Ack Receipt of 970818,0915 & 29 Ltrs Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-295/97-12 50-295/97-13,50-304/97-13,50-295/97-16 & 50-304/97-16 Issued on 970717,0815 & 28.No Further Questions
ML20199K148
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 11/26/1997
From: Anton Vegel
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Brons J
COMMONWEALTH EDISON CO.
References
50-295-97-12, 50-295-97-13, 50-295-97-16, 50-304-97-13, 50-304-97-16, NUDOCS 9712010028
Download: ML20199K148 (2)


Text

. - - . . _ . - - . -

R / ilk November 26, 1997 i

. s

.

Mr. E

'

Site Vice President Zion Station Commonwealth Edison Company  ;

101 Shiloh Boulevard ,

Zion. IL 60099 SUBJECT: NOTICE OF VIOLATION (NRC INSPECTION REPORTS NO. 50 295/97012(DRP) 50 295/97013(DRP),50 304/97013(DRP); and 50 295/97016(DRP); 50 304/97016(DRP))

Dear Mr. Brons:

This will acknowledge receipt of your letters dated August 18, September 15, and September 29,1997, in response to our letters dated July 17. August 15, and August 28,1997, transmitting Notices of Violation associated with Inspection Reports No. 50 295/97012(DRP);

50-295/97013(DRP),50-304/97013(DRP); and 50-295/97016(DRP),50-304/97016(DRP) We have reviewed your corrective actions and have no further questions at this time. These corrective actions will be examined during future inspections.

Sincerely,

/s/ Anton Vegel Anton Vogel, Acting Chief Reactor Projects Branch 2 Docket No. 50 295 Docket No. 50 304 Gee Attached Distribution DOCUMENT NAME: G: ZION \ZIO97012.TKU To receive a copy of this document, indicate in the box "C" = Copy without attach /enci "E" = Copy with attach /enci "N" = No copy OFFICE Rlli ,

G NAME Vogellet h -

DATE 11/$ f /97 OFFICIAL RECORD COPY l

fod"188EIEsdaes l G PDR ,. ,

kh (__m - _ . . , . , . , . . . _ -_ ,, ,_

_ _ . _ _ _ _ _ _ . _

.. cc: O. Kingsley, Nuclear Generation Group President and Chief Nuclear Officer M. Wallace, Senior Vice President, Corporate Services H. G. Stanley,' %6 President PWR Operati. t Usison Officer, i:00 800 D. A. Sager, Vice President, Generat6on Support D. Ferrar, Nuclear Regulatory Services Manager 1. Johnson, Uconsing Operations Manager Document Control Desk Ucensing R. Starkey, Plant General Manager R. Godley, Regulatory Assurance Supervisor Richard Hubbard Nathan Schloss, Economist Office of the Attomey General Mayor, City of Zion State Walson Officer State Liaison Officer, Wisconsin Chairman, Illinois Commerce Commission

'

Distribution: '

Docket File DRP OC/LFDCB TSS PUBUC IE-01 DRS (2)

A. Beach RlllPRR Deputy RA RACi (E-Mail)

Rlli Enf. Coord. CAA1 (E Mail)

SRI Zion DOCDESK (E Mail)

Project Mgr., NRR