IR 05000423/1981001

From kanterella
Jump to navigation Jump to search
IE Mgt Meeting Rept 50-423/81-01 on 810106.Areas Discussed: Details Re Establishment of Onsite Ofc for Placing Full Time NRC Inspector at Facility
ML19350A428
Person / Time
Site: Millstone Dominion icon.png
Issue date: 01/27/1981
From: Robert Carlson, Mattia J, Mcoscar J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML19350A422 List:
References
50-423-81-01, 50-423-81-1, NUDOCS 8103160156
Download: ML19350A428 (2)


Text

A

.

O U. S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT

REGION I

Report No.

50-423/81-01 Docket No.

50-423 License No.

CPPR-113 Priority Category A

-

Licensee:

Northeast Nuclear Energy Comoany P. O. Box 270 Hartford, Connecticut 06101 Facility Name:

Millstone Nuclear Power Station, Unit No. 3 Meeting At:

Waterford, Connecticut Meeting Conducted:

January 6, 1981 NRC Personnel:

. $.

N)

h6/F/

[',/J. C. Mattia, Acting Chief, Projects

'

date I

/ \\ 'Section RC&ES Branch

% M. N \\ d.J

.c..

_

/I't.h)

J'._ J. Mc0 scar, Chief, Administrative date Branch.

_

date

/

/

8/

Approved by:

h

/ da'te R. T. Carlson, Chief, RC&ES Branch Meeting Summary:

Management Meeting on January 6, 1981 (Report No. 50-423/81-01)

Areas Discussed:

Management meeting held at NRC request to discuss details related to the establishment of an on-site office for the purpose of placing a full time NRC inspector at the facility.

Results:

All parties concurred on admir.istrative and operational considerations needed to establish an on-site NRC inspector.

Region I Form 12 (Rev. April 1977)

slo 8160/5h

_

_

-.

i

.

DETAILS 1.

Persons Contacted On January 6,1981, a meeting was held at Millstone Nuclear Power Station, Unit 3 to discuss details of establishing on-site facilities for a resident reactor inspector.

Personnel Present at the Meeting Northeast Utilities Service Company (NUSCO)

Mr. B. Carlson, Project Manager (Berlin Office)

Mr. S. Orefice, Superintendent, New Site Construction Mr. S. Toth, System Superintendent / Generation Construction USNRC - Region I J. C. Mattia, Acting Chief, Projects Section, RC&ES Branch J. J. Mc0 scar, Chief, Administrative Branch 2.

Areas Discussed a.

Facilities to be provided for the resident inspector.

b.

Provisions for telephone service including a plant telephone extension l

and NRC arranged outside phone lines.

c.

Interface responsibilities for communications equipment installation.

d.

Accessibility of NRC resident inspector to members of media and public.

e.

Resident Inspection Program f.

Office space requirements.

g.

Mail services and the NRC local postal box.

h.

Clerical help to be provided by the NRC.

l The proposed office space (interim trailer and final office in NUSCO building)

for the resident inspector was examined and approved. A firm activation date for the resident office has not been established but a tentative date of March 15, 1981 was discussed.

The NRC representatives indicated that further coordination to establish the resident inspector office and program at Millstone Unit 3 would be effected by the resident inspector.

l A site tour was also conducted and no items of noncompliance or areas of concern were identified.