June 18, 2019

SUBJECT:

HATCH UNITS 1, 2 - NRC TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000321/2019010 AND 05000366/2019010

Dear Mr. Vehec:

On May 16, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Hatch Units 1, 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

.

Sincerely,

/RA/

Scott M. Shaeffer, Chief Engineering Branch 2 Division of Reactor Safety

Docket Nos.: 05000321 and 05000366 License Nos.: DPR-57 and NPF-5

Enclosure:

Inspection Report 05000321/2019010 and 05000366/2019010

Inspection Report

Docket Number(s):

05000321 and 05000366

License Number(s):

DPR-57 and NPF-5

Report Number(s):

05000321/2019010 and 05000366/2019010

Enterprise Identifier:

I-2019-010-0037

Licensee:

Southern Nuclear Operating Company, Inc.

Facility:

Hatch, Units 1 and 2

Location:

Baxley, GA

Inspection Dates:

April 29, 2019 to May 17, 2019

Inspectors:

P. Braaten, Reactor Inspector

J. Dymek, Reactor Inspector

L. Jones, Senior Reactor Inspector

D. Strickland, Reactor Inspector

Approved By:

Scott M. Shaeffer, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Triennial Fire Protection inspection at Hatch Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. Findings and violations being considered in the NRCs assessment are summarized in the table below.

List of Findings and Violations

No findings were identified.

INSPECTION SCOPE

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.05T - Fire Protection B.5.b Inspection Activities (IP Section 02.03)

The inspectors evaluated the following B.5.b Mitigating Strategies:

Make-Up to the Spent Fuel Pool

Fire Protection Inspection Requirements (IP Section 02.02) (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas and/or fire zones, including analyzed electrical circuits:

(1) Fire Area 1412, DG 1A SWGR Room 1E [Elevation 130]
(2) Fire Area 0014K, Control Building, North and South Corridors [Elevation 130]
(3) Fire Area 1016, W 600V SWGR Room 1C [Elevation 130]
(4) Fire Area 24A, Unit 1 Cable Spreading Rm [Elevation 147]

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On May 16, 2019, the inspector presented the Triennial Fire Protection inspection results to Tom Vehec and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05T Calculations

557V.1B.6

E. I. Hatch Units 1 and 2, Control Building and Reactor

Building Peak Temperatures During Station Blackout

Rev. 0

BH2-M-0578

HNP-1,2 Control Building Heat-up due to Station Blackout

(SBO Temperature Profile)

Rev. 2

SENH-15-009

FA 0014 Compliance Assessment Scenario

03/12/2018

SENH-15-009

FA 1016 Compliance Assessment scenario

2/14/2018

SENH-15-009

FA 1412 Compliance Assessment Scenario

2/16/2018

Corrective Action

Documents

294125

Several Unit 2 Gaitronics Units Discovered not functional

During PA UPS FT

11/03/2016

10306120

Gaitronics System At The Intake Is Not Functioning

2/07/2016

10325083

Remote Shutdown Panel Light (Procedure Enhancement)

01/31/2017

10343412

Broken Phones in Case of Emergency

03/16/2017

10417185

Unsatisfactory Fire Radio Checks

10/08/2017

10439543

Ascom Phones Not Working Properly In Parts of Control

2/13/2017

10548102

2018 TFPI FASA Identified

10/23/2018

10575206

Fire Main Rupture

01/26/2019

10581729

Underground Fire Protection Piping System Leaks

2/12/2019

1060074

Fire Piping Break (Switchyard)

