MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000293/20240022024-08-21021 August 2024 NRC Inspection Report No. 05000293/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24129A1042024-05-26026 May 2024 Preapplication Readiness Assessment Plan for the Holtec Decommissioning International License Termination Plan ML24136A2382024-05-14014 May 2024 Annual Radiological Environmental Operating Report for 2023 ML24135A3212024-05-14014 May 2024 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2023 IR 05000293/20240012024-05-0707 May 2024 NRC Inspection Report No. 05000293/2024001 L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 L-24-010, Request for Preapplication Readiness Assessment of the Draft License Termination Plan2024-04-22022 April 2024 Request for Preapplication Readiness Assessment of the Draft License Termination Plan L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000293/20230032024-02-29029 February 2024 NRC Inspection Report Nos. 05000293/2023003 and 05000293/2023004 L-24-002, Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G2024-02-0202 February 2024 Late LLRW Shipment Investigation Report Pursuant to 10 CFR 20, Appendix G ML23342A1182024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23334A1822023-11-30030 November 2023 Biennial Report for the Defueled Safety Analysis Report Update, Technical