IR 05000369/2016005

From kanterella
Jump to navigation Jump to search
Mid-Cycle Assessment Letter for McGuire Nuclear Station Units 1 and 2 (NRC Inspection Report 05000369/2016005 and 05000370/2016005)
ML16244A136
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 08/31/2016
From: Frank Ehrhardt
Division Reactor Projects II
To: Capps S
Duke Energy Carolinas
References
IR 2016005
Download: ML16244A136 (6)


Text

UNITED STATES ust 31, 2016

SUBJECT:

MID-CYCLE ASSESSMENT LETTER FOR MCGUIRE NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000369/2016005 AND 05000370/2016005)

Dear Mr. Capps:

On August 9, 2016, the Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of the McGuire Nuclear Station, Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2015 through June 30, 2016. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, McGuire Nuclear Station operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at McGuire Units 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2018. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the second half of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections which will be sent via separate, non-publicly available correspondence.

The NRC staff completed Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans at McGuire on July 29, 2016, to confirm full implementation of orders Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The results of the inspection can be found in inspection report 05000369/2016009 and 05000370/2016009.

In Staff Requirements Memorandum - SECY 16-0009, Recommendations Resulting from the Integrated Prioritization and Re-Baselining of Agency Activities, the Commission approved the NRC staff recommendation to discontinue the formal mid-cycle assessment process beginning in calendar year 2017. This will be the final mid-cycle assessment letter. The staff will continue to conduct quarterly assessment meetings and communicate changes in the assessment of licensee performance in accordance with the guidance in Inspection Manual Chapter 0305, Operating Reactor Assessment Program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 404-997-4611 with any questions you have regarding this letter.

Sincerely,

/RA/

Frank Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-369, 50-370 License Nos.: NPF-9, NPF-17 Enclosure: McGuire Inspection/Activity Plan (09/01/2016 - 06/30/2018)

cc: distribution via ListServ

_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE RII:DRP RII:DRP RII:DRP SIGNATURE MMT2 JGW1 FJE NAME M. Toth J. Worosilo F. Ehrhardt DATE 8/25/2016 8/25/2016 8/25/2016 8/ /2016 8/ /2016 8/ /2016 8/ /2016 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO Letter to Steven from Frank Ehrhardt dated August 31, 2016 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR MCGUIRE NUCLEAR STATION UNITS 1 AND 2 (NRC INSPECTION REPORT 05000369/2016005 AND 05000370/2016005)

DISTRIBUTION:

D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMMcGuire Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

Page 1 of 2 McGuire 08/31/2016 06:56:54 Inspection / Activity Plan Report 22 09/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site MODS - PLANT MODIFICATIONS INSPECTION 4 1, 2 09/12/2016 09/16/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 09/26/2016 09/30/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications RP - RAD HAZARDS 1 1, 2 04/03/2017 04/07/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls ISI - UNIT 2 IN-SERVICE INSPECTION 1 2 04/10/2017 04/14/2017 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 2 SG IN-SERVICE INSPECTION 1 2 04/17/2017 04/21/2017 IP 7111108P Inservice Inspection Activities - PWR RP - RP PUBLIC RAD SAFETY BASELINE 3 1, 2 06/05/2017 06/09/2017 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 06/05/2017 06/09/2017 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 06/05/2017 06/09/2017 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation EP - EP EXERCISE INSPECTION 3 1, 2 08/07/2017 08/11/2017 IP 7111401 Exercise Evaluation 1, 2 08/07/2017 08/11/2017 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 08/07/2017 08/11/2017 IP 7111408 Exercise Evaluation - Scenario Review 1, 2 08/07/2017 08/11/2017 IP 71151 Performance Indicator Verification ISI - UNIT 1 IN-SERVICE INSPECTION 1 1 10/02/2017 10/06/2017 IP 7111108P Inservice Inspection Activities - PWR SGISI - UNIT 1 SG IN-SERVICE INSPECTION 1 1 10/09/2017 10/13/2017 IP 7111108P Inservice Inspection Activities - PWR CDBI - COMPONENT DESIGN BASES INSPECTION 6 1, 2 03/05/2018 03/10/2018 IP 7111121 Component Design Bases Inspection 1, 2 03/26/2018 03/30/2018 IP 7111121 Component Design Bases Inspection 1, 2 04/09/2018 04/13/2018 IP 7111121 Component Design Bases Inspection 1, 2 04/23/2018 04/27/2018 IP 7111121 Component Design Bases Inspection EP - EP PROGRAM INSPECTION 3 1, 2 06/18/2018 06/22/2018 IP 7111402 Alert and Notification System Testing 1, 2 06/18/2018 06/22/2018 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 06/18/2018 06/22/2018 IP 7111404 Emergency Action Level and Emergency Plan Changes 1, 2 06/18/2018 06/22/2018 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 06/18/2018 06/22/2018 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure

Page 2 of 2 McGuire 08/31/2016 06:56:54 Inspection / Activity Plan Report 22 09/01/2016 - 06/30/2018 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site HS - TRIENNIAL HEAT SINK PERFORMANCE 1 1, 2 06/25/2018 06/29/2018 IP 7111107T Heat Sink Performance This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures. Enclosure