IR 05000413/2024010

From kanterella
Jump to navigation Jump to search
Fire Protection Team Inspection Report 05000413-2024010 and 05000414-2024010
ML25044A484
Person / Time
Site: Catawba  
Issue date: 02/14/2025
From: Daniel Bacon
NRC/RGN-II/DORS/EB2
To: Flippin N
Duke Energy Carolinas
References
I-2024-010-0043 IR 2024010
Download: ML25044A484 (1)


Text

SUBJECT:

CATAWBA NUCLEAR STATION - FIRE PROTECTION TEAM INSPECTION REPORT 05000413/2024010 AND 05000414/2024010

Dear Nicole Flippin:

On January 16, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Catawba Nuclear Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Daniel M. Bacon, Chief Engineering Branch 2 Division of Operating Reactor Safety Docket Nos. 05000413 and 05000414 License Nos. NPF-35 and NPF-52

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000413 and 05000414

License Numbers:

NPF-35 and NPF-52

Report Numbers:

05000413/2024010 and 05000414/2024010

Enterprise Identifier:

I-2024-010-0043

Licensee:

Duke Energy Carolinas, LLC

Facility:

Catawba Nuclear Station

Location:

York, SC

Inspection Dates:

November 18, 2024 to January 16, 2025

Inspectors:

J. Alamudun, Reactor Inspector

P. Braaten, Senior Reactor Inspector

J. Montgomery, Senior Reactor Inspector

Approved By:

Daniel M. Bacon, Chief

Engineering Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a fire protection team inspection at Catawba Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

(1) CO2 system in FA 2 (Unit 2 CA Pump Room)
(2) CO2 system in FA 39 (Unit 2 Turbine Driven CA Pump Pit)
(3) Unit 2 RN (Service Water) System
(4) Unit 2 CA (Auxiliary Feedwater) System

Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1) NFPA 805 Monitoring Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (2 Samples)

The inspectors verified the following:

a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.

b. The adequacy of the design modification, if applicable.

c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.

d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.

e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1) CNS 2024-001, Limiting detectors credit in proximity to fire rated assembly based upon UL spacing
(2) EC 417257, EC 418258, Addition of auxiliary lube oil pumps to 1A, 1B, 2A, and 2B Emergency Diesel Generators

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 16, 2025, the inspectors presented the fire protection team inspection results to Nicole Flippin and other members of the licensee staff.
  • On December 12, 2024, the inspectors presented the initial inspection results to Nicole Flippin and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CNC-1435.00-00-

0039

Evaluation of Auxiliary Feedwater Pump Pit CO2 System

Pilot Valve Inlet Stem

Rev. 00

CNC-1435.00-00-

0044

Fire Protection Nuclear Safety Capability Assessment

Rev. 004

CNC-1435.00-00-

0053

NFPA 12, High Pressure Carbon Dioxide System, Code

Conformance Review for NFPA 805 Transition

Rev. 02

CNC-1435.00-00-

0067

NFPA 805 Transition - Fire Risk Evaluation (FRE)

Rev. 004

Calculations

CNM-1206.08-

0083

High Pressure Carbon Dioxide Flow Calculations, AFWP

1A Calc

Rev. a

AR 2535972

24 NRC TFPI: Out of date references in fire safe

shutdown calc

11/19/2024

AR 2536418

24 NRC TFPI: 2CA VA0174 Normal Position is

incorrect in NFPA 805 NSCA

11/21/2024

AR 2537959

CNS 2024 NRC FPTI: 2 questions concerning NFPA 805

Monitoring Program

2/9/2024

AR 2538209

24 NRC TFPI: Fire PRA Non-Suppression Probability

CO2 system

2/11/2024

Corrective Action

Documents

Resulting from

Inspection

AR 2538382

24 NRC TFPI: Observation on NSCA supporting

information

2/12/2024

CN-1574-01.01

Flow Diagram of Nuclear Service Water System (RN)

Rev. 63

CN-1574-01.02

Flow Diagram of Nuclear Service Water System (RN)

Rev. 56

CN-1762-02.20

Connection Diagram Fire Detection System (EFA) CO2

Fire Suppression Aux FDWP Pits

Rev. 13

CN-2574-02.01

Flow Diagram of Nuclear Service Water System (RN)

Rev. 48

CN-2574-02.05

Flow Diagram of Nuclear Service Water System (RN)

Rev. 53

CN-2592-01.00

Flow Diagram of Auxiliary Feedwater System (CA)

Rev. 32

CN-2592-01.01

Flow Diagram Auxiliary Feedwater System (CA)

Rev. 34

CN-2592-01.02

Flow Diagram of Auxiliary Feedwater System (CA)

Rev. 1

CN-2713-31.01

Connection Diagram Left Front Half Input Cabinet 2IC31

Rev. 10

71111.21N.05

Drawings

CN-2716-03.05-

Connection Diagram Standby Shutdown Facility Auxiliary

Relay Interface Cabinet 2ELCC0034 EOC System

Rev. 37

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CN-2779-02.15

Connection Diagram Aux Feedwater Sys (CA) RC to CA

Suct Isol Vlv 2CA174

Rev. 0

CNEE-0215-

01.33-01

Elementary Diagram 4160V Switchgear 2ETB Unit #13

Auxiliary Feedwater Pmp. Mtr. 2B

Rev. 7

CNEE-0247-

01.04

Elementary Diagram Auxiliary Feedwater System (CA,

SA) Auxiliary Fdw Turbine Driven Pump Ind. Lights &

Turbine Trip

Rev. 6

CNEE-0247-

2.02

Elementary Diagram Auxiliary Feedwater Sys (CA) Driven

& Motor Pmps A&B Loss of Suction

Rev. 7

CNEE-0247-

03.03

Elementary Diagram Auxiliary Feedwater Sys. (CA) CA to

Nuclear Service Wtr Alignment and CA Pmp B Autio Start

Circuitry

Rev. 5

CNWT-2717-

2.17

Wiring Tabulations Area Terminal Cabinet 2ATC17

Rev. 031

CNWT-2779-

01.01

Wiring Tabulations Aux Fdw Pmp Turb Control Panel

2AFWPTCP

Rev. 043

Engineering

Changes

EC 418257

Install Aux Lube Oil Pumps on the 1A and 1B EDGs

Engineering

Evaluations

CNC-1435.00-00-

0084

Catawba NFPA 805 Monitoring Program

Rev. 002

AD-EG-ALL-1501

Fire Protection Change Process

Rev. 5

AD-EG-ALL-1503

FIRE PROTECTION PERFORMANCE MONITORING

AND OTHER PROGRAM ELEMENTS

Rev. 5

Procedures

AP/0/A/5500/045

Plant Fire

Rev. 20

WO 20453316-01

Unit 2 Aux FDWP CO2 System Test (18 month)

08/22/2021

WO 20521989

Unit 2 Aux FDWP CO2 Annual Test

08/21/2022

WO 20555016

Unit 2 Aux FDWP CO2 System Test (18 Month)

05/17/2023

WO 20586541-01

Unit 2 Aux FDWP CO2 System Annual Test

08/20/2023

WO 20604427

Unit 2 Aux Feedwater Pump Room CO2 Test

04/09/2024

Work Orders

WO 20660291

Unit 2 Aux Feedwater Pump Room CO2 Test

07/24/2024