IR 05000373/2024004

From kanterella
Jump to navigation Jump to search
County Station - Integrated Inspection Report 05000373/2024004 and 05000374/2024004
ML25041A288
Person / Time
Site: LaSalle  
Issue date: 02/10/2025
From: Robert Ruiz
NRC/RGN-III/DORS/RPB1
To: Rhoades D
Constellation Energy Generation
References
IR 2024004
Download: ML25041A288 (1)


Text

SUBJECT:

LASALLE COUNTY STATION - INTEGRATED INSPECTION REPORT 05000373/2024004 AND 05000374/2024004

Dear David Rhoades:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at LaSalle County Station. On January 8, 2025, the NRC inspectors discussed the results of this inspection with John VanFleet, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection.

A licensee-identified violation which was determined to be Severity Level IV is documented in this report. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at LaSalle County Station.

February 10, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Robert Ruiz, Chief Reactor Projects Branch 1 Division of Operating Reactor Safety Docket Nos. 05000373 and 05000374 License Nos. NPF-11 and NPF-18

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000373 and 05000374

License Numbers:

NPF-11 and NPF-18

Report Numbers:

05000373/2024004 and 05000374/2024004

Enterprise Identifier:

I-2024-004-0060

Licensee:

Constellation Nuclear

Facility:

LaSalle County Station

Location:

Marseilles, IL

Inspection Dates:

October 01, 2024, to December 31, 2024

Inspectors:

M. Abuhamdan, Reactor Inspector

J. Benjamin, Senior Resident Inspector

J. Cassidy, Senior Health Physicist

A. Guieb, Project Engineer

T. Hooker, Health Physicist

J. Kutlesa, Senior Emergency Preparedness Inspector

E. Magnuson, Reactor Inspector

J. Meszaros, Resident Inspector

J. Nance, Operations Engineer

J. Park, Reactor Inspector

Approved By:

Robert Ruiz, Chief

Reactor Projects Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at LaSalle County Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 7115

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000373,05000374/

2023-002-01 LER 2023-002-01, LaSalle County Station, Units 1 and 2,

Air Circuit Breaker (ACB)

Mechanically Operated Contacts (MOC) Switch Failed to Actuate 71153 Closed LER 05000373/2024-001-00 LER 2024-001-00, LaSalle County Station, Unit 1, Core Operating Limits Report Thermal Limits Exceeded 71153 Closed LER 05000373/2024-003-00 LER 2024-003-00, LaSalle County Station, Unit 1,

Technical Specification (TS)

Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded 71153 Closed LER 05000373/2024-003-01 LER 2024-003-01, LaSalle County Station, Unit 1,

Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded 71153 Closed LER 05000373/2024-002-00 LER 2024-002-00, LaSalle County Station, Unit 1,

Reactor Protection System Half Scram due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On November 22, 2024, the unit was down powered to approximately 60 percent power for power suppression testing and to make a control rod pattern adjustment. The unit was restored to full power on November 25, 2024, and remained at or near rated thermal power for the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power. On November 15, 2024, the unit was down powered to approximately 75 percent power for control rod scram time testing and to make a control rod pattern adjustment. The unit was restored to full power on November 16, 2024. On December 13, 2024, the unit was down powered to approximately 80 percent power for a control rod pattern adjustment. It was restored to full power on December 14, 2024. The unit remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) Station cold weather preparations

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

(1)2A emergency diesel generator following work window and restoration to operability on October 10, 2024

(2) Unit 2 reactor core isolation cooling (RCIC) following troubleshooting window and restoration to operability on October 18, 2024
(3) Unit 1 RCIC system with Unit 1B emergency diesel generator inoperable due to a diesel fuel leak on October 21, 2024
(4) Unit 1B standby liquid control after quarterly pump run surveillance on November 26, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 2H4, reactor building, elevation 694'-6," Unit 1 RCIC and low-pressure core spray pump cubicle week October 7, 2025

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) 2A residual heat removal (RHR) heat exchanger and performance testing

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) Simulator training scenario titled Cold Weather Preps

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)2A reactor water cleanup pump auto trip, per Work Order (WO) 5580104

(2) Unit 2 RCIC flow control issues
(3) Unit 2 local power range monitor failure trend caused by reverse engineered cards as documented in Action Request (AR) 4781907

