IR 05000395/2022011

From kanterella
Jump to navigation Jump to search
Fire Protection Team Inspection Report 05000395/2022011, Summer Report Final
ML22270A077
Person / Time
Site: Summer 
Issue date: 09/29/2022
From: Gerald Mccoy
NRC/RGN-II/DRS/EB2
To: Stoddard D
Dominion Energy Co
References
IR 2022011
Download: ML22270A077 (11)


Text

September 29, 2022

SUBJECT:

VIRGIL C. SUMMER NUCLEAR STATION - FIRE PROTECTION TEAM INSPECTION REPORT 05000395/2022011

Dear Mr. Stoddard:

On August 26, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Virgil C. Summer Nuclear Station. On August 25, 2022, the NRC inspectors discussed the results of this inspection with Mr. George Lippard III and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Gerald J. McCoy, Branch Chief Engineering Branch 2 Division of Reactor Safety Docket No. 05000395 License No. NPF-12

Enclosure:

As stated

Inspection Report

Docket Number:

05000395

License Number:

NPF-12

Report Number:

05000395/2022011

Enterprise Identifier:

I-2022-011-0018

Licensee:

Dominion Energy

Facility:

Virgil C. Summer Nuclear Station

Location:

Jenkinsville, SC

Inspection Dates:

August 08, 2022 to August 25, 2022

Inspectors:

P. Braaten, Senior Reactor Inspector

W. Monk, Senior Reactor Inspector

M. Singletary, Reactor Inspector

D. Terry-Ward, Construction Inspector

Approved By:

Gerald J. McCoy, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a fire protection team inspection at Virgil C. Summer Nuclear Station, in accordance with the Reactor Oversight Process (ROP). The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

a. Review deficiencies or open fire protection impairments for the selected system, including any temporary modifications, operator workarounds, or compensatory measures.

b. Verify that operator actions can be accomplished as assumed in the licensees FHA, or as assumed in the licensees fire probabilistic risk assessment (FPRA) analysis and SSA.

c. Review repetitive or similar maintenance work requests which could be an indicator of a design deficiency and could affect the ability of the components to perform their functions, when needed.

d. Ensure that post maintenance and/or surveillance activities are performed as scheduled.

e. Perform a walkdown inspection to identify equipment alignment discrepancies. Inspect for deficient conditions such as corrosion, missing fasteners, cracks, and degraded insulation.

f. Ensure the selected SSCs that are subject to aging management review (AMR) pursuant to 10 CFR Part 54 are being managed for aging (e.g., loss of material, cracking, reduction of heat transfer) in accordance with appropriate aging management programs. Verify that the licensees aging management program activities (such as, Fuel Oil Analysis or Selective Leaching Aging Management Program) associated with FP equipment are being implemented.

g. If a review of operating experience issues will be completed for the selected inspection sample, verify that the licensee adequately reviewed and dispositioned the operating experience in accordance with their processes.

(1) Emergency Feedwater
(2) 480 V Emergency AC Busses
(3) Incipient Fire Detection Systems
(4) Select Fire Barriers and Penetrations in Auxiliary Building

Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1) NFPA 805 Monitoring Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors verified the following:

a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.

b. The adequacy of the design modification, if applicable.

c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.

d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.

e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1) ECR 50940 - Spent Fuel Pool Cooling Alternate Power

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On August 25, 2022, the inspectors presented the triennial fire protection inspection results to Mr. George Lippard III and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

DC00340-001

Fire PRA Plant Final Report

Rev. 02

DC0780B-001

Fire Modeling: Generic Methodology

Rev. 10

DC07860-005

Fire Protection - Base Transient Combustible Loads

Rev. 1

DC07860-006

Fire Loading Calculation (Appendix R)

Rev. 7

DC08500-018

Cable Sizing Criteria Development

Rev. 9

DC08500-023

Cable Ampacity Considerations for power cable trays in

Kaowool Fire Barrier Blanket

Rev. 01

DC08500-024

Cable Ampacity Considerations for Power cable air drops

wrapped in Kaowool Fire Barrier

Rev. 02

DC08500-026

Cable Ampacity Considerations for Power cable raceways

wrapped with 3M Interam Fire Barrier System

Rev. 01

Calculations

DC08620-046

Electrical Cable Insulation Contribution to Fire Loading

Rev. 03

CR-20-00764

Breaker failed testing. While performing EMP280.004 on

breaker XMC1DB2Z 02HM breaker failed to

01/29/2022

CR-20-02387

During research for procurement of GE Q12IAC66K57A

relays (SKU 54-7602-0517-13)

