IR 05000317/2019011

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000317/2019011 and 05000318/2019011
ML19284A518
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 10/10/2019
From: Glenn Dentel
Engineering Region 1 Branch 2
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Dentel G
References
IR 2019011
Download: ML19284A518 (13)


Text

October 10, 2019

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT, UNITS 1 AND 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000317/2019011 AND 05000318/2019011

Dear Mr. Hanson:

On September 26, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Calvert Cliffs Nuclear Power Plant, Units 1 and 2 and discussed the results of this inspection with Mr. Mark Flaherty and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety

Docket Nos. 05000317 and 05000318 License Nos. DPR-53 and DPR-69

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000317 and 05000318

License Numbers:

DPR-53 and DPR-69

Report Numbers:

05000317/2019011 and 05000318/2019011

Enterprise Identifier: I-2019-011-0015

Licensee:

Exelon Generation Company, LLC

Facility:

Calvert Cliffs Nuclear Power Plant, Units 1 and 2

Location:

Lusby, MD

Inspection Dates:

September 9, 2019 to September 26, 2019

Inspectors:

E. DiPaolo, Senior Reactor Inspector (Team Lead)

C. Bickett, Senior Reactor Inspector

P. Finney, Senior Project Engineer

S. Graves, Senior Reactor Inspector

Approved By:

Glenn T. Dentel, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Calvert Cliffs Nuclear Power Plant, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.05XT - Fire Protection - NFPA 805 Fire Protection Inspection Requirements (IP Section 02.01a)

The inspectors evaluated fire protection program implementation in the following selected areas and/or fire zones, including analyzed electrical circuits:

(1) Fire Area 16 - Unit 1 Cable Spreading Room and 1C Cable Chase
(2) Fire Area 18 - Unit 2 27' Switchgear Room
(3) Fire Area 25 - Unit 2 45' Switchgear Room
(4) Fire Area 32 - Unit 1 45' West Electrical Penetration Room

Analyzed Circuits:

1-CV-4030OP, Main Steam Isolation Valve Circuit

1-ERV-402, Power Operated Relief Valve

1-HC-3987B, 11 Auxiliary Feedwater Pump Controller

2-CV-4070, AFW Pump Steam Admission Valve

2-HC-4056A, 21 Atmospheric Dump Valve Controller

B.5.b Inspection Activities (IP Section 02.03) (2 Samples)

The inspectors evaluated the following B.5.b Mitigating Strategies:

(1) Makeup to Condensate Storage Tank using the B.5.b Pump
(2) Manually Depressurize Steam Generator and Use Portable Pump

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On September 26, 2019, the inspectors presented the triennial fire protection inspection results to Mr. Mark Flaherty and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05XT Corrective Action

Documents

20773

21559

2742586

4046035

4067297

248214

248382

256424

257102

267663

268815

275593

Corrective Action

Documents

Resulting from

Inspection

267663-05, -06,

-07

274804

276645

277875

278033

278046

278073

278075

278079

278324

278327

278683

278741

278790

278853

279004

280273

280796

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

281526

281807

281862

281997

282024

282071

282114

282386

Drawings

263-0003

Halon 1301 Fire Suppression System

2E-198, Sheet

28

Connection Diagram Junction Box 2J571

60616B, Sheet 57 Logic Diagram Pressurizer Solenoid Operated Relief

Valves-1ERV402 & 404

60714, Sheet 3

Plant Fire Protection System Turbine, Service Bldgs. &

Intake Structure

60722, Sheet 3

Auxiliary Building Ventilation System

60723, Sheet 4

Ventilation Systems Control Room and Cable Spreading

Room HVAC

60729, Sheet 1

Reactor Coolant System

60929, Sheet 1

Loop Diagram 11 AFW Pump Turbine Speed Control

1HC3987A & B

61-199-B, Sheet

9A

Electrical Penetration Assembly Termination 1ZEC1

61001, Sheet 1

Electrical Main Single Line Diagram Final Safety Analysis

Report (FSAR) Fig. No. 8-1

61005

Meter and Relay Diagram 4KV System Unit Buses 11 and

FSAR Fig. No. 8-4

61017

Single Line Diagram Reactor 480V MCC 114R

and 43

61035

Equipment Layout Cable Spreading Room Aux. Bldg. Area

EL.27'-0

61075, Sheet 53

Reactor Auxiliaries Pressurizer Relief 1ERV402

61076, Sheet

2H

Schematic Diagram Reactor Safeguards S.G. 11 Main

Steam Isolation 1CV4043

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

61086, Sheet 1

Schematic Diagram 4KV Bus 11 & 17 Tie Breaker 152-

1103

61086, Sheet 3

Schematic Diagram 4KV Bus 14 Diesel Generator 1B

Feeder Breaker 152-1403

61101, Sheet 43A Connection Panel Isolation Panel 1C43A

61101, Sheet

43D

Wiring and Connection Diagram Aux Feed Water Control

Panel 1C43

2-632-C, Sheet

Loop Diagram Alternate Shut-Down Related Circuits Unit

No. 2 AFW System Throttle, and Miscellaneous Control

Valves

2153, Sheet 33

Barrier Segment Drawing for Plant Elevation 69

2583, Sheet 1

AFW System (Steam)