04/11/2019

10606354

Leaking Isolation Valve

04/30/2019

275606

Fire Protection Yard Piping Failure

2/29/2019

Corrective Action

Documents

Resulting from

Inspection

10597865

Lube Oil Storage Tank Room is flooded

04/03/2019

10606267

2019 NRC TPFI Inspection

04/30/2019

10606354

Leaking isolation valve

04/30/2019

10606415

Compensatory Fire watch personnel unaware of full duties

04/30/2019

10610851

TFPI NRC Inspection

05/15/2019

10610984

A potential NFPA 72E code compliance deviation has been

identified

05/15/2019

10611136

600VAC Power Cables Identified in Cable Spreading Room

05/16/2019

Drawings

A-43965, Sheet

24A

Edwin I Hatch Nuclear Plant-Unit 1 & 2 Pre-Fire Plan

General Area and Corridors Control Building Elevation 130-

Rev. 4

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

A-43965, Sheet

24B

Edwin I Hatch Nuclear Plant-Unit 1 & 2 Pre-Fire Plan

General Area and Corridors Control Building Elevation 130-

Rev. 9

A-43965, Sheet

28A

Edwin I Hatch Nuclear Plant-Unit 1 Pre-Fire Plan West 600V

Switchgear Room 1C Control Building Elevation 130-0

Rev. 5

A-43965, Sheet

28B

Edwin I Hatch Nuclear Plant-Unit 1 Pre-Fire Plan West 600V

Switchgear Room 1C Control Building Elevation 130-0

Rev. 8

A-43965, Sheet

44A

Edwin I Hatch Nuclear Plant-Unit 1 & 2 Pre-Fire Plan Cable

Spreading Room 1C Control Building Elevation 147-0

Rev. 4

A-43965, Sheet

44B

Edwin I Hatch Nuclear Plant-Unit 1 & 2 Pre-Fire Plan Cable

Spreading Room 1C Control Building Elevation 147-0

Rev. 6

A-43966, Sheet

17A

Edwin I Hatch Nuclear Plant-Unit 1 Pre-Fire Plan Diesel

Generator Building Switchgear Room 1E

Rev. 2

A-43966, Sheet

17B

Edwin I Hatch Nuclear Plant-Unit 1 Pre-Fire Plan Diesel

Generator Building Switchgear Room 1E

Rev. 3

B-13011, Sheet

Penetration List Under Control Room Panels

2/15/1972

B-19631, Sheet

296

Edwin I. Hatch Nuclear Plant-Unit No. 2 Penetration Seals

Type, Number and As-Built Location

Rev. 30

B-19631, Sheet

306

Edwin

I. Hatch Nuclear Plant-Unit No. 2, Penetration Seals

Type, Number and As-Built Location

Rev. 5

B-23276, Sheet

Edwin

I. Hatch Nuclear Plant-Unit No. 2, Penetration Seals

Type, Number and As-Built Location

Rev. 3

H-11033, Sheet 1

Edwin I. Hatch Nuclear Plant Unit No. 1 Fire Protection - P &

ID Pumphouse Layout

Rev. 53

H-11151

Edwin I. Hatch Nuclear Plant Unit No. 1 Piping-Fire

Protection Pump House Plan and Elevation

Rev. 13

H-11153

Edwin I. Hatch Nuclear Plant Unit No. 1 Piping-Fire

Protection Pump House Section and Details

Rev. 3

H-11816

Edwin

I. Hatch Nuclear Plant Unit No. 1-2, Fire Hazards

Analysis Control Building E. 147-0

Rev. 2

H-11884 Sheet 1

Edwin

I. Hatch Nuclear Plant Unit No. 1, Equipment Layout

Drawings Fire Detection/Fire Suppression Multiplex System

1Z43 Control Building Elevation 147-0

Rev. 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

H-12631

Edwin I. Hatch Nuclear Plant Unit No. 1 Architectural Control

Building-Detailed Floor Plan at El. 147-0

Rev. 11

H-13350

Edwin I. Hatch Nuclear Plant Unit No. 1 Master Single Line

Diagram

Rev. 29.0

H-13395

Edwin I. Hatch Nuclear Plant Unit No. 1 Elementary Diagram

Diesel Generator !A Heating and Ventilation

Rev. 20

H-14836

Edwin I. Hatch Plant Unit No. 1 Conduit and Grounding

Penetrations Under Control Room Panels Plan-El - 164-0

H-14837, Sheet 1

Edwin I. Hatch Plant Unit No. 1 Conduit and Grounding

Spreading Room Exposed Conduit Plan - El. 147-0

H-16329

Edwin I. Hatch Nuclear Plant Unit No. 1 R.H.R System P&ID

SHT. 1

Rev. 71.0

H-16334

Edwin I. Hatch Nuclear Plant No. 1 RCIC System P& ID

Sheet No. 1

Rev. 44.0

H-16335

Edwin I. Hatch Nuclear Plant Unit No. 1 RCIC System P&ID

Sheet No. 2

Rev. 29

H-17163

Edwin I. Hatch Nuclear Plant Unit No. 1 High Pressure

Coolant System E41 Elementary Diagram Sheet 7

Rev. 26.0

H-17164

Edwin I. Hatch Nuclear Plant Unit No. 1 High Pressure

Coolant Injection SYS. E41 Elementary Diagram Sheet 8 of

Rev. 33.0

H-17774

Edwin I. Hatch Nuclear Plant Unit No. 1 Residual Heat

Removal System E11 Elementary Diagram Sheet 15 of 25

Rev. 25.0

H-19614

Edwin I. Hatch Nuclear Plant Unit No. 1 Remote Shutdown

System (C82) Sheet 7 of 9

Rev. 17.0

H-23350

Edwin I. Hatch Nuclear Plant Unit No. 2 Master Single Line

Diagram

Rev. 15.0

H-40178

Edwin I. Hatch Nuclear Plant Unit No. 1 Appendix "R"

Raceways Cont. BLDG. EL. 130' - 0" TA-TE & T10-T13

Rev. 15.0

H-40433

Edwin I. Hatch Nuclear Plant Unit No. 1 Fire Protection

Piping Cable Spreading Room Sprinkler System, Unit 1 East

Rev. 1

H-40434

Edwin I. Hatch Nuclear Plant Unit No. 1 Fire Protection

Piping Cable Spreading Room Sprinkler System, Unit 1 East

H-41497

Edwin I. Hatch Nuclear Plant Unit No. 1 Reactor BLDG. EL.

