IR 05000409/1980004

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-409/80-04 During June 1980.No Noncompliance Noted.Major Areas Inspected:Operational Safety,Surveillance, Maint & TMI short-term Mods
ML19332B284
Person / Time
Site: La Crosse File:Dairyland Power Cooperative icon.png
Issue date: 07/09/1980
From: Baker K, Ridgway K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML19332B282 List:
References
50-409-80-04, 50-409-80-4, NUDOCS 8009260420
Download: ML19332B284 (5)


Text

_ - _ _ _ _ - _ _ _ _ - _

_

___

_

________ _ _ _ _ _ _ _ _ - _ _ _

__ _ _

O e

U.S. NUCLEAR REGULATORY COMMISSION i

0FFICE OF INSPECTION AND ENFORCEMENT

.

REGION III

Report No. 50-409/80-04 Docket No. 50-409 License No. DPR-45 Licensee:

Dairyland Power Cooperative 2615 East Avenue, South La Crosse, WI 54601 Facility Name: La Crosse Boiling Water Reactor Inspection At:

La Crosse Site, Genoa, WI l

Inspection Conducted: June, 1980 Inspectors:

.R 6-20, 1980)

his

. u n $ 2-13, 23-27, 1980)

9k R. Riilgwdf Quid u

'I 7,!i,/fd hW June 2-6, 23-30, 1980)

.

1.,/4.,/h-A ne 2-6, 1980)

x./. 9=L- +

Approved By:

D. C. Boyd /Chied Projects Section 4 7,/9.,/pg

__

Inspection Summary Inspection during June, 1980 (Report No.50-409/80-04)

Areas Inspected: Routine, announced inspection of the licensee's opera-tional safety; surveillance; maintenance, TMI short-term modifications, and followup action relative to IE Bulletins, IE Circulars, and open inspection items. This inspection involved 244 inspector-hours onsite by four NRC inspectors'.

Results:

In the seven areas inspected, no items of noncompliance or deviations were found.

8 000260q g

.

_- -

_ _ _ _.

,

DETAILS 1.

Persons Contacted

  • J. Parkyn, Assistant Plant Supteintendent
  • G. Boyd, Operations Supervisor
  • L. Goodman, Operations Engineer
  • L. Krajewski, Health and Safety Supervisor
  • H. Towsley, Quality Assurance Supervisor
  • S. Rafferty, Reactor Engineer W. Angle, Process Engineer
  • M. Polsean, Shift Supervisor
  • W. Nowicki, Supervisor, Instrument and Electrical R. Wery, QA Specialist
  • G. Joseph, Security and Fire Protection Supervisor L. Kelley, Assistant Operations Supervisor

-

  • Denotes those present at exit interview.

In addition, the inspector observed and held discussions with other engineers, plant equipment operators, reactor operators, assistants, and plant attendants.

2.

General The reactor was shut down on June 21, 1980, to repair a leaking mechanical seal on control rod 24 and to replace a leaking seal on the 1A Forced Circulation Pump. The facility was restarted on June 29.

The refueling outage is now tentatively scheduled for the last of September, 1980.

3.

Operational Safety Verification The inspector observed control room operations, reviewed applicable logs and conducted discussions with control room operators during the month of June, 1980. The inspector verified the operability of selected emergency systems, reviewed tagout records and verified proper return to service of affected components. Tours of LACBWR reactor buildings and turbine buildings were conducted to observe plant equipment conditions, including potential fire hazards, fluid leaks, and excessive vibrations and to verify that maintenance requests had been initiated for equipment in need of maintenance.

The inspector by observation and direct interview verified that the physical security plan was being implemented in accordance with the

=tation security plan.

The inspector observed plant housekeeping / cleanliness conditions and verified implementation of radiation protection controls. During the month of June, 1980, the inspector walked down the accessible portions of the tternate core spray system to verify operability. The-2-

.

inspector also witnessed portions of the radioactive waste system

'

controls associated with radwaste shipments and barreling.

These reviews and observations were conducted to verify that facility operations were in conformance with the requirements established under technical specifications, 10 CFR, and administrative procedures.

4.

Monthly Maintenance Observation Station naintenance activities of safety related systems and com-ponents listed below were observed / reviewed to ascertain that they were conducted in accordance with approved procedures, regulatory guides and industry codes or standards and in conformance with technical specifications.

