IR 05000333/1985015

From kanterella
Jump to navigation Jump to search
Insp Rept 50-333/85-15 on 850512-15.No Violations Observed. Major Areas Inspected:Containment Leakage Testing Area, Including Containment Integrated Leak Rate Test,Test Results Review & General Tours of Facility
ML20134E969
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/05/1985
From: Elsegroth P, Hodson J, Vito D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20134E958 List:
References
50-333-85-15, NUDOCS 8508200628
Download: ML20134E969 (5)


Text

e

.

.

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report N /85-15 Docket N License N DPR-59 Priority -

Category C Licensee: New York Power Authority __

P.O. Box 41 Lycoming, New York 13093 Facility Name: James A. FitzPatrick Nuclear Power Plant Inspection At: Scuba, New York Inspection Conducted: May 12 - 15, 1985 Inspectors: MfTI D. J./Vito, Reactor Engineer 'ldath SQth6 dson, s

rictor Engineer nlulic Idath ~

Approved by: P, [

. Eslegroth, Chief, Test Programs ' date Section, DRS Inspection Summary: Inspection on May 12-15, 1985 (Inspection Report No. 50-333/85-15)

Areas Inspected: Routine, announced inspection of the containment leakage testing area including CILRT witnessing, test results review and general tours of the facility. The inspection involved 70 inspection-hours onsite by two region based inspector Results: No violations were identifie $DR ADOCK 0500 333 ,

PDR

n

,

.

DETAILS 1.0 Persons Contacted New York Power Authority

  • Fernandez, Operations Superintendent
  • H. Glovier, Resident Manager
  • J. Greene, Operating Experience Engineer, Ass L. Johnston, QA Supervisor
  • H. Keith, I&C Superintendent
  • P. Swinburne, Performance Engineer, ILRT Test Director Stone and Webster
  • R. Bone
  • Busa
  • R. Samson NRC
  • L. Doerflein, Senior Resident Inspector

2.0 Containment Integrated Leak Rate Testing 2.1 Documents Reviewed

-

Procedure F-ST-39F, Type A Test (60 psi) Primary Containment Integrated Leak Rate Test, Rev. 4, March 27,1983 (as-run copy)

-

CILRT Instrumentation Records

-

CILRT Log Book

-

Test Results

-

Selected Piping and Instrument Drawings 2.2 Scope of Review The inspector reviewed the above listed documents for technical ade-quacy and to determine compliance with the regulatory requirements of

. Appendix J to_10 CFR 50, Technical Specifications and applicable in-dustry standards. The inspector witnessed portions of the CILRT and the subsequent verification test. The inspector also performed an independent calculation of the test result *

.

.

2.3 Procedure Review The inspector reviewed the "as-run" copy of Procedure F-ST-39F to determine if appropriate' changes had been made as a result of pre-vious inspection findings (50-333/85-08). The inspector determined that appropriate changes had been made, including the use of instan-taneous data values to calculate the leak rate. Several of the CILRT valve lineups were verified during the performance of the test. The test log and test data were maintained in accordance with the proce-dur No unacceptable conditions were identifie .4 CILRT Instrumentation The inspector reviewed the calibration records for the resistance temperature detectors, devices and precision pressure detectors. The calibrations met applicable accuracy requirements and were traceable to the National Bureau of Standards. The inspector also reviewed the calibration curves for the flow meter used during the superimposed leak verification test. The validity of the flow meter readings were questioned during a previous inspection (50-333/85-08) because the data sheet for the flow meter did not state whether it could be used in the 50-100 psi pressure range. The manufacturer provided the licensee with documentation stating that the instrument was suitable for use in the 50-100 psi range. The instrument performed accurately during the verification tes No unacceptable conditions were identifie .5 Test Witnessing / Chronology A large portion of the CILRT and subsequent verification test was witnessed by the inspector. Inspector observations of licensee test performance and test control are delineated in Section 2.6 of this report. The test chronology was as follows:

Test Chronology 5/13/85 0600 Commenced containment pressurization after resolution of torus water level problems 1230 Reached test pressure, commenced temperature stabili-zation period 1630 Completed temperature stabilization period. Accep-tance criteria met. Commenced taking data for CILRT

r-

'

,o

.o-

2000 Test personnel note that measured mass appears to be in-creasing. Investigations reveal a large water leak into the torus from a relief valve on the RHR Shutdown Cooling line. Test director decides to continue with the test and account for the torus level change at the end of the test 5/14/85 1630 Completed taking data for CILRT i

Measure Leak Rate at 95% UCL =

-0.23952 wt%/ day Type B & C leakage correction

0.0416 wt%/ day Water Level Correction

0.44015 wt%/ day Total Leak Rate = -0.23952 +

0.0416 + 0.44015 = 0.24223 wt%/ day Acceptance criterion = 0.75 La

= 0.375 wt%/ day 1730 Commenced data collection for superimposed leak verifi-cation test 2130 Verification test completed. Acceptance criteria me .6 Test Performance / Control The test was performed strictly within the procedural guideline The inspector also noted that the licensee had attempted (after the completion of the verification test) to isolate the water leak into the torus to try to measure the leak rate directly with the instru-mentation. Although the licensee was not successful in stopping the leak, the inspector commended them for making the attemp No unacceptable conditions were identifie .7 Test Results Review The calculated leakage rate at the 95% Upper Confidence Limit (UCL)

was -0.23952 wt%/ da The leakage correction for Type B and C pene-trations isolated or in use during the CILRT totalled 0.0416 wt%/ da The water level correction for changes in the reactor vessel, torus, and drywell equipment sump water level was 0.44015 wt%/ da The sum of these values (0.24223 wt%/ day) reflects the "As-Left" integrated leak rate and is below the allowable limit of 0.75 La (0.375 wt%/ day).

,

,,

,

.

The inspector performed an independent calculation of the test results using a sample of raw data from the test to estimate the accuracy of the licensee's leak rate and volume correction calculations. The in-spector's calculated results were identical. The inspector concluded that the licensee's calculations were appropriately performed and ac-curate and that the test was successfu The CILRT was followed by a successful superimposed leak verification test. The licensee imposed a leak of 0.5005 wt%/ day onto the exist-ing leak. The measured verification test leak rate was 0.32608 wt%/ da The result was within the acceptance criteria band. The inspector also verified this result by independent calculatio The licensee also stated that an "As-Found" leak rate calculation would be performed and reported in the CILRT final repor No unacceptable conditions were identifie .0 Independent Calculations The inspector performed independent calculations of the CILRT and verifi-cation test results. Details are included in Section 2.7 of this repor .0 QA/QC Involvement The inspector verified QA/QC involvement in CILRT activities by observa-tion of the QA personnel monitoring the test. The inspector also re-viewed two QA Surveillance Reports (Nos. 1014 and 1021) to determine the QA coverage of local leak rate testing activities. This had been indi-cated as an area of concern in Inspection Report 50-333/85-08 since the last audit of the LLRT area had been performed in 1980. During this previous inspection, the inspector found the surveillance to be satis-factory but asked that QA pay more attention to the scheduling of LLRT surveillances in the future. The licensee acknowledged that because of the frequency of local leak rate testing, the audit sampling process could create a long time between audits, as happened in this case. The licensee agreed that attempts would be made to preclude this from recurrin .0 Tours The inspector toured the reactor building and other areas of the facility to observe containment leakage testing activities, component tagging, other work in progress, and general housekeepin No unacceptable conditions were identifie .0 Exit Meeting A meeting was held on May 15, 1985, to discuss the scope and finaings of the inspection as delineated in this report. At no time during this in-

!

spection was written information provided to the licensee.

<