IR 05000322/1981014

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-322/81-14 on 810801-31.Noncompliance Noted: Authorization Block Not Signed on Tags,Fuses Installed in Remote Shutdown Panel & Control Room Set of Procedures Not Current
ML20010J648
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 09/09/1981
From: Higgins J, Kister H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20010J643 List:
References
50-322-81-14, NUDOCS 8110060312
Download: ML20010J648 (7)


Text

.

.

.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT Region I Report No. 50-322 / 81-14 Docket No.

50-322 B

License No. CPPR-96 Priority

_

Category

--

Licensee:

Long Island Lichting Company 175 East Old Country Road Hicksville, New York 11801 Facility Name: Shoreham Nuclear Power Station, Unit 1 Inspection at: Shoreham, New York Inspection condacted: August 1 - 31, 1981 7!3 h

h

/

Inspectors:

,

date signed

[ ~C'. hins, Senior Resident Inspector date signed

.

date signed

[w

/9

/

Approved by:

Ff. B. Kist'er,Mief, Reactor Projects Section 1C date/ signed

~

Projects Branch #1, DRPI Inspection Summary:

Inspections on:

August 1 - 31, 1981 (Inspection Report No. 50-322/81-14)

Areas Inspected: Routine onsite regular a11 backshift inspections by the resident inspector (91 inspection hours) of work at tivities, preoperational testing, and plant staff activities including:

tours of the facility; test witnessing; review of test procedures; review of plant tagging systems; witnessing of feedwater sparger installation and, followup on previous inspection findings.

.

P.esults: Cf the seven areas inspected, no vio;otions were identified in six areas and one in the seventh area (failure to follow procedures, paragraph 7).

Regicn I Fora 12

$h

-

FDR

- _ _ _ _ _ _ - _ - - _ _ _ _ _ _ _ _ - _ _ - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - - _ _ - _ _ _ _ _ _ - _ _ _ _ - - _ _ _ _ - _ _ _ - _ - _ - _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _

_

- -

.

-

.

.

,

.

DETAILS 1.

Persons Contacted T. Autagne, Site Me ager (RCI)

D. Durand, Lead Startup Engineer (L)

T. Gerecke, Quality Assurance Manager (L)

J. Kelly, Field QA Manager (L)

W. Matejek, Lead Advisory Engineer (S&W)

B. McCaffrey, Manager, Project Engineering (L)

J. Morin, Senior Licensing Engineer (L)

A. Muller, Acting 00A Engineer (L)

R. Reen, Site Security Supervisor J. Riley, Lead Startup Engineer (GE)

W. Steiger, Chief Operating Engineer (L)

D. Terry, Assistant Startup Manager (L)

E. Youngling, Startup Manager (L)

GE - General Electric L

- Long Island Lighting Company RCI - Reactor Controls, Inc.

S&W - Stone and Webster The inspectar also held discussions with other licensee and contractor personnel during the course of the inspection including management, clerical, maintenance, operations, engineering, testing, quality assurance and contruction personnel.

2.

Pr0vious Inspection Item Update

(closed) Inspector Follow Item (322/81-06-02): ECCS Suctian Strainer Testing:

In letters.to the NRC numbered SNRC-598 and SNRC-602, the licensee has committed to verify the flow capability of both the HPCI and RCIC pumps with their suction strainers 50% plugged during the Preoperational Test Program. 7: 1s addresses the inspector's concern and the item is closed.

(open) Unresolved Item (322/81-04-07): Alarm Response Procedures (ARPs):

Startup Instruction No.1, Rev. 5 now specifies the review and updating of ARPs. The inspector noted that not all ARPs, for annunciators under startup control (blue dotted) or under plant staff control (no dots), have been updated.

This item remains open pending the review and updating of ARPs already in use.

3.

Plant Tour a.

Discussion The inspector conducted periodic tours of accessible areas in the plant during normal and backshift hours.

During these tours, the following specific items were evaluated:

-- Hot Work: Adequacy of fire prevention / protection measures used.

-- Fire Equipment: Operability and evidence of periodic inspection of fire suppression equipment.

.

'

.

-3-

-- Housekeeping: Minimal accumulations of debris ard maintenance of required c'eanness levels of systems under or following testing.