and 63

2633, Sheet 1

Loop Diagram 21 & 22 Main Steam Line Atmos Dump and

Turbine Bypass 2PT4056 & 2 HIC4056

2730, Sheet 1

Chemical and Volume Control System

63069

Schematic Diagram Turbine Steam Dump and Bypass

Controls

63079, Sheet 55A Schematic Diagram AFW Pumps 21 & 22 Isolation Valves

2CV4070 & 2CV4070A

and 3

63196, Sheet 120

Connection Diagram for 2I/P3938 and 2I/P3939

63196, Sheet 7W

Connection Diagram Solenoid Valves 2SV4070,

2SV4070A, 2SV4071 & 2SV4071A

66065, Sheet 1

Instrument Installation Detail for 2CV3938 & 2CV3939

203, Sheet 4

Electrical Wiring Diagram Panel 1C03 Condensate &

Feedwater Control Board

87303, Sheet 9

Electrical Wiring Diagram Panel 2C03 Condensate &

Feedwater Control Board

M-162

Heating & Ventilation System Auxiliary Building Unit 1 Plan

at Elevation 45'

Engineering

Changes

ECP 14-000070

Protection of Secondary Side Transformers with Excessive

Thermal Overload or Short Circuit Design Issues (NFPA

805 Compliance LAR #15)

ECP-16-000335

Replace Fire Protection Valves

04/26/2016

ECP-17-000653

NSB Modular Building Installation

11/17/2017

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Engineering

Evaluations

1-ERV402 Cable Selection Worksheets

03/31/2011

1-HC-3987B 11 AFW Pump Controller Cable Selection

Worksheets

06/29/2011

2-CV-4070

AFW Pump Steam Admission Valve Cable Selection

Worksheets

2/22/2011

C0-FRE-F001

Fire Risk Evaluation Report

CA04007

Appendix R Analysis of Inadvertent Lifting of Both

Pressurizer PORVs

CA05974

CFR 50 Appendix R Fire Protection Abnormal Operating

Procedure 9 Simulations

CA07803

Minimum Allowable Reactor Coolant System Temperature

to Support NFPA 805 Transition

ECP-13-000303-

015-6-01

Equivalent Change Technical Evaluation for Acceptability of

The Following 1.5-Hour Fire Doors Installed In 3-Hour Fire

Barriers

ECP-13-000325-

015-6-01

Equivalent Change Technical Evaluation for Acceptability of

Issues Related to Fire Dampers Installed in Fire Barriers

ES199901141

Engineering Evaluation to Summarize Appendix R

Communications Issue

10/14/1999

FP00002

Fire Hazards Analysis Summary Report

NFPA 805-00006

Nuclear Safety Capability Assessment Report (NSCA)

NFPA 805-

00006A

NSCA Analysis Result

and 1

NFPA-805-

00006A

NFPA 805 Transition Project Attachments

and 1

NFPA-805-00008

Non-Power Operation Modes Transition Review

R2215-003-001

NFPA 805 Radioactive Release Review

R2215-021-001

NFPA 805 Chapter 3 Fundamental Fire Protection Program

and Design Elements Review

R2215-022-001

NFPA Code Conformance Review

R2215-043-001

NFPA 805 Effects of Fire Suppression Activities Review

Report

R2215-048-001

Fire Area Review Report (Table B-3 Report)

and 1

R2215-049-001

Recovery Action Feasibility Assessment

and 2

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Fire Plans

Fire Fighting

Strategy

Unit 1 Cable Spreading Room 306

00300

Fire Fighting

Strategy

Unit 1 West Electrical Penetration Room 423

00400

Fire Fighting

Strategy

Unit 2 Switchgear Room 311

00300

Fire Fighting

Strategy

Unit 2 Switchgear Room 430

00600

Miscellaneous

2019 Annual Fire Fighting Training

Calvert Cliffs Fire Protection Program Health Report

1P2019

Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 And 2 -

Issuance of Amendments Regarding Transition to A Risk

Informed, Performance-Based Fire Protection Program in

Accordance With 10 CFR 50.48(c) (CAC NOS. MF2993

AND MF2994)

