IR 05000354/2025012
| ML25037A009 | |
| Person / Time | |
|---|---|
| Site: | Hope Creek |
| Issue date: | 02/06/2025 |
| From: | Glenn Dentel Division of Operating Reactors |
| To: | Mcfeaters C Public Service Enterprise Group |
| References | |
| IR 2025012 | |
| Download: ML25037A009 (1) | |
Text
February 6, 2025
SUBJECT:
HOPE CREEK GENERATING STATION - FIRE PROTECTION TEAM INSPECTION REPORT 05000354/2025012
Dear Charles McFeaters:
On January 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Hope Creek Generating Station and discussed the results of this inspection with Robert McLaughlin, Nuclear Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Glenn T. Dentel, Chief Engineering Branch 2 Division of Operating Reactor Safety
Docket No. 05000354 License No. NPF-57
Enclosure:
As stated
Inspection Report
Docket Number:
05000354
License Number:
Report Number:
Enterprise Identifier: I-2025-012-0005
Licensee:
Facility:
Hope Creek Generating Station
Location:
Hancocks Bridge, NJ
Inspection Dates:
January 13, 2025 to January 30, 2025
Inspectors:
L. Cline, Senior Reactor Inspector
E. Miller, Senior Reactor Inspector
J. Tifft, Senior Reactor Inspector
Approved By:
Glenn T. Dentel, Chief
Engineering Branch 2
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a fire protection team inspection at Hope Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21N.05 - Fire Protection Team Inspection (FPTI)
Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===
The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis or safe shutdown analysis (SSA).
- (1) Fire Detection System
- (2) Fire Barrier System
- (3) Reactor Core Isolation Cooling System
- (4) Emergency Diesel Generator 'A'
Fire Protection Program Administrative Controls (IP Section 03.02) (2 Samples)
The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees Fire Protection Program (FPP) contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.
- (1) Control of Transient Combustibles
- (2) Fire Brigade Training, Drills, and Qualification
Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)
The inspectors verified the following:
a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.
b. The adequacy of the design modification, if applicable.
c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.
d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, fire hazards analysis, and SSA were updated consistent with the FPP or design change.
e. Post-fire safe shutdown operating procedures, such as abnormal operating procedures, affected by the modification were updated.
- (1) Time Critical Actions Revalidation
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On January 30, 2025, the inspectors presented the fire protection team inspection results to Robert McLaughlin, Nuclear Plant Manager, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21N.05 Corrective Action
Documents
20880344
20898243
20899016
20941160
20981379
20946992
20967574
20971380
20972669
20980170
20898424
Corrective Action
Documents
Resulting from
Inspection
20983334
20985279
20985414
20985602
20985610
20985611
20985613
20985616
20985639
20985927
20986162
20986168
20986183
20986184
20986528
20986531
20986541
20986591
Drawings
E-1521-1 Sheet 2 Raceway Plan Reactor Building Area 14 Plan Elevation
54'-0"
Revision 24
E-1522-1 Sheet 1 Raceway Plan Reactor Building Area 14 Plan Elevation
Revision 26
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
77'-0"
E-1523-1 Sheet 1 Raceway Plan Reactor Building Area 14 Plan Elevation
2'-0"
Revision 30
E-1531-1 Sheet 2 Raceway Plan Reactor Building Area 13 Plan Elevation
54'-0"
Revision 28
E-1631-1 Sheet 2 Raceway Plan Reactor Building Area 22 Plan Elevation
54'-0"
Revision 25
E-1683-1
Raceway Plan Aux. Building D/G Area 28 plan at
Elevation 102'
Revision 34
E-1685-1
Raceway Plan Aux Building D/G Area 28 plan at Elevation
130'
Revision 29
Engineering
Evaluations
HC.ER-PS.FP-
0001-A5
Combustible Loading Calculation Methodology and Fire
Hazard Analysis for Turbine and Radwaste Building
Revision 0
VTD 430049
Volume 002
EPU TR T0611 - Appendix R/Fire Protection
11/16/2005
Miscellaneous
AC1G0601P
AP1G0636B
Cable Pull Cards 'A' Emergency Diesel Generator
01/16/2025
AC1G0601P
AP1G0636B
Cable Reports for 'A' Emergency Diesel Generator
01/16/2025
BL1Q0310A
BL1Q0310E
BP1Q0310B
BP1Q0310C
BP1Q0310D
Cable Pull Cards RCIC Feedwater Isolation Valve F013
01/13/2025
BL1Q0310A
BL1Q0310E
BP1Q0310B
BP1Q0310C
BP1Q0310D
Cable Reports RCIC Feedwater Isolation Valve F013
01/13/2025
HC.ER-PS.FP-
0001-A3
Hope Creek Fire Protection Report - Safe Shutdown
Analysis
Revision 0
NOSA-HPC-23-
Limited Scope Fire Protection Audit Report
05/31/2023
Demonstrating the Feasibility and Reliability of Operator
October
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Manual Actions in Response to Fire
2007
Order 80131728-
0070
Operations Time Validation Sheet - TCA-3 and TCA-4
11/27/2025
Order 80131728-
0090
Operations Response Time Validation Sheet - TCA-6
10/18/2024
Order 80131728-
0130
Operations Response Time Validation Sheet - TCA-12
01/27/2025
Updated Final
Safety Analysis
Report
Revision 26
Procedures
Fire Protection Surveillance and Periodic Test Program
Revision 8
Control of Transient Combustible Material
Revision 9
Fire Protection Training Program
Revision 7
HC.FP-ST-QK-
29(F)
Class 1 Fire Detection Functional Test
Revision 19
HC.FP-SV.ZZ-
26(F)
Flood and Fire Barrier Penetration Seal Inspection
Revision 9
HC.FP-SV.ZZ-
0056(F)
Fire Barrier Inspection
Revision 8
HC.FP-SV.ZZ-
0078(F)
Drywall Fire Barrier Inspection
Revision 6
Operator Response Time Program
Revision 2
OP-HC-102-106
Hope Creek Master List of Timed Actions
Revision 7
OP-HC-102-106-
F1
Master List of Timed Actions
Revision 2
OP-HC-108-101
Key Control - Hope Creek
Revision 3
Control of Security Locks, Keys, Cores and Combination
Locks
Revision 15
Work Orders
251906
229301