01/29/2022

Corrective Action

Documents

CR-21-00631

Found fuses for FU1 had a 15-amp fuse on top and 10-

amp fuse on bottom. Found fuses for FU2

03/11/2021

CR 1205423

Determine whether DO NOT CUT THROUGH RELAY

ROOM Sign is Required

08/11/2022

Corrective Action

Documents

Resulting from

Inspection

CR 1206345

Incipient Detection NFPA 72 Code Reconciliation

08/24/2022

B-208-021

Charging/Safety Injection Pump C (XPP43C) (Channel B)

Rev. 10

B-208-021, page

A

Electrical - Elementary Diagram, Charging/Safety

Injection Pump C

Rev. 12

B-208-021, Page

B

Electrical - Elementary Diagram, Charging/Safety

Injection Pump C

Rev. 12

B-208-021, Page

C

Charging/Safety Injection Pump C (XPP43C) (Channel B)

Rev. 10

B-208-032

Electrical - Elementary Diagram, EF Isolation from

Turbine Driven Pump to Steam Gen. B IFV-3546

Rev. 15

71111.21N.05

Drawings

B-208-032

Electrical - Elementary Diagram, EF Isolation from Turb.

Rev. 12

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Driven PPs to Steam Gen. B IFV-3546

B-814-207

I & C Instrument Diagram, INTMD Bldg EL 412-0 Emer

FDW to S. G. A flow FT-3561; PT-3563; and S.G. A

BLDWN FT-4702A

Rev. 05

B-814-212

I&C Instrument Diagram, Intermediate Bldg EL 412-0

Emergency FDW to Steam Generator FT-3571; PT-3573;

FT-3581 & FT-3541

Rev. 06

D-302-085

Piping, System Flow Diagram, Emergency Feedwater

(Nuclear)

Rev. 52

D-912-132

Aux Building Pump Room Cooling System

Rev. 21

E-201-240, sht.

3M INTERAM E-54A Installation. Electrical Raceway

Barrier System 21-3M-1, sht. 22

Rev. 00

E-201-240, sht.

3M INTERAM E-54A Installation. Elect. Raceway Barrier

Sys. 216-3M-3, sht. 44

Rev. 00

E-206-022

Electrical, one Line Diagram, 7200V SWGR Busses 1DA,

1DB, 1EA, 1EB

Rev. 17

E-206-047

Electrical, one Line & Relay Diagram, 480V Engineered

Safeguard MCC Power Feeds

Rev. 06

E-304-090

Piping System, Emergency Feedwater Pen. Access Area,

Plan above EL. 412-0 & 435-0

Rev. 06

E-811-017

Instrument Location Layout, Intermediate Bldg East &

Penetration Basement Floor EL. 412-0

Rev. 32

E-813-058

I & C Schematic Detail, Instrument Hookup, Details P and

Q (NSR),sht.1

Rev. 09

SS-211-032

Electrical Block Diagram, System EF, Emergency

Feedwater

Rev. E

SS-211-032

Electrical Block Diagram, System EF, Emergency

Feedwater, sht. number U1

Rev. K

VCS-IFT03561A-

EF

Instrument Loop Diagram, Emergency Feedwater to

Steam Generator A Flow, Train B

Rev. 01

50940

Spent Fuel Cooling Pumps Alternate Power

11/05/2020

2535

Replacement of Obsolete Chessell Model 344/345 Main

Control Board Recorders

Rev. 00

Engineering

Changes

2543

Replacement of Limitorque SMB-000 Torque Switches

Rev. 00

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

(ETBT 72543)

2551

Replacement of Obsolete Rosemount Model 1153

Transmitters

06/20/2019

43046-RPT-01

VCSNS Circuit Analysis Updates for ECR 50940, Jensen

Hughes

Rev. 01

SP-0839

Engineering Services Specification, Installation, Repair

and Quality Verification of 3M INTERAM E-54 Series

Flexible Mat

Rev. 07

TR00180-015

License Renewal Aging Management Program, Program

Basis Document for the Fire Protection Program

Rev. 00

TR07800-033

Fire Safety Analysis Report

Rev. 00

TR0780E-001

VCS UNIT 1 SSD SEPARATION FIRE PROTECTION

ENGINEERING EQUIVALENCY EVALUATIONS

Rev. 00

TR0780E-003

VCS Unit 1 Fire Alarm & Detection Fire Protection

Engineering Equivalency Evaluations

Rev. 01

TR0780E-004

VCS Unit 1 Fire Protection Administrative Features and

Materials Fire Protection Engineering Equivalency

Evaluations

Rev. 00

TR0780E-005

VCS Unit 1 Fire Suppression Fire Protection Engineering

Equivalency Evaluations

Rev. 00

TR07870-017

Engineering Service Technical Report, 86-10 Evaluation:

INTERAM E-54A Fire Wrap

Rev. 01

TR08620-031

NFPA 805, NSCA Modification DROID Listing Appendix R

Compliance Review

Rev. 01

TR08620-034

FIRE RESPONSE ABNORMAL OPERATING

PROCEDURES TECHNICAL BASIS DOCUMENT

Rev. 02

TR08620-036

NFPA 805 RECOVERY ACTIONS,

FEASIBILITY/RELIABILITY STUDY

Rev. 02

TR08620-312

Engineering Service Technical Report Nuclear Safety

Capability Assessment Report Fire Shutdown Analysis

Rev. 03

Engineering

Evaluations

VCSNS-FP DBD

NFPA 805 Fire Protection - Design Basis Document

Rev. 02

FP1AB-388

Auxiliary Building

Rev. 03

FP1CB-436

Control Building

Rev. 04

Fire Plans

FP1CB-448

Control Building

Rev. 02

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

FP1LGD-001

FIRE PREPLAN LEGEND

09/07/2021

VC-FSAR-000-

FSAR

VC-FSAR-000-FSAR, Chapter 8, page 8.3-39,

Reformatted February 2019

2/2019

VCSNS - EDBD -

EF

Enhanced Design Basis Document, Emergency

Feedwater System (EF)

Rev. 17

Miscellaneous

Xtralis VESDA

VFT-15

Product Guide

April 2009

AOP-900,

APPENDIX C

LOCAL OPERATOR ACTIONS

Rev. 01

ARP-043-XPN-

5599

INCIPIENT DETECTION PANEL

Rev. 00

ICP-230.006

INCIPIENT DETECTION FUNCTIONAL CHECK

Rev. 01

PI-AA-200

Corrective Action

Rev. 38

STP-128.024

CO2 SYSTEM FUNCTIONAL REFUELING TEST

Rev. 10

STP-170.015

Surveillance Test Procedure, Fire Switch Functional Test

for XPP0043C, Charging SI Pump C

Rev. 05

STP-428.060

VENTILATION FIRE DAMPER UNITS

Rev. 09

Procedures

VCS-ERP-0020

PRE-PLAN DEVELOPMENT AND CONTROL

Rev. 02

1912689

Fire SW Func Test-XPP43C, CHG/SI PMP %

Preconditioning "Acceptable" Per CR-13-04664 Action 11

03/30/2022

88101014107

1904787 001 EMP0280.004-XMC1DB2Z 02HM Molded

Case Circuit Breaker XMC1DB2Z Feeder T

03/10/2020

88101382693

1103974 001 Replace 50/51/74 relay with a tested spare

relay. Verify proper pump start/stop

11/21/2011

WO 1903831-001

Incipient Detection Analyzer (15CHNL) for XPN5600

Panel

06/04/2020

WO 1903844-001

Incipient Detection Analyzer (15CHNL) for XPN5602

Panel

06/03/2020

WO 1912021-001

Incipient Detection Analyzer (15CHNL) for XPN5599

Panel

08/07/2020

WO 2009864-001

Incipient Detection Analyzer (15CHNL) for XPN5600

Panel

07/28/2021

Work Orders

WO 2009869-001

Incipient Detection Analyzer (15CHNL) for XPN5602

Panel

08/26/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO 2102525-001

Incipient Detection Analyzer (15CHNL) for XPN5599

Panel

2/07/2022

WO 88101019406

STP-428.060 HVAC Fire Damper Inspection

08/04/2020

WO 88101039040

STP-428.060 HVAC Fire Damper Inspection

03/08/2022