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Unit 2 B/C RHR water leg pump rebuild and installation on November 13, 2024, given previous ball-bearing commercial grade dedication issue documented in AR 4786379

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2 elevated risk due to 2A emergency diesel generator work window on October 8, 2024
(2) Unit 2 elevated risk due to Unit 2 RCIC inoperable for troubleshooting on October 17, 2024
(3) Unit 2 elevated risk due to outside earth core bore activities the week of October 21, 2024
(4) Unit 1 elevated risk due to 1A emergency diesel generator out of service for maintenance on October 28, 2024
(5) Unit 2 elevated risk due to planned 2A RHR system work window on November 11, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) AR 4805729, 0 Emergency Diesel Generator Circulating Oil Pump Abnormal Noise
(2) AR 4809723, 2B Residual Heat Removal Service Water Pump Leak
(3) AR 4810060, LaSalle Susceptibility to GNF-3 LTP Threading Burrs
(4) AR 4813563, A-VC Delayed Compressor Start
(5) AR 4817902, Entered LOA-RD-201 for Potential Stuck Control Rod
(6) AR 4825553, High Servo Error on RR Subloop 1A1

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (10 Samples)

(1) PMT associated with the 2A emergency diesel generator work window October 7, 2024
(2) PMT associated with the replacement of air circuit breaker 2423 mechanically operated contact switch on October 7, 2024, per WO 4736142
(3) PMT associated with the Unit 2 RCIC troubleshooting work window on October 17, 2024
(4) PMT associated with the B diesel fire pump controller under WO 54113390
(5) PMT associated with the 0B auxiliary electrical equipment room (VE) compressor low suction pressure under WO 4851648
(6) PMT associated with the 2A cooling water pump, per WOs 5557974 and 5351844
(7) PMT associated with the Unit 1B emergency diesel generator after a diesel fuel leak occurred during the October 21, 2024, endurance run
(8) PMT associated with the Unit 1A emergency diesel generator cooling water pump after a planned work window on October 29, 2024
(9) PMT associated with the B control room/auxiliary electrical equipment room ventilation system train after a planned work window on November 15, 2024
(10) PMT associated with the 2A emergency diesel generator cooling water strainer high d/p alarm, per WO 5574165 on November 1, 2024

Surveillance Testing (IP Section 03.01) (4 Samples)

(1) Unit 1 division 1 RHR service water pump run and system flush on November 4, 2024
(2) Unit 1 RCIC cold quick start per LOS-RI-Q5 on November 14, 2024
(3) Common diesel driven A fire pump operational check on November 7, 2024
(4) Unit 1 2B emergency diesel generator surveillance test LOS-DG-3 idle start on November 18, 2024

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1) Unit 1 primary containment isolation valve operability test and in-service inspection (ISI) performed under WO 5550556, attachment 1A valves

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • EP-AA-1005, Addendum 1, LaSalle Station On-Shift Staffing Technical Basis, Revision 3
  • EP-AA-1005, Addendum 2, LaSalle Evacuation Time Estimates, Revision 2

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) Winter readiness in the simulator with evaluation of drill and exercise performance indicators on November 14,

RADIATION SAFETY

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (1 Sample)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1) Unit 2 control room envelope ventilation system

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee processes, stores, and uses external dosimetry.

Internal Dosimetry (IP Section 03.03) (1 Sample)

The inspectors evaluated the following internal dose assessments:

(1) EID 018931 06/13/2023

Special Dosimetric Situations (IP Section 03.04) (2 Samples)

The inspectors evaluated the following special dosimetric situations:

(1) Declared pregnant worker
(2) Effective dose equivalent for external (EDEX) radiation exposures

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (8 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1) Frisker used at the radiologically controlled exit
(2) Whole body monitors used at the chemistry lab and auxiliary building 768' elevation
(3) Chemistry lab radiation counting instrumentation
(4) Whole body counters in the dosimetry room
(5) Portal monitors at the main access facility exit
(6) Portable ion chambers stored ready for use in the calibration facility
(7) Irradiators stored and secured in the plant
(8) Area radiation monitors and continuous air monitors staged in the plant