-- Equipment Preservation: Maintenance of special precautionary measures for installed equipment, as applicable.

-- Component Tagging:

Implementation and cbservance of equipment tagging for safety, equipment protection, and jurisdiction.

-- Logs: Completeness of logs maintained.

-- Security: Adequate site lanstruction security.

,

-- Post-Accident Radiation Monitors: Discussions with licensee and NRC representatives regarding adequacy of monitors per NUREG-0737 item II.F.1 and plant tours to observe equipment locations and arrangements.

-- Weld Rod Control: Observations to determine weld rod was being controlled in accordance with site procedures.

With the exception of the below item and those in paragraph 7, no discrepancies were identified.

b.

Plant Stack All plant, gaseous, potentially radioactive, effluents exit in the main station exhaust stack. The Reactor Building Standby Ventilation System (RBSYS) exits the Reactor Building and then according to FSAR Fiqure 6.2.3-1 and NUREG-0737 Item II.F.1 submittal, enters into the station exhaust stack.

The inspector noted on tcurs that the RBSYS actually h&s its own smaller stack which runs next to the station exhaust stack. Licensee representatives were unable to explain the differences during the inspection. This item is unresolved pending action to makc the plant and the licensing submittals agree and is designated as unresolved item no. (322/81-14-03).

4.

Test Witnessing a.

Discussion The inspector witnessed portions of the below tests:

- CG.000.012, " Insulation Resistance of Flectrical Equipment", performed on the Reactor Building Closed Loop Cooling Water (RBCLCW) System Pumps;

- CG.000.014, " Motor Operated Valve Static Test" performed on RBCLCW valves; and;

- CG.000.022, "480V AC MCC Cubicle and Control Circuit Test" performed on RBCLCW valve motor circuitry.

l-

-. - _

,-_., - _ _. - _ _,,

-

-

.- -_

- - -. - - -

'

.

-4-Duri g the tests the inspector noted that:

- the test procedure was approved and released for performance as required;

- test procedure was in use by pctsonnel performing the test;

- test personnel were suitably qualified;

- test exceptions and problem areas were appropriately documented;

- test instrumentation was properly calibrated;

- data was properly logged; and

- test acceptancs criteria were met for portions observed or appropriate action taken to initiate corrective action.

With the exception of the below item no discrepancies were identified.

b.

Valve Stroke Times The inspector noted that the valve stroke times specified ou procedure CG.000.014 data sheets did not agree with the FSAR c31ues in Table 6.2.4-1 in some cases.

For example, the times for containment isolation valves P42*M0V-035, 036, 047 and 048 for the RBCLCW System were listed 60 seconds on the data sheets but 23 seconds in the FSAR. The inspector questioned how the data sheet values for valve stroke times were determined. The licensee's representative stated that this area would be reviewed. This item is unresolved and is designated unresolved item no. (322/81-14-02).

c.

Halon Fire Protection System Test The Remote Shutdown Panel is located in the Reactor Building and is protected from fire by a local, total flooding, Halon fire protection system. The inspector noted that the system was scheduled for its final startup testing durinc the inspection period using a vendor test, which was not reviewed or appraved by the Startup organization. The response te FSAR question 413.26 cor.mits to testing the fire protection systems using approved preoperational tests (pts). The Startup Manual, Section 7.6.1 and

.6.2 requires that all Checkout and Initial Operations Tests be done to approved procedures and that vendor tests to be used be subnitted for appropriate approval. The vendor test was performed, out the licensee stated that no credit would be taken for the test and that a preoperational test (PT) would be written, approved, and performed on the Halon System. This iter, is unresolved pending inspector review of an approved PT for the Halon System and is designated item no.

(322/81-14-04).

<

-

.

.

.

-

....

-.

-5-5.

Feedwater Spargers a.

Documentation Reviewed

-- NUREG-0619, "BWR Feedwater Nozzle and Control Rod Drive Return Line Nozzle Cracking"

-- SER Open Item #13 response, "Feedwater Nozzle and Control ' Rod Return Line-Cracking" from SNRC-566.

-- E&DCR F20462A and FDI 84/88 524, Installation instructions for feed-water spargers.

