October 14, 2009
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - NRC SECURITY INSPECTION REPORT 05000382/2009403
Dear Mr. Walsh:
On September 25, 2009, the U.S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Waterford Steam Electric Station, Unit 3. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on September 25, 2009, with Mr. J. Kowalewski, Operations Vice President, and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
No findings of significance were identified.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, ADAMS.
ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
UNITED STATES NUCLEAR REGULATORY COMMISSION R E GI ON I V 612 EAST LAMAR BLVD, SUITE 400 ARLINGTON, TEXAS 76011-4125 Entergy Operations, Inc.
- 2 - In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response Security-Related Information-Withhold Under 10 CFR 2.390 and follow the instructions for withholding in 10 CFR 2.390(b)(1).
Sincerely,
/RA/
Michael P. Shannon, Chief
Plant Support Branch-1
Division of Reactor Safety
Docket No.: 50-382 License No.: NPF-38
Nonpublic Enclosure:
Inspection Report 05000382/2009403 w/Attachment: Supplemental Information
cc w/o enclosure:
Senior Vice President Entergy Nuclear Operations P. O. Box 31995 Jackson, MS 39286-1995
Senior Vice President and Chief Operating Officer Entergy Operations, Inc.
P. O. Box 31995 Jackson, MS 39286-1995
Vice President, Operations Support Entergy Services, Inc.
P. O. Box 31995 Jackson, MS 39286-1995 Entergy Operations, Inc.
- 3 - Senior Manager, Nuclear Safety and Licensing Entergy Services, Inc.
P. O. Box 31995 Jackson, MS 39286-1995
Site Vice President Waterford Steam Electric Station, Unit 3 Entergy Operations, Inc.
17265 River Road Killona, LA 70057-0751
Director Nuclear Safety Assurance Entergy Operations, Inc.
17265 River Road Killona, LA 70057-0751
General Manager, Plant Operations Waterford 3 SES Entergy Operations, Inc.
17265 River Road Killona, LA 70057-0751
Manager, Licensing Entergy Operations, Inc.
17265 River Road Killona, LA 70057-3093 Entergy Operations, Inc.
- 4 - bcc w/enclosure:
Ronald Albert (Ronald.Albert@nrc.gov), Chief, Reactor Security Oversight Branch Shyrl Coker, (Shyrl.Coker@nrc.gov) NSIR/DSO/DDSO, TWFN Mail Stop: T-3A5M Senior Resident Inspector (Dean.Overland@nrc.gov)
Electronic distribution by RIV:
bcc w/o enclosure:
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Chuck.Casto@nrc.gov)
DRP Director (Dwight.Chamberlain@nrc.gov)
DRP Deputy Director (Anton.Vegel@nrc.gov)
DRS Director (Roy.Caniano@nrc.gov)
DRS Deputy Director (Troy.Pruett@nrc.gov)
Resident Inspector (Dean.Overland@nrc.gov)
Branch Chief, DRP/E (Jeff.Clark@nrc.gov)
Senior Project Engineer, DRP/E (Ray.Azua@nrc.gov)
WAT Site Secretary (Linda.Dufrene@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Team Leader, DRP/TSS (Chuck.Paulk@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
OEMail Resource RidsNsirDso@nrc.gov OEMail Resource OEDO RIV Coordinator (Leigh.Trocine@nrc.gov)
ROPreports
Security-Related Complete Report - OUO:
R:\\REACTORS\\_WAT\\2009\\WAT2009403-JRL.Non-SGI.doc ADAMS - ML092890485 ADAMS: No x Yes
SUNSI Review Complete Reviewer Initials: JRL
Publicly Available
Non-Sensitive Category A.
x Non-publicly Available x Sensitive KEYWORD: MD 3.4 Non-Public A.3
Letter Only:
SUNSI Review Completed: JRL ADAMS: Yes Initials: JRL Publicly Available Non-Sensitive
SPSI/PSB-1 Peer Review PSI/PSB-1 C:PSB-1 C:PBE C:PSB-1 JRLarsen KSBrooks JLBuchanan MPShannon JAClark MPShannon
/RA/
/RA/
/RA/
/RA/
/RA/
/RA/
10/09/09 10/09/09 10/13/09 10/14/09 10/14/09 10/14/09 OFFICIAL RECORD COPY
T=Telephone E=E-mail F=Fax