08/30/2016

Fire Brigade Drill records from 4th quarter 2016 through

2nd quarter 2019

Plant Barrier Impairment Log as of Plant Barrier Impairment

  1. 19-8-3

Updated Final Safety Analysis Report, Chapter 9.9, Fire

Protection Program Report

U.S. NRC License Amendment and Safety Evaluation

Report

8/30/2016

19-04-006, 19-08-

005, and 19-05-

2

Hot Work Permits

2686762-04

NRC Information Notice 2016-08: Inadequate Work

Practices Resulting in Faulted Circuit Breaker Connections

AOP-9X-2

Safe Shutdown due to a Severe Fire

ES-056

Fire Protection Codes and Standards

NFPA-20

Standard for the Installation of Centrifugal Fire Pumps

1969

NFPA-600

Standard on Industrial Fire Brigades

2000

NRC Generic Letter 81-12

Fire Protection Rule (45 FR 76602, November 19, 1980)

2/20/1981

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NRC Generic Letter 81-12

Clarification Letter, Fire Protection Rule - Appendix R

03/22/1982

OE-2009-003518

Response to NRC Information Notice 2009-29, Potential

Failure of Fire Water Supply Pumps to Automatically Start

Due To A Fire

2/17/2009

OPEX 4163523

NRC Information Notice 2018-009, Electrical Arc Flash

Caused by Foreign Material Damages Fire Door

11/13/2018

PCR-13-02102

PCR-13-02104

PCR-13-02122

PCR-13-02123

PCR-13-02124

Project No.03-

5980-003

Fire Stop Penetration Tests on Fire Protection System, Slab

No.2

08/15/1980

SA-1-105

Fire Brigade Training,

01100

VTD-D243-1014

Instructions for Installation and Maintenance Consoli

Electromatic Relief Valve Type 31533VX-30 with Bellows,

09/04/1990

Procedures

1C24B-ALM

Calvert Cliffs Nuclear Power Plant Fire Systems Alarm

Manual, Unit One and Two

AOP-9A-1

Control Room Evacuation and Safe Shutdown due to a

Severe Control Room Fire

AOP-9B-1

Safe Shutdown due to a Severe Cable Spreading Room

Fire

CC-AA-103

Configuration Change Control for Permanent Physical Plant

Changes

CC-AA-209

Fire Protection Program Configuration Change Review

CC-AA-211

Fire Protection Program

EDMG-1

Large Area Loss

ER-AA-610-1003

NFPA 805 Monitoring Program

FM-FP-W-1

Transient Combustible Walkdown/Weekly Fire Marshall

Tour/Weekly B.5.b Checks

LS-AA-128-101

Regulatory Review of Proposed Changes to the Approved

NFPA 805 Fire Protection Program

NO-AA-10

Quality Assurance Topical Report (QATR)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OI-22H

Control Room and Cable Spreading Rooms Ventilation

03000

OI-22H

Switchgear Ventilation and Air Conditioning

2500

OI-27D-2

Station Power 480V System Breaker Lineup

200

OP-AA-108-103

Locked Equipment Program

OP-AA-108-105-

1001

MCR and RWCR Equipment Deficiency Management and

Performance Indicator Screening

OP-AA-201-003

Fire Drill Performance

OP-AA-201-010-

1001

B.5.b Mitigating Strategies Equipment Expectations

OP-CA-102-106

Operator Response Time Program at Calvert Cliffs

OP-CA-108-3.0

Immediate Actions

00400

OP-CA-201-012-

1001

On-Line Fire Risk Management

201

OP-CA-TRM-100

CCNPP Technical Requirements Manual

PE 1-102-10-O-R

Remote Shutdown Panel Operation Verification

00503

Preventive

Maintenance

Task 01022041

Inspect, Inventory, and Test Run Portable B.5.b Diesel

Pump

08/19/2008

SAG-3

Technical Support Center Severe Accident Guideline:

Inject into Steam Generators

STP O-63-1

Remote Shutdown and Post Accident Monitoring Instrument

Channel Check

STP-F-592-2

Penetration Fire Barrier Inspection

01400

STP-M-499-2

and 45 Switchgear Rooms Halon System Fire

Detection Instruments Functional Test

00301

STP-M-699-2

Functional Test of Halon System for Switchgear Rooms

00800

TQ-AA-173

Emergency Services Training Programs

TSG-3

Technical Support Guideline: Site Capabilities

Self-Assessments

Functional Area Self-Assessment of Fire Protection

Program

08/06/2019

NOSA-CAL-18-

Fire Protection Audit Report

09/14/2018

Work Orders

C93231444

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

C93374514

C93374514

C93589599

C93589599

C93645538

C93645538

C93661670

C93661670

C93677938

C93683576

C93683576

M-80-9333