Calibration and Testing Program (IP Section 03.02) (13 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Eberline AMS 4, SN #0013597
(2) Ludlum Model 3, SN #0016630
(3) Gamma Products Inc HPGe Detector, Cave A
(4) PerkinElmer Tri-Carb 4910TR, C
(5) ThermoScientific PM-12, SN #12008
(6) Canberra FastScan
(7) ThermoScientific RadEye PX, SN #0025283
(8) MGP AMP-200, SN #0016004
(9) MGP AMP-100, SN #077575
(10) MGP Telepole, SN #0023597
(11) Ludlum Model 3002, SN #0029014
(12) Eberline RO20, SN #0015813
(13) RADeCO H-810, SN #228 Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (2 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1) Unit 2, service water effluent radiation monitor, 2D18-1009
(2) Unit 2, standby gas treatment system, 0PLD1J

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

MS08: Heat Removal Systems (IP Section 02.07) (2 Samples)

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1) Unit 1 (September 1, 2023, through September 30, 2024)
(2) Unit 2 (September 1, 2023, through September 20, 2024)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) September 1, 2023, through September 30, 2024 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) September 1, 2023, through September 30, 2024

===71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03) (1 Sample 1 Partial)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) The inspectors evaluated corrective actions implemented in response to a Unit 1B emergency diesel generator fuel oil leak documented in AR 1041521, given an additional fuel oil leak on October 21, 2024.

(2)

(Partial)

The inspectors evaluated the overall problem identification and resolution aspects of a relatively long-standing issue regarding the Unit 2 RCIC system response in manual control mode. The review of this sample was still ongoing at the end of this inspection period and was therefore treated as a partial sample.

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)===

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in initial corrective action identification, screening, and resolution prioritization that might be indicative of a more significant safety issue.

71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) Licensee Event Reports (LERs) 05000373/2024-003-00 and

===05000373/2024-003-01, LaSalle County Station, Unit 1, Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded (Agencywide Document Access and Management System [ADAMS]

Accession Nos. ML24158A051 [2024-003-00] and ML24213A022 [2024-003-01].)

The inspection conclusions associated with this LER are documented in this report under Inspection Results Section. This LER is closed.

(2) LER 05000373/2024-002-00 for LaSalle County Station Unit 1, Reactor Protection System Half Scram due to Motor Generator Set Electric Power Monitoring Assembly Output Breaker Trip (ADAMS Accession No. ML24138A030.) The inspectors reviewed the LER and determined that the cause of the condition described in the LER was not reasonably within the licensees ability to foresee and correct, and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. This LER is closed.
(3) LER 05000373/2024-001-00 for LaSalle County Station, Unit 1, Core Operating Limits Report Thermal Limits Exceeded (ADAMS Accession No. ML24117A127.)

The inspection conclusions associated with this LER are documented in this report under Inspection Results Section. This LER is closed.

(4) LER 05000373(374)/2023-002-01, LaSalle County Station, Units 1 & 2, Supplement to Air Circuit Breaker (ACB) Mechanically Operated Contacts (MOC) Switch Failed to Actuate (ADAMs Accession No. ML24283A102.) The inspectors reviewed the updated LER submittal, which includes administrative changes only. The previous LER submittal was reviewed in NRC Integrated Inspection Report 05000373/2024003 and 05000374/2024003. This LER is closed.

Personnel Performance (IP Section 03.03)===

(1) The inspectors observed the Unit 2 control rod pattern adjustment on December 13, 2024, and evaluated the execution of the activity within established procedures.
(2) The inspectors observed the Unit 1 control rod power suppression testing on November 23, 2024, and evaluated execution of the activity within established plant procedures.

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71153 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: LaSalle Unit 1 Technical Specifications (TSs) 3.2.2 requires, in part, that all minimum critical power ratios (MCPR) to be greater than or equal to the MCPR operating limits specified in the core operating limit report. TS 3.2.2 Condition A applies to any MCPR not within the limits and requires the MCPR(s) to be restored within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. Contrary to the above, the licensee exceeded the completion time of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to restore the MCPR operating limit after not being met during the previous operating cycle (March 18, 2022, through February 19, 2024).

Significance/Severity: Severity Level IV. Traditional Enforcement is being used to disposition this violation with no associated reactor oversight process performance deficiency, per NRC Enforcement Manual revision dated December 26, 2023, Section 3.10. The inspectors determined the severity of the violation using Section 6 of the NRC Enforcement Policy and determined this issue was a Severity Level IV because it most represented the examples in Section 6.1.d.