-- E&DCR F36548 and FDDR KS-01-460, Disposition for incorrectly assembled feedwater spargers.

-- Pertinent drawings.

.

-- NEDE-21821-A, " Boiling Water Reactor Feedwater Nozzle /Sparger Final Report".

b.

Scope and Findings Over the past several years feedwater nozzle cracking has been a ' problem at Boiling Water Reactors. NUREG-0619 describes the problem and proposed solutions. The licensee has comitted to portions of these sclutions.

The inspector observed the newly designed interference fit triple sleeve feedwater spargers and the unclad feedwater nozzles and compared the various design features to those described i;. the above documents.- The inspector-also witnessed selected portions of the assembly,. repair and installation into the Reactor Vessel of the feedwater spargers and noted that selected procedural and drawing requirements were being met. The inspector also noted that contmls were being maintained over. personnel and equipment entry into the Reactor Vessel.

Based on the review of the above documents and selected observations, the inspector noted that licensee comittments to the NRC and specificatien requirements were met.

6.

Cable Pulling Lubricant The cable pulling lubricant, Flaxoap has been reported by another licensee -

to-have the potential for becoming fluid at high temperatures, running out of conduit into junction or control boxes, and shorting out electrical connections since the fluid is conouctive. The inspector discussed this problem with the licensee and requested that the licensee determine if a similar condition may exist at this site. The licensee determined that Flaxoap was not used at Shoreham and that of the two lubricants used onsite, one turns to powder when-heated and the other dries to a wax filn. which is not conductive if it should mel t.

The inspector had ~no further cuestions in this area.

t

-

-

.

....

.

-6-l 7.

Tagging Systems a.

Documents Reviewed LILC0 Startup Manual S.P.12.035.01, Rev. 2, " Control of Lif ^ed Leads and Jumpers" S.P.12.006.02, Rev.10. " Station Procedures - Control and Distribution" Str

"n Jumper Records Plant Staff Lifted Lead and Jum;1r Log Various Tagout Logs Active tags and jumpers b.

Discussion The inspector reviewed plant tagging systems in the following arcas:

- Jurisdictional tagging; yellow construction tags, blue startup tags and green plant staff tags;

- Danger tags; red tags used by startup and plant staff; and

- Jumper and lifted Lead systems in use by startup and by the plant staff.

The inspector reviewed the controlling documents or procedures; sampled the log books, files, permit sheets and tagout sheets; observed the installation and crorer ussge of tags in the plant; and toured various areas of the plant, parti olarly inside control panels and motor control center cubicles, to dC-.ine if components or wires were operated or lifted without implerrenting tagging as required. The bel:v discrepancies were identified during the review and are collectively designated as a violation (322/81-14-01).

c.

Findings 10 CFR 50, Appendix B, Criterion V, FSAR section 17.2.5 and the LILC0 Operational QA Manual section 5.3.1 require that activities be accomplished in accordance with instructions. The LILC0 Startup Manual and Station Procedures provide detailed instructions for implementing the various tagging systems.

Contrary to these requirements: leads were found lifted with no tags hung, jumper tags were placed without being authorized; fuses, red tagged as pulled, were found installed; components were yellow and blue tagged simultar.eously; expected durations of jumpers were not included on permits; jumpers were removed but the permit and log were not updated; and the main controi room set of controlled procedures had an outdated revision of the lifted lead and jumper procedure. During the inspection period the licensee corrected each of the above items except the missing expected durations of jumpers, t

.

.

....

'

.

-7-The inspector also noted that the jumpers installed per plant staff jumper permit no. 79-05-01 still had startup jumper tags on them,

,

which had been hung in 1978.

The system was turned over to the plant staff jurisdiction in October,1978. The startup jumper tags were promptly cleared.

8.

Unresolved Items Areas for wF.ich more information is required to determine acceptability are considered unresolved. Unresolved items are contained in Paragraphs 3, 4 and 7 of this report.

,

9.

Management Meetings At periodic intervals during the ccurse of this inspection, meetings were held with plant management to discuss the scope and findings of this inspection.

The resident inspector also attended the exit interviews for two inspections conducted by region-based inspectors during August.

!

I I

i l

i l

l

..

-

-

- -

-

--

~

.