IR 05000321/2024004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 5000321/2024004 and 05000366/2024004
ML25030A356
Person / Time
Site: Hatch  
Issue date: 02/05/2025
From: Alan Blamey
NRC/RGN-II/DORS/PB3
To: Coleman J
Southern Nuclear Operating Co
References
IR 2024004
Download: ML25030A356 (1)


Text

SUBJECT:

EDWIN I. HATCH - INTEGRATED INSPECTION REPORT 05000321/2024004 AND 05000366/2024004

Dear Jamie Coleman:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Edwin I. Hatch. On January 8, 2025, the NRC inspectors discussed the results of this inspection with Matthew Busch, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Alan J. Blamey, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000321 and 05000366 License Nos. DPR-57 and NPF-5

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000321 and 05000366

License Numbers:

DPR-57 and NPF-5

Report Numbers:

05000321/2024004 and 05000366/2024004

Enterprise Identifier:

I-2024-004-0017

Licensee:

Southern Nuclear Operating Company, Inc.

Facility:

Edwin I. Hatch

Location:

Baxley, GA

Inspection Dates:

October 01, 2024 to December 31, 2024

Inspectors:

J. Bundy, Senior Operations Engineer

R. Easter, Resident Inspector

D. Johnson, Sr Emergency Preparedness Specialist

P. Niebaum, Senior Resident Inspector

A. Nielsen, Senior Health Physicist

K. Schaaf, Operations Engineer

Approved By:

Alan J. Blamey, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Edwin I. Hatch, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000321/2024-004-00 LER 2024-004-00 for Edwin I. Hatch Nuclear Plant, Unit 1 Manual Reactor Trip During Hurricane Helene Due to Degrading Condenser Vacuum 71153 Closed NOV 05000321,05000366/20 2409001 Failure to Conduct Radiation Surveys EA-23139 92702 Closed NOV 05000321,05000366/20 2409002 Incomplete and Inaccurate Radiation Surveys EA-23139 92702 Closed

PLANT STATUS

Unit 1 began the inspection period in mode 4 following the September 27, 2024 manual scram due to a degrading main condenser vacuum associated with Hurricane Helene. On October 2, the unit was restarted and began raising power. On October 6, the unit achieved 100% rated thermal power (RTP). On December 14, 2024, power was reduced to approximately 70% RTP to perform a sequence exchange and main turbine valve testing. Operators began raising power and reached full RTP on December 15, 2024. The unit remained at or near RTP for the remainder of the inspection period with limited exceptions for planned evolutions such as rod pattern adjustments on December 17, 2024 and December 18, 2024.

Unit 2 began the inspection period at or near RTP. On December 7, 2024, the unit lowered power to approximately 70% RTP to perform main turbine valve testing. On December 9, 2024, the unit was raised to approximately 90% RTP. The unit remained at or near 90% RTP (due to isolation of two feedwater heaters) for the remainder of the inspection period with limited exceptions for planned evolutions such as rod pattern adjustments on November 16, 2024 and December 4,

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.11 A - Licensed Operator Requalification Program and Licensed Operator Performance Requalification Examination Results (IP Section 03.03)

The licensee completed the annual requalification operating examinations and biennial written examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), "Requalification Requirements," of the NRC's "Operator's Licenses." The inspector performed an in-office review of the overall pass/fail results of the individual operating examinations, the crew simulator operating examinations, and the biennial written examinations in accordance with IP 71111.11, "Licensed Operator Requalification Program and Licensed Operator Performance." These results were compared to the thresholds established in Section 3.03, "Requalification Examination Results," of IP 71111.11.

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered on November 13, 2024.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

An inspection was performed to assess the effectiveness of the facility licensee in implementing requalification requirements identified in 10 CFR Part 55, Operators Licenses. Each of the following inspection activities was conducted in accordance with IP

===71111.11, Licensed Operator Requalification Program and Licensed Operator Performance.

(1) The licensee completed the annual requalification operating examinations and biennial written examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2),

"Requalification Requirements," of the NRC's "Operator's Licenses." The inspector performed an in-office review of the overall pass/fail results of the individual operating examinations, the crew simulator operating examinations, and the biennial written examinations in accordance with IP 71111.11, "Licensed Operator Requalification Program and Licensed Operator Performance." These results were compared to the thresholds established in Section 3.03, "Requalification Examination Results," of IP 71111.11.