The following items were considered during this review:

the limiting conditioas for operation were met while components or systems were removed from service; approvals were obtained prior to initiating the work; activities were accomplished using approved procedures and were inspected as applicable; functional testing and/or calibrations were performed prior to returning components or systems to service; quality control records were maintained; activities were accomplished by qualified personnel; parts and materials used were properly certified; radiological controls were implemented; and, fire preven-tion controls were implemented.

Maintenance requests were reviewed to determine status of outstanding jobs and to assurc that priority is assigned to safety related equipment maintenance which may affect system performance.

The following maintenance activities were reviewed:

Forced Circulation Pump 1A seal replacement and Control rod 24 seal replacenient.

5.

Monthly Surveillance Observation The inspector observed technical specifications required surveil-lance testing on the fire detection and alarm system, nuclear instru-mentatic.n full scram hot short and Emergency Diesel Generator IB monthly test and verified that testing was performed in accordance with adequate procedures, that test instrumentation was calibrated, that limiting conditions for operation were met, that removal and restoration of the affected components were accomplished, that test results conformed with technical specifications and procedure re-quirements and were reviewed by personnel other than the individual directing the test, and that any deficiencies identified during the testing were properly reviewed and resolved by appropriate management personnel.

-3-

)

. _ _ _

,

r

.

The inspector also witnessed portions of the test activities listed

above.

6.

Licensee Event Reports Followup Through direct observations, discussions with licensee personnel, and review of records, the following event reports were reviewed to determine that reportability requirements were fulfilled, immediate correccive action was accomplished, and corrective action to prevent recurrence had been accomplished in accordance with technical speci-fications.

80-04 - During Testing (TS 5.2.6) while shutdown, the 1A Reactor Emergency Flooding Vent Valve did not open.

7.

IE Circular Followup For the IE Circulars listed below, the inspector verified that the Circular was received by the licensee management, that a review for applicability was performed, and that if the circular were ap lic-able to the facility, appropriate corrective actions were taken or were scheduled to be taken.

79-18 - Proper installation of Terget-Rock Safety Relief Valves 79-19 - Loose locking devices an Ingersoll Pump propellers 79-21 - Prevention of unplanne3 teleases of radioactivity 80-11 - Emergency Diesel Generator lube oil cooler failures 80-12 - Valve-Shaft-To-Actuator key may fall out of place when mounted below horizontal axis.

8.

Special Inspection Regarding TMI Short Term Items (NUREG 0578)

During the inspection in May, 1980, the inspectors reviewed commit-ments made by the licensee regarding short term TMI items. Several items were left open following that inspection. These items were reviewed and closed during this inspection as follows:

a.

(Closed) Unresolved Items 50-409/80-01, 02 and 03, NUREG - 0578 Item 2.1.3.a:

The inspectors determined that approved procedures are in place for the maintenance of the safety valve position indicators and that facility drawings have been modified to reflect the new installation.

b.

(Closed) Unresolved Item 50-409/80-01-05, NUREG - 0578, Item 2.1.6.a:

The inspector verified that the leak testing of the Component Cooling Water System and the Off-Gas System had been placed on the refueling surveillance schedule.

c.

(Closed) Unresolved Item 50-409/80-01-06, NUREG - 0578, Item

'

2.1.8a., b. and c.:

The inspector reviewed the following procedures to determine that operating and calibration procedures-4-

r

I are in place for the stack noble gas monitor and the control room and technical support center radioiodine monitors:

a.

EPP-21, Sample Collection and Analysis During Emergencies, Issue 0, March 6, 1980.

b.

HSP-2.7, Calibration of Installed Radiation Monitors, Issue 1, May 21, 1980.

c.

HSP-6.16, Radioactive Off-Gas System Analysis, Issue 2, October 5, 1979.

9.

Use of Senior Operators in LACBWR Training, TI 2515/36 The responsibility for the training program at LACBWR is under the direct control of the Assistant Superintendent and the Training Supervisor who both hold SRO licenses. Most of the training is conducted by them and other SR0's, however, LACBUR also uses the expertise of engineers with 10 to 15 years experience in reactor operations and engineering to present some lectures in the areas integrated response and transients. These engineers are not applying for SRO licenses.

10.

Exit Interview

.

The inspector met with licensee representatives (denoted in Paragraph 1) throughout the month and at the conclusion of the inspection and summarized the scope and findings of the inspection activities.

l

-5-l

-