Rev. 2.0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

130' - 0" Northeast Emergency Lighting

H-42102

Edwin I. Hatch Nuclear Plant Unit No. 2 Fire Protection

Protectowire-Plan Control Building El. 130-0 Columns 1-10

to T-14 / TA to TF

06/29/1989

H-42103

Edwin I. Hatch Nuclear Plant Unit No. 2 Fire Protection

Protectowire-Plan Control Building El. 130-0 Columns 1-10

to T-14 / TA to TF

06/29/1989

PSI Drawing

3074 Sheet 1

Access Door Location 4 Fire Barrier Elevation 130-0

Control Building 1 Hour Fire Rated Promat Assembly

07/14/1998

S-11185

Fire Pump Engine Driven 550 Gallon Fuel Tank Outline

06/23/1969

S-13699

1000 Gallon Fuel Oil Day Tank

06/01/1971

S-51118

Fire Protection System Mechanical Outline 20 Zone 9090

Detection

08/15/1985

S-54873B Sheet

& 2

Promatec Technologies Inc. Unit 2 Control Building Corridor

Elevation 130-0 Control Building 1-hour Fire Rated Promat

Assembly

2/15/1998

Engineering

Changes

CCP SNC933694

Install 120v Power Receptacle

Rev. 2

DCP SNC937823

NFPA 805 Project Fusible Links

Rev. 1

Engineering

Evaluations

Risk Based Analysis, Unit No. 2 CSR Thermoset Cable

Percentage Analysis

04/22/2016

S-52429

BISCO Fire Rated Penetration Seal Details and Cross

Reference Matrix for Edwin I. Hatch Nuclear Plant

04/1990

S-52439

Fire Rated Penetration Seal Qualification Data SWRI Project

No. 01-8821-028B

08/16/1990

S-52483

Hatch Unit 1, 2 Fire Rated Penetration Seal Qualification

Data-Various Sealing Products and Configurations

04/17/1991

SMNH-16-026

NFPA 13 Code Compliance Review (Sprinkler Systems)

03/20/2018

Miscellaneous

NANTel Generic Plant Access Training

2/2018

Technical Evaluation of Promatec Technologies,1 & 3 Hour

Fire Barriers Installed at Plant Hatch, Baxley GA

09/16/1998

ENG-0246

Fire Fighting Equipment Inspection Inventory

Rev. 24.3

Mann Wireless,

LTD.

Edwin I. Hatch Nuclear Plant In-Building Enhancement

Project Baxley, Georgia

06/26/2006

NL-15-2023

Edwin

I. Hatch Nuclear Plant - Units 1 and 2, Commitment to

2/23/2015

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Maintain Severe Accident Management Guidelines

Procedures

20AC-IRS-001-0

Control of Portable RF Transmitting Devices

Rev. 3.0

34-AB-X43-001-1

Fire Procedure

Rev. 16.0

34-GO-OPS-

031.1

ISI Pump and Valve Operability Test

Rev. 21.30

34IT-EOP-001-0

EOP Equipment Checks

07/15/2018

34IT-R25-001-0

Control Room Emergency Lighting Supply Weekly Test

Rev. 1.10

34SO-X43-001-1

Fire Pumps Operating Procedure

Rev. 6.5

34SV-E51-005-2

RCIC OPS From RSDP

03/06/2018

2SV-FPX-003-0

Emergency Lighting Surveillance

Rev. 16.6

2SV-FPX-008-0

Fire Protection Water Suppression System Flow Test

Rev. 4.2

2SV-FPX-013-0

Rolling Fire Door Surveillance

Rev. 4.1

51GMM-FPX-

004-0

Installation and Repair of Rolling Fire Doors

Rev. 1.4

NMP-ES-035-007

Fleet Fire Watch Instruction

Rev. 5

NMP-ES-035-

007-F01

Hourly Fire Watch

Rev. 4

NMP-ES-035-

007-F02

Continuous Fire Watch

Rev. 2.1

NMP-OS-007-007 Rounds

Rev. 4

NMP-OS-019-010 Emergency Management Guideline (EMG)

Rev. 1.1

NMP-OS-019-268 Hatch Unit 1 SIG-8, Spent Fuel Pool Makeup

Rev. 3.2

NMP-OS-019-288 Hatch Unit 2 SIG-8, Spent Fuel Pool Makeup

Rev. 2.2

Work Orders

SNC218170

DG Low Pressure CO2 System Surveillance

SNC602101

Investigate / Repair Valve that is Hard to Operate

SNC852429

Valve Leaking from Packing

SNC884460

Emergency Lighting Surveillance Group 2

2/05/2018

SNC904439

Packing Leak