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on October 5, 2023.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the following activities:
  • Unit 2, '2A' core spray system surveillance on October 1, 2024
  • Unit 1, reactor and plant startup activities on October 2, 2024
  • Unit 2, troubleshooting of 'B' 8th stage feedwater heater (FWH) on December 11, 2024 Licensed Operator Requalification Training/Examinations (IP Section 03.02)===
(1) The inspectors observed and evaluated an annual operating exam in the simulator on October 15, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Failure of the 2A residual heat removal service water (RHRSW) pump discharge check valve and its impacts on the 2C RHRSW pump, reviewed on December 19, 2024.
(2) Failure of unit 1 and unit 2 main turbine valve fast acting solenoids (FAS), reviewed on December 17, 2024.

Aging Management (IP Section 03.03) (1 Sample)

The inspectors evaluated the effectiveness of the aging management program for the following SSCs that did not meet their inspection or test acceptance criteria:

(1) Unit 1 drywell electrical penetrations 105C and 103A with unsatisfactory leakage test results during the refueling outage, reviewed on December 20, 2024.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Unit 2, elevated risk due to 2B residual heat removal system outage on October 22, 2024
(2) Unit 1, elevated risk due to 1A standby liquid control (SBLC) system outage on October 30, 2024
(3) Unit 1 and unit 2, elevated risk due to high voltage and low voltage switchyard maintenance, intake structure pump pit cleaning and inspection, and the 1C plant service water (PSW) pump out of service for planned maintenance on November 45, 2024
(4) Unit 2, risk mitigation measures associated with the return to service of the 'B' 8th stage feedwater heater during the week of December 9, 2024.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (2 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Condition Report (CR) 11116339, Unit 1 received alarm "602222 Pump B Seal Staging Flow High/Low," reviewed on October 8, 2024.
(2) CR 11136417, Leak from outlet clamp on 2C EDG lube oil filter, reviewed on December 18, 2024.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1)1P51C001A, 1A station service air compressor (SSAC) post maintenance functional test after repairs on October 7, 2024 (2)34SV-P41001-2, plant service water pump operability test after replacement of the 2A PSW pump, reviewed on October 21, 2024 (3)34SV-E51002-1, reactor core isolation cooling pump operability test following a turbine control system setpoint adjustment on October 29, 2024 (4)34SV-C41002-1, PMT after gearbox inspection and oil change of the 1A standby liquid control (SBLC) pump, on October 30, 2024

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.0102.04) (1 Sample)

(1) The inspectors evaluated the maintenance and testing of the alert and notification system during the week of December 2, 2024.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.0102.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Response Organization during the week of December 2, 2024.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.0102.03) (1 Sample)

(1) The inspectors evaluated submitted Emergency Action Level, Emergency Plan, and Emergency Plan Implementing Procedure changes during the week of December 2, 2024. This evaluation does not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program during the week of December 2, 2024.

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) Emergency preparedness (EP) drill with a loss of coolant accident, loss of offsite power, loss of containment that results in a radiological release, and fuel clad break(s) that resulted in a general emergency with protective action recommendations on November 12, 2024

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) Training drill involving emergency action level classifications after loss of reactor coolant system barrier due to emergency reactor pressure vessel depressurization on October 8,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

MS10: Cooling Water Support Systems (IP Section 02.09) (2 Samples)

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) July 1, 2023, through September 30, 2024.

EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)

(1) July 1, 2023, through September 30, 2024.

EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)

(1) July 1, 2023, through September 30, 2024.

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends associated with the scaffolding procedure implementation that might be indicative of a more significant safety issue. Specifically, the inspectors reviewed the following issues in the CAP:
  • CR 11070320, Scaffolding in the intake structure did not have a minimum distance of 2" from a RHRSW strainer isolation valve
  • CR 11108703, Scaffold ladder potentially unsafe
  • CR 11111441, Evaluate the need for scaffold on 164' TB in front of 1L48-C86
  • CR 11135732, Scaffold near unit 2 division 1 RHRSW strainer is within 2 inches
  • CR 11102407, NRC Resident Concern - scaffold pole left under the stairs to the SW diagonal 130'

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensees event reporting determinations to ensure it complied with reporting requirements.

(1) LER 05000321/2024004-00, "Manual Reactor Trip During Hurricane Helene Due to Degrading Condenser Vacuum," dated November 19, 2024. (ADAMS Accession No. ML24324A187) The inspectors determined that the cause of the condition described in the LER was not reasonably within the licensee's ability to foresee and correct, and therefore was not reasonably preventable. No performance deficiency or violation of NRC requirements was identified. This LER is closed.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===92702 - Follow-Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, and Orders The inspectors conducted a follow-up inspection of the licensee's corrective actions in response to Notice of Violations (NOVs) 05000321, 05000366/202409001 and -02, issued on August 27, 2024 (ADAMS Accession No. ML24214A328).