Corrective Action References: AR 4752108 Minor Violation 71153 LERs 05000/373/2024-003-00 and 2024-003-01, LaSalle County Station, Unit 1, Supplement to Technical Specification (TS) Limiting Condition for Operation (LCO) 3.6.1.3 Completion Time Exceeded Minor Violation: The inspectors reviewed the LER and identified a minor violation of NRC requirements as described in the LER. LaSalle Unit 1 TS Surveillance Requirement (SR) 3.6.1.3.9 requires the removal and testing of the explosive squib from each shear isolation valve of the traversing in-core probe (TIP) system. The TS bases for SR 3.6.1.3.9 states that the controls that limit shelf life and operating life of the explosive charge be followed. The 5-year expiration date was exceeded for the three identified TIP shear valves, therefore the licensee determined that TS SR 3.6.1.3.9 bases was not met. This licensee declared the three TIP shear valves inoperable. The station exceeded the completion time for TS LCO 3.6.1.3, Primary Containment Isolation Valve, and therefore the licensee reported this condition as a condition prohibited by the TSs.

Screening: The inspectors determined the performance deficiency was minor. The inspectors determined that this violation was minor. The expired squib cartridges were subsequently removed and tested successfully demonstrating that the expired squib cartridges were still capable of performing their function.

Enforcement:

This failure to comply with LaSalle Unit 1 TS SR 3.6.1.3.9 constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 8, 2025, the inspectors presented the integrated inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.
  • On October 25, 2024, the inspectors presented the radiation protection inspection results to John VanFleet, Site Vice President, and other members of the licensee staff.
  • On December 16, 2024, the inspectors presented the EAL, and emergency plan change inspection results to Ronald Vanderhyden Jr., Emergency Preparedness Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP-AA-108-111-

1001

Severe Weather and Natural Disaster Guidelines

71111.01

Procedures

SY-AA-101-146

Severe Weather Preparation and Response

M-101, Sheet 1

P&ID Reactor Core Isolation Coolant (R.C.I.C)

BH

M-101, Sheet 2

P & ID Reactor Core Isolation Coolant System (R.C.I.C)

