defined the authorities and assignments of the emergency response organizatio .____ __-__- - _ _________ _ _ _ _ _. _ _ . _ _ .

., -

,

(Closed)(458/8435-38): The inspector verified that door bells were installed at the entrance points of the Emergency Operations Facilit (Closed)(458/8435-59): The inspector noted that emergency verification telephone numbers to the control room were made available to offsite authoritie (Closed)(458/8435-66): 'The inspector verified that a new revision of procedure EIP-2-001, " Classification of Emergencies," specified substan-tial reviews by the River Bend Station Facility Review Committee and key station manager (Closed) (458/8435-74): The inspector noted that the NRC initial Notification Form had been incorporated in revision 4 of EIP-2-006,

" Notifications."

'

(Closed)(458/8435-75): The inspector verified that authentication schemes were adequate.

, (Closed)(458/8435-76): The inspector held discussions with the licensee l staff pertaining to the rationale behind their radiological environmental '

program and concluded that their policy of optionally removing thermolu-minescent dosimeters during accidents was adequat (Closed)(458/8435-78): The inspector verified that 8 pci Cs-137 check sources were in kits to be used for offsite monitoring during accident (Closed)(459/8435-80): The inspector verified that current emergency implementing procedures made consistent use of emergency title (Closed) (458/8435-81): The inspector noted that procedure EIP-2-014,

"Offsite Radiological Monitoring" directed users to use " closed" versus

"open" window readings in order to determine whether airborne samples were being collected within the radioactive plum (Closed)(458/8435-97): The inspector noted that the first emergency preparedness audit by an independent organization was conducted in August 1985 and that it included discussions with plant personne In

,

oddition, the quality assurance inspector group participated in the observation of drills and exercise ,

,

No violations or deviations were identifie . Exit Interview At the end of the inspection, on October 11, 1985, the inspector met with the persons identified in paragraph 1 above and sunmarized the status of follow up items from the previous emergency preparedness appraisal.