Follow-Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, and Orders===

(1) The inspectors evaluated corrective actions that were implemented by the licensee to determine whether they were adequate to address the identified deficiencies and to prevent recurrence. The inspection consisted of a review of the licensee's response to the NOVs, dated June 17, 2024 (ML24169A622), all relevant corrective action documents including an Organizational and Programmatic causal analysis evaluation, interviews with six members of the radiation protection (RP) organization regarding expectations for radiological survey performance and documentation, review of 15 surveys of five different plant areas to screen for anomalous results, evaluation of procedural guidance for performance of surveys and RP conduct of operations, and review of corrective action program administrative procedures. The inspectors concluded that the licensee's corrective actions were appropriate. Based on the results of this review, no additional NRC actions are necessary.

For administrative purposes. The original apparent violation (AV) and the circumstances surrounding it were previously described in detail in the NRCs letter to Southern Nuclear Company Hatch on May 15, 2024 (ML24080A415), and was assigned violation tracking number AV 05000321, 05000366/202409001 and -02.

This AV tracking number was re-designated as NOV 05000321, 05000366/202409001 and -02 in NRC inspection report dated August 27, 2024, when the NOV was issued. The NOVs 05000321, 05000366/202409001 and -02, are now closed.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 23, 2024, the inspectors presented the biennial licensed operator requalification program inspection results to Andrew Belcher and other members of the licensee staff.
  • On December 4, 2024, the inspectors presented the IP 92702 inspection results to Jason Butler and other members of the licensee staff.
  • On December 5, 2024, the inspectors presented the emergency preparedness program inspection results to Matthew Busch, Site Vice President and other members of the licensee staff.
  • On January 8, 2025, the inspectors presented the integrated inspection results to Matthew Busch, Site Vice President and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.11Q

Miscellaneous

H-LTC-SE-00306

Simulator Guide for Annual Exam Scenario

2.0

71111.11Q

Procedures

34GO-OPS-0011

Plant Startup

10/02/2024

71111.12

Corrective Action

Documents

CAR 666270

Equipment Reliability Checklist for 2E11F005A, Residual

Heat Removal Service Water Pump Discharge Check

Valve Failure.

06/04/2024

71111.12

Corrective Action

Documents

CAR 736511

Cognitive trend on shorted solenoid coils

11/01/2024

71111.12

Corrective Action

Documents

CAR 750723

Main Turbine Valve Fast Dump Failures

10/24/2024

71111.12

Corrective Action

Documents

CR 10774443

71111.12

Corrective Action

Documents

CRs: 11067437,

10619830,

11068256,

11050453,

11051050

71111.12

Corrective Action

Documents

Resulting from

Inspection

CR 11136854

71111.12

Drawings

H-21039

Hatch Unit 2 RHRSW System P&ID

71111.12

Engineering

Evaluations

TE 1164315

Create PMCR to increase turbine valve testing frequency

71111.12

Engineering

Evaluations

TEs: 1043501,

1164173, 1152995

Technical Evaluations - Maintenance Rule Evaluations

71111.12

Miscellaneous

Type B LLRT data sheets for electrical penetrations during

1R31

71111.12

Miscellaneous

A-47039

License Renewal Aging Management Review Summary

2.0

71111.12

Miscellaneous

E1108,

Suppression Pool

Cooling

E1104, RHRSW

Maintenance Rule SSC Function Consolidation and

Performance Criteria Selection Forms

11/12/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Vessel Injection

71111.12

Miscellaneous

S-75930

PSW Pump and RHRSW Pump Reverse Rotation

Assessment

1.0

71111.12

Procedures

2SV-TET-0011

Primary Containment Type B and Type C Leak Rate

Testing

30.3

71111.12

Procedures

NMP-ES-027

Maintenance Rule Program

11.1

71111.12

Procedures

NMP-GM-002-F02

Cause Determination Report Summary

11/14/2024

71111.12

Procedures

NMP-GM-002-F08

Organizational and Programmatic Checklist (OPC)