AT

Drawings

M-99

P & ID Standby Liquid Control System

AD

LOP-SC-02

Standby Operation of the Standby Liquid Control System

LOS-DG-M2

2A EDG Operability Test

111

LOS-RI-Q

RCIC Valve IST Test

LOS-RI-R4

RCIC System Startup and Valve IST

111

71111.04

Procedures

LOS-SC-Q1

SBLC Pump Operability/Inservice Test and Explosive Valve

Continuity Check

71111.05

Fire Plans

FZ 2H4

Pre-fire plan FZ 2H4 694-6 Elevation, Unit 1 RCIC and

Low-pressure Core Spray Pump Cubicle

71111.06

Engineering

Changes

EC 638241

Evaluation of 2A RHR Heat Exchanger Thermal

Performance Data Using Alternate EPRI Methodology

01/06/2023

Engineering

Changes

EC 626941

Evaluation of 2A RHR Heat Exchanger Thermal

Performance Data Using Alternate EPRI Method

03/23/2021

WO 1906481

3E12-B001A RHR HX Heat XFER Test per LTS-200-17

01/07/2019

WO 4902321

LRA 2E12-B001A RHR HX XFER Test per LTS-200-17

01/04/2023

71111.07A

Work Orders

WO 503342

LRA 2E12-B001A RHR HX XFER Test per LTS-200-17

01/04/2023

71111.11Q

Miscellaneous

LaSalle Training

Plan Cold

Weather Preps

Simulator Based Cold Weather Scenarios 1-3

AR 4559104

2A RWCU Pump Failed to Start

03/03/2023

AR 4698556

Received MCR Alarm 2H13-P602 A306 RT Outlet Cond

08/25/2023

AR 4704224

LOS RI-Q5 Attachment 2A Completed with Portions UNSAT

09/22/2023

AR 4775638

2A RWCU Pump Auto-Tripped

05/21/2024

AR 4776907

U2 RX Water Recirculation Loop B Flow Issues at 2PL14J

05/28/2024

AR 4777334

Unit 2 RCIC Pump Flow Controller Not Working in Manual

05/30/2024

71111.12

Corrective Action

Documents

AR 4781907

RM-U2 LPRM 24-17D Bypassed Due Being Downscale

06/20/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4783569

Unit 2 LPRM Inoperability Trend

06/27/2024

AR 4786567

Evaluate RM Frequency for 2G33-F033

07/12/2024

AR 4786835

2G33-Z001-08A Failed to Cycle During 2A RT f/D Backwash

07/13/2024

AR 4810348

Unit 2 RCIC Identified Issues, Troubleshooting Results

10/18/2024

Miscellaneous

169788

Quality Receipt Inspection Package of Ball Bearings

01/24/2012

ER-AA-320

Maintenance Rule Implementation Per NEI 18-10

Procedures

ER-AA-320-1004

Maintenance Rule - (a)(1) and (a)(2) Requirements

WO 1859149

MMD Rebuild the HPCS Water Leg Pump

08/20/2016

Work Orders

WO 5559386

MM Repair/Replace the 2E12-C003 Water Leg Pump

11/14/2024

71111.13

Procedures

ER-AA-600-1042

On-Line Risk Management

AR 4805729

0DG01K-C (0 DG Circ Oil Pump Noise

11/05/2024

AR 4813563

A-VC Delayed Compressor Start

10/30/2024

Corrective Action

Documents

AR 4825553

High Servo Error on RR Subloop 1A1

2/23/2024

LOP-VC-01

Control Room HVAC Operation

OP-AA-108-115

Operability Determinations

71111.15

Procedures

OP-LA-102-106

LaSalle Station Operator Response Time Program

AR 3989154

3-5 DPS Leak From 1E51-C005 When Running

03/24/2017

AR 4717922

B VC Filter Train Inlet Temp Indicator Pegged Upscale High

11/15/2023

AR 4773376

1CM022A Failed to Indicate Fully Closed

05/10/2024

AR 4804315

1F012 Close Time at Max Acceptable Value

09/25/2024

AR 4810192

U2 RCIC Governor Valve Indicating Closed When Throttled

10/17/2024

AR 4810348

Unit 2 RCIC Identified Issues, Troubleshooting Results

10/18/2024

AR 4817562

Small Steam Leak on the 1E51-F045

11/14/2024

Corrective Action

Documents

AR 4817562

Small Steam Leak on the 1E51-F045

11/14/2024

1E-2-4009AA

4160V Switchgear 242Y (2AP06E) Diesel Generator 2A

Feed ACB 2423 System DG Part 1

Y

Drawings

M-87, Sheet 3

P&ID Core Standby Cooling System Equipment Cooling

Water System

T

WO 4736142

Replace MOC Switch(s) That Have Used Contacts

10/09/2024

WO 5283468

U2 RCIC System Biennial Comprehensive IST Pump Test

10/18/2024

WO 5307861

OP LOS-DG-SR6 1A DG Flow Balance Test, Div II

10/29/2024

WO 5419093

OP LOS-VC-A1 VC EMU Train Att B

11/15/2024

71111.24

Work Orders

WO 5546106-10

OP PMT After RCIC Governor Valve Inspect/Repair

10/17/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

WO 5570588

LRA_LOS-RI-Q5 U1 RCIC Cold-Quick Start Att 1A

11/15/2024

