MONTHYEARIR 05000382/20230102024-01-31031 January 2024 Comprehensive Engineering Team Inspection Report 05000382/2023010 IR 05000382/20230032024-01-23023 January 2024 Acknowledgment of Reply to a Notice of Violation NRC Inspection Report 05000382/2023003 ML24012A1962024-01-12012 January 2024 Response to 2nd Round Request for Additional Information Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and ML23340A2292023-12-28028 December 2023 Withdrawal of an Amendment Request to Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability (EPID L-2022-LLA-0169)-LTR ML23349A1672023-12-21021 December 2023 Request for Withholding Information from Public Disclosure ML23348A3572023-12-14014 December 2023 Application to Revise Technical Specifications to Use Online Monitoring Methodology Slides and Affidavit for Pre-Submittal Meeting ML23352A0292023-12-13013 December 2023 Entergy - 2024 Nuclear Energy Liability Evidence of Financial Protection ML23340A1592023-12-13013 December 2023 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23333A1362023-11-29029 November 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1442023-11-21021 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23312A1832023-11-14014 November 2023 Integrated Inspection Report 05000382/2023003 and Notice of Violation ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000382/20234012023-10-0404 October 2023 Cyber Security Inspection Report 05000382/2023401 (Cover Letter Only) IR 05000382/20230052023-08-21021 August 2023 Updated Inspection Plan for Waterford Steam Electric Station, Unit 3 - (Report 05000382/2023005) IR 05000382/20233012023-08-15015 August 2023 NRC Initial Operator Licensing Examination Approval 05000382/2023301 IR 05000382/20230022023-08-0808 August 2023 Integrated Inspection Report 05000382/2023002 IR 05000382/20234022023-08-0707 August 2023 NRC Security Inspection Report 05000382/2023402 (Full Report) IR 05000382/20230402023-07-12012 July 2023 Revised 95001 Supplemental Inspection Report 05000382/2023040, Exercise of Enforcement Discretion, and Follow-Up Assessment Letter ML23191A4562023-07-10010 July 2023 Notification of Comprehensive Engineering Team Inspection (050003822023010) and Request for Information ML23158A1042023-06-0808 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000382/2023401 ML23145A2272023-06-0202 June 2023 95001 Supplemental Inspection Report 05000382/2023040, and Exercise of Enforcement Discretion ML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment IR 05000382/20230012023-04-24024 April 2023 Integrated Inspection Report 05000382/2023001, Independent Spent Fuel Storage Installation Report 07200075/2023001, and Exercise of Enforcement Discretion ML23111A2132023-04-21021 April 2023 Responses to RAI Concerning Relief Request Number EN-RR-22-001 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities ML23110A1122023-04-20020 April 2023 Annual Report for Entergy Quality Assurance Program Manual Changes Under 10 CFR 50.54(a)(3), 10 CFR 71.106, and 10 CFR 72.140(d). Notification of Application of Approved Appendix B to 10 CFR 72 Subpart G ML23108A2542023-04-18018 April 2023 WCGS Information Request, Security IR 2023401 IR 05000382/20234032023-04-17017 April 2023 Security Baseline Inspection Report 05000382/2023403 ML23093A2122023-04-0303 April 2023 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2022 ML23089A0602023-03-30030 March 2023 Entergy Operations, Inc. - Fleet Project Manager Assignment ML23088A3922023-03-29029 March 2023 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML23080A2882023-03-21021 March 2023 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) Entergy Operations, Inc ML23059A2592023-03-0707 March 2023 Correction to Issuance to Amendment No. 270 Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23065A2002023-03-0303 March 2023 EN 56252 Update - Flow Serve - Final Notification of Potential Part 21 on Peerless 56 Frame DC Motors ML23060A1092023-03-0101 March 2023 Proof of Financial Protection (10 CFR 140.15) IR 05000382/20220062023-03-0101 March 2023 Annual Assessment Letter for Waterford Steam Electric Station, Unit 3, (Report 05000382/2022006) ML22322A1092023-02-17017 February 2023 Issuance of Amendment No. 270 Adoption of TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000382/20230902023-02-0101 February 2023 Final Significance Determination of a White Finding, NOV, and Follow-Up Assessment Letter; NRC Inspection Report 05000382/2023090 ML23032A5062023-02-0101 February 2023 Technical Specification Index and Bases Update to the NRC for the Period November 11, 2021 Through July 25, 2022 ML23030A6642023-01-27027 January 2023 Flowserve, Part 21 Second Interim Notification Report Re Peerless 56 Frame DC Motors IR 05000382/20220042023-01-26026 January 2023 Integrated Inspection Report 05000382/2022004 and Independent Fuel Storage Installation Inspection Report 07200075/2022001 ML23024A0822023-01-20020 January 2023 Stephens Insurance, Entergy - 2023 Nuclear Energy Liability Evidence of Financial Protection ML23018A2202023-01-18018 January 2023 Quality Assurance Program Manual Reduction in Commitment IR 05000382/20220912023-01-12012 January 2023 Emergency Preparedness Inspection Report 05000382/2022091 and Preliminary White Finding and Apparent Violation IR 05000382/20220032023-01-0505 January 2023 Revised Integrated Inspection Report 05000382/2022003 ML22342B1402022-12-0202 December 2022 56252-EN 56252 - Flowserve - Limitorque - Interim Report Potential Part 21 on Peerless 56 Frame DC Motors ML22300A2082022-11-30030 November 2022 Issuance of Amendment No. 269 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML22332A5292022-11-29029 November 2022 Notification of NRC Initial Operator Licensing Examination 05000382/2023301 IR 05000382/20220132022-11-28028 November 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000382/2022013 IR 05000382/20220022022-11-0101 November 2022 Revised Integrated Inspection Report 05000382/2022002 2024-01-31
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000382/20223012022-03-28028 March 2022 NRC Examination Report 05000382/2022301 ML20307A1752020-10-19019 October 2020 NRC Examination Report 05000382/202008, ML20293A178 IR 05000382/20203012020-10-19019 October 2020 NRC Examination Report 05000382/2020301 IR 05000382/20183012018-12-14014 December 2018 NRC Examination Report 05000382/2018301 IR 05000382/20173012017-05-16016 May 2017 NRC Examination Report 05000382/2017301 IR 05000382/20153012015-11-0202 November 2015 Er 05000382/2015301; on 09/14/2015, 10/05/2015; Waterford Steam Electric Station, Unit 3; Initial Operator Licensing Examination Report IR 05000382/20143012014-05-15015 May 2014 Er 05000382-14-301; 04/02/2014 - 04/22/2014; Waterford Steam Electric Station, Unit 3; Initial Operator Licensing Examination Report IR 05000382/20123012013-01-0303 January 2013 Er 05000382-12-301, on October 1-November 19, 2012, Waterford Steam Electric Station, Unit 3, Initial Operator Licensing Examination Report W3F1-2011-0062, Preparation and Scheduling of Operator Licensing Examinations, Waterford Steam Electric Station, Unit 32011-07-24024 July 2011 Preparation and Scheduling of Operator Licensing Examinations, Waterford Steam Electric Station, Unit 3 IR 05000382/20113012011-05-13013 May 2011 NRC Examination Report 05000382-11-301 IR 05000382/20103022010-11-23023 November 2010 Er 05000382/10-302, on 10/04/10 - 10/21/10; Waterford Steam Electric Station, Unit 3, Initial Operator Licensing Examination Report IR 05000382/20103012010-05-0606 May 2010 Er 05000382-10-301 on March 16-24, 2010, Waterford Steam Electric Station, Unit 3, Initial Operator Licensing Examination Report IR 05000382/20093012009-11-16016 November 2009 Er 05000382-09-301 on 10/05/2009 - 10/27/09 for Waterford Steam Electric Station, Unit 3 IR 05000382/20083012008-05-0101 May 2008 Er 05000382-08-301 on 03/24/08 - 04/16/08 for Waterford, Unit 3; Initial Operator Licensing Examination Report ML0808102172008-03-21021 March 2008 NRC Initial Operator Licensing Operating Test) Examination Approval (05000382/08/301) W3F1-2005-0076, Preparation and Scheduling of Operator Licensing Examinations2005-10-27027 October 2005 Preparation and Scheduling of Operator Licensing Examinations ML0409200332004-03-30030 March 2004 Generic Fundamentals Section of the Written Operator Licensing Examination IR 05000382/20033012003-09-16016 September 2003 Er 05000382-03-301, on 8/22/03 Through 28/2003, for Waterford 3, Entergy Operation Inc.; Initial Operator Licensing Examinations W3F1-2002-0014, WAT3 - Init Exam - 01/2002 - Licensee Post Exam Recommendations2002-01-30030 January 2002 WAT3 - Init Exam - 01/2002 - Licensee Post Exam Recommendations 2022-03-28
[Table view] |
Text
UNITED STATES NUC LE AR RE G UL AT O RY C O M M I S S I O N May 6, 2010
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NRC EXAMINATION REPORT 05000382/2010301
Dear Mr. Kowalewski:
On March 16, 2010, the U.S. Nuclear Regulatory Commission (NRC) completed an initial operator license retake examination at Waterford Steam Electric Station, Unit 3. The enclosed report documents the examination findings and licensing decision. The preliminary examination findings were discussed on March 17, 2010, with Mr. John Signorelli, Operations Training. A telephonic exit meeting was conducted on March 24, 2010, also with Mr. Signorelli, who was provided the NRC licensing decision.
The examination included the evaluation of one applicant for reactor operator license and was a retake of Administrative and Control Room/In-Plant Systems Job Performance Measures. The license examiners determined that the applicant satisfied the requirements of 10 CFR Part 55, and the appropriate license has been issued. There were no post-examination comments submitted by your staff. The enclosure to this letter contains the details of this report.
No findings of significance were identified during this examination.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Mark S. Haire, Chief Operations Branch Division of Reactor Safety
Entergy Operations, Inc -2-Docket: 50-382 License: NPF-38
Enclosure:
NRC Examination Report 05000382/2010301
REGION IV==
Docket: 50-382 License: NPF-38 Report: 05000382/2010301 Licensee: Entergy Operations, Inc Facility: Waterford Steam Electric Station, Unit 3 Location: Hwy. 18 Killona, Louisiana Dates: March 16 through 24, 2010 Inspectors: B. Larson, Senior Operations Engineer C. Steely, Operations Engineer Approved by: Brian Larson, Acting Chief Operations Branch Division of Reactor Safety 1 Enclosure
SUMMARY OF FINDINGS
ER05000382/2010301; March16-24, 2010; Waterford Steam Electric Station, Unit 3; Initial
Operator Licensing Examination Report.
NRC examiners evaluated the competency of one applicant for a reactor operator license at Waterford Steam Electric Station, Unit 3.
The licensee developed the examination using NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1. NRC examiners administered the operating test on March 16, 2010.
The examiners determined that the applicant satisfied the requirements of 10 CFR Part 55, and the appropriate license has been issued.
NRC-Identified and Self-Revealing Findings
No findings of significance were identified.
Licensee-Identified Violations
None.
REPORT DETAILS
OTHER ACTIVITIES (OA)
4OA5 Other Activities (Initial Operator License Examination)
.1 License Applications
a. Scope
NRC examiners reviewed the license application submitted to ensure the applicant satisfied relevant license eligibility requirements. The examiners also audited the license application in detail to confirm that it accurately reflected the subject applicants qualifications. This audit focused on the applicants experience and on-the-job training, including control manipulations that provided significant reactivity changes.
b. Findings
No findings of significance were identified.
.2 Examination Development
a. Scope
NRC examiners reviewed the examination outlines and draft examination submitted by the licensee against the requirements of NUREG-1021. The NRC examination team conducted an onsite validation of the operating test.
b. Findings
NRC examiners provided outline, draft examination and post-validation comments to the licensee. The licensee satisfactorily completed comment resolution prior to examination administration.
NRC examiners determined that the operating test initially submitted by the licensee was within the range of acceptability expected for a proposed examination.
.3 Operator Knowledge and Performance
a. Scope
The NRC examination team administered the operating test, which consisted of four Administrative and eight Control Room/In-Plant Systems Job Performance Measures, to the applicant on March 16, 2010.
b. Findings
No findings of significance were identified.
The applicant passed the retake examination.
.4 Simulation Facility Performance
a. Scope
The NRC examiners observed simulator performance with regard to plant fidelity during examination validation and administration.
b. Findings
No findings of significance were identified.
.5 Examination Security
a. Scope
The NRC examiners reviewed examination security during both the onsite preparation day and examination administration day for compliance with 10 CFR 55.49 and NUREG-1021. Plans for simulator security and applicant control were reviewed and discussed with licensee personnel.
b. Findings
No findings of significance were identified.
4OA6 Meetings, Including Exit
The NRC presented the preliminary examination results to Mr. John Signorelli, Operations Training, on March 17, 2010. A telephonic exit was conducted on March 24, 2010, between Messrs. Chris Steely, Examiner, and Mr. Signorelli.
The licensee did not identify any information or materials used during the examination as proprietary.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
John Signorelli, Examination Developer, Operations Training
Horace
- J. Lewis, Superintendent, Operations Training
NRC Personnel
Dean Overland, Resident Inspector
ADAMS DOCUMENTS REFERENCED