11/14/2024

71111.12

Procedures

NMP-GM-002-F22

Equipment Reliability Checklist

11/14/2024

71111.12

Work Orders

SNC1142889

Degraded insulation on SV #4 and CV #4

11/22/2024

71111.12

Work Orders

SNC2147041

Replace all FAS on U1 from Refurbished to new

11/13/2024

71111.12

Work Orders

SNC2147045

Remove/reinstall Turbine Building shield plugs

11/19/2024

71111.13

Procedures

NMP-GM-031

On-Line Configuration Risk Management Program

9.4

71111.13

Procedures

NMP-GM-031001

Online Maintenance Rule (a)(4) Risk Calculations

8.0

71111.13

Procedures

NMP-OS-010

Protected train/division and protected equipment program

71111.13

Procedures

NMP-OS-010002

Hatch Protected Equipment Logs

2.6

71111.15

Corrective Action

Documents

CR 10710692,

10798439,

11136417

71111.15

Corrective Action

Documents

CR 11116339,

10951460,

10961511,

11011345,

11061219

71111.15

Drawings

H16066

Reactor Recirculation System PI&D

04/05/2016

71111.15

Work Orders

SNC1747169,

2076887

71111.15

Work Orders

SNC919984

71111.24

Corrective Action

Documents

CR 11117400

1A SSAC output pressure low at 35 psig

10/09/2024

71111.24

Procedures

34SV-C41002-1

Standby Liquid Control Pump Operability Test

10/30/2024

71111.24

Procedures

34SV-P41001-2

Plant Service Water Pump Operability

10/20/2024

71111.24

Procedures

2SP-1028-24-RC-

Alternate RCIC Turbine Speed Control Test

1.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.24

Work Orders

SNC1964920,

SNC2082973, SNC

1579390

71114.04

Procedures

Standard Emergency Plan Annex for Hatch Nuclear Plant,

Units 1 and 2

Rev. 9

71114.06

Miscellaneous

Drill Scenario for Hatch EP Drill on November 12, 2024.

71114.06

Miscellaneous

Hatch 24EX03 EP Drill Final Report

71114.06

Miscellaneous

NMP-EP-142-F01

Emergency Notification Form

2.4

71114.06

Procedures

H-LTC-SE-00314

Turbine Bldg Fan Flow Low, Gen H2 TCV auto failure,

HPCI inadvertent, MSL Break manually isolate, RCIC fails,

Emergency Depress

2.0

71114.06

Procedures

NMP-EP-141002

Hatch Emergency Action level and Basis

5.0

71114.06

Procedures

NMP-EP-142

Emergency Notifications

9.0

71114.06

Procedures

NMP-EP-144

Protective Actions

11.0

71114.06

Procedures

NMP-EP-300

SNC Emergency Preparedness Conduct of Operations

31.0

71114.06

Procedures

NMP-EP-303

Drill and Exercise Standards

24.1

71151

Miscellaneous

Performance Indication Data Hatch Units 1 & 2 for period

10/1/20239/30/2024

71152S

Corrective Action

Documents

CR 11101696,

11108703,

11111441,

11135732

71152S

Corrective Action

Documents

Resulting from

Inspection

CR 11070320,

11102407,

11108054

71152S

Procedures

NMP-MA-010

Erecting, modifying, and disassembling scaffolding

4/17/2024

71152S

Procedures

NMP-MA-010-F03

Scaffolding Evaluation

1.1

71153

Miscellaneous

Unit 1 Control Log

09/27/2024

71153

Miscellaneous

Unit 2 Control Log

09/27/2024

71153

Miscellaneous

EN#57343

Reactor Plant Event Notification Worksheet

09/27/2024

71153

Miscellaneous

LER

05000321/2024004-

Manual Reactor Trip During Hurricane Helene Due to

Degrading Condenser Vacuum

11/19/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71153

Procedures

31GO-OPS-0100

Scram/Transient Analysis

11/05/2024

71153

Procedures

NMP-GM-020-F02

Event Personnel Statement

09/30/2024

71153

Procedures

NMP-GM-020-F03

Event Recovery Report

2/05/2024

2702

Corrective Action

Documents

CR 11018617

2702

Procedures

NMP-AD-051

Work Verification

Version 9.0

2702

Procedures

NMP-HP-008

Radiological Protection Conduct of Operations

Version 4.14

2702

Procedures

NMP-HP-008001

Radiation Protection Standards and Expectations

Version 8.0

2702

Procedures

NMP-HP-009

Radiological Protection Fundamentals

Version 2.0

2702

Procedures

NMP-HP-300

Radiation and Contamination Surveys

Version 6.1