WO 5572925

OP LOS-RI-Q6 U2 RCIC Quarterly Att 2A

10/18/2024

WO 5579385

LRA OP LOS-DG-M3 U1 HPCS DG Surv Att 1B-Idle

10/22/2024

WO 5583605

LRA Flush U1 Div 1 RHR Service Water

11/04/2024

WO 5588273-03

OP PMT New B VE Compressor Operates Properly

11/15/2024

WO 5590224

LRA LOS-DG-M3 2B DG Idle Start

11/18/2024

EP-AA-1005,

Addendum 1

LaSalle Station On-Shift Staffing Technical Basis

Calculations

EP-AA-120-1001

LAS Emergency Plan Revised for IPAWS Implementation,

Evaluation No. 23-36

23-36

71114.04

Procedures

EP-AA-1005

Radiological Emergency Plan Annex for LaSalle Station

71114.06

Miscellaneous

S-24-6-2

LORT Dynamic Simulator Scenario Guide Winter Readiness

with DEP

LAP-300-45

Ventilation Filter Testing Program

06/21/2017

RP-AA-825

ATTACHMENT 1

Respiratory Inspection and Certification Log

05/09/2024

Miscellaneous

SRRS ID: 2B.117

RP-LA-826 Pneumatic/Air Systems Quality Surveillance

2nd Quarter 2024

05/01/2024

ER-LA-390

Control Room Envelope Habitability Program

LOS-VC-SR1

Control Room and Auxiliary Electric Equipment Room HVAC

Pressurization Surveillance

LOS-VC-SR2

Control Room Envelope In-Leakage Test Using Tracer Gas

LOS-VC-SR3

Control Room Emergency Make-Up Train HEPA Filter and

Charcoal Filter In-Place Leak Tests

LOS-VC-SR4

VC/VE Recirculation Filter Test

RP-AA-444

Controlled Negative Pressure (CNP) Fit Testing

Procedures

RP-LA-826

Pneumatic / Air System Quality Surveillance

71124.03

Work Orders

WO 4922872-03

Control Room Emergency Makeup Train Charcoal Filter

Leak Test

05/07/2021

ED and TLD Data Comparison and Trending

Alpha Scorecard

10/07/2024

EID #E088111

Declaration of Pregnancy

various

71124.04

Miscellaneous

EID 018931

RP-AA-220 Attachment 2

03/02/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Internal Investigation Form

LAS-24-001

24 Bioassay Program Annual Review at LaSalle Nuclear

Power Station

Personnel

Exposure

Investigation #24-

2

SLR/SRD Discrepancy INPO 05-008

03/19/2024

RP-AA-605

ATTACHMENT 2

Waste Stream LLD Verification

01/11/2024

RP-AA-220

Bioassay Program

Procedures

RP-AA-222

Methods for Estimating Internal Exposure from In-Vivo and

In-Vitro Bioassay Data

0011487876

Ludlum RADEYEPX/NRD Certificate of Calibration

2/21/2023

0011492021

Ludlum Model 3002 Certificate of Calibration

11/01/2023

0011493223

Ludlum Model 3030P Certificate of Calibration

01/31/2024

0011498458

MGP AMP-100 Certificate of Calibration

2/11/2024

0011503964

Eberline RO20 Certificate of Calibration

2/06/2024

0011504144

MGP Telepole WR Certificate of Calibration

2/06/2024

0011532147

Eberline RO20AA

07/08/2024

0011540882

Ludlum Model 3 Certificate of Calibration

05/30/2024

0011565521

Eberline AMS-4 Certificate of Calibration

09/16/2024

CY-LA-130-310

Post Calibration Geometry Check Worksheet

05/02/2024

RP-AA-700-1215

Air Sampler Calibration Data Sheet

08/12/2024

RP-AA-700-1216

RADeCO H-810 Calibration Data Sheet

07/28/2024

RP-AA-700-1235

PM-12 Calibration Data Sheet

08/08/2023

RP-AA-700-1239

SAM-12 Calibration Data Sheet

2/27/2023

Calibration

Records

RP-AA-700-1240

ARGOS-5 Calibration Data Sheet

2/19/2023

71124.05

Corrective Action

AR 4719094

Unable to Access ARM for Source Check

11/21/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4721021

Unable to Complete Weekly Surveillance of 1PL75J

2/01/2023

AR 4753508

RP-LA-716ARM Source Check Completed Past Crit Date

2/27/2024

Documents

AR 4804004

OOT Not Completed in Timely Manner

09/24/2024

Corrective Action

Documents

Resulting from

Inspection

AR 4812059

NRC Identified Out of Spec Value in IMD Data Table

10/25/2024

RP-AA-232

Operation of the Whole-Body Counter (WBC) Using

Apex-InVivo

RP-AA-700-1216

Calibration of Hi-Vol Air Samplers

RP-AA-700-1235

Operation and Calibration of the PM-12 Gamma Portal

Monitor

RP-AA-700-1305

Operation and Calibration of the AMP-50/100/200

RP-LA-710

Source Response Testing and Calibration of the General

Atomic ARM (Reboiler Steam Outlet and HRSS Room)

RP-LA-713

Determination of Liquid PRM HI Alarm Setpoints

RP-LA-716

Area Radiation Monitor (A.R.M.) Source Checks

Procedures

RP-LA-720

Station Vent Stack and Standby Gas Treatment Stack Wide

Range Gas Monitor Effluent Release Rate Alarm Setpoints

AR 4469158

22 Radiation Instrumentation Self-Assessment

2/27/2022

AR 4469159

Exelon Power Labs Self-Assessment

08/11/2022

Self-Assessments

NCS-23-001

Annual Review of Process of Performing Weekly

Performance Source Checks for Portable Radiation Survey

Instruments

03/31/2023

WO 5062148

Unit 02 Service Water Effluent Radiation Monitor Calibration

01/03/2023

WO 5141982

LRA SBGT WIDE RNG GAS MON

06/19/2023

WO 5161386

Post Acc Div II CNMT Gross Gamma Rad Mon

11/28/2023

WO 5204708

Fuel Pool Exhaust Radiation Monitor Calibration

04/25/2024

Work Orders

WO 5469686

U2 DW Gross Gamma PPC Point Spurious Alarm

05/08/2024

AR 4709273

PPC Point D483 Shows RCIC CY Suction Vlv 1E51-F010

Not Open

10/13/2023

AR 4712710

Unexpected Alarm for 2A DG Cooling Water Strainer D/P Hi

10/26/2023

71151

Corrective Action

Documents

AR 4718031

U2 D RHR WS Pump Seal Leak When Running

11/16/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

AR 4718222

MSPI Reporting Review by NRC

11/16/2023

AR 4722895

U1 RCIC Governor Valve Indicating Closed When Throttled

2/11/2023

AR 4755464

MCR Unexpected Alarms 2PM01J-A109, 2PM01J-A201

250VDC UV

03/04/2024

AR 4756691

1E51-F019 Breaker Tripped during RCIC Run

03/09/2024

AR 4764916

Unit 2 Div 2 RHRWS Pumps in Alert Range

04/10/2024

AR 4797322

NOS ID: Oil Weeping From 1A EDG Cooling Water Pump

08/28/2024

AR 4828295

Unknown Cause in Change in the IST Dp for 2C & 2D

RHRWS pps

01/08/2025

Corrective Action

Documents

Resulting from

Inspection

AR 4829990

NRC IDed: CSCS MSPI Reporting in May-2024

01/15/2025

Miscellaneous

LS-MSPI-001

LaSalle County Nuclear Generating Station Mitigating

System Performance Index (MSPI) Basis Document

LS-AA-1240

Monthly Data Elements for NRC ROP Indicator -

Occupational Exposure Control Effectiveness

Various

LS-AA-2090

Monthly Data Elements for NRC ROP Indicator - Reactor

Coolant System (RCS) Specific Activity

Various

LS-AA-2150

Monthly Data Elements for NRC ROP

Indicator -RETS/ODCM Radiological Effluent Occurrences

Various

Procedures

LS-AA-2200

Mitigating System Performance Index

Data Acquisition & Reporting

Work Orders

WO 5527960

2B RHR WS Biennial Comprehensive IST Pump Test

05/14/2024

AR 1041521

1B DG Fuel Line Leak

03/11/2010

AR 1095832

NRC Questions on 1B EDG Fuel Line IR 1041521

07/28/2010

Corrective Action

Documents

AR 4811034

Diesel Fuel Leak on U1 HPCS DG During 24hr Run

10/21/2024

Engineering

Evaluations

ECR 396464

NRC Questions on 1B EDG Fuel Line IR 1041521

07/25/2011

Miscellaneous

LAS-89656

Evaluation of a Leaking Fuel Oil Line Connection from the

1B EDG at LaSalle Station

04/13/2010

71152A

Work Orders

WO 1336535

MM Replace EDG Fuel Lines

10/02/2013

05000373,

05000374/2023-

2-01

LaSalle County Station, Units 1 & 2, Supplement to Air

Circuit Breaker (ACB) Mechanically Operated Contacts

(MOC) Switch Failed to Actuate

10/09/2024

ReMA L1C21-

10PST

Reactivity Maneuver Approval (ReMA) Plan L1C21-10PST

for November 2024 Power Suppression Test

11/21/2024

71153

Miscellaneous

ReMA Plan 2025

December Control

Rod Exchange

Reactivity Maneuver Approval (ReMA) Plan L1C21-10PST

for November 2024 Power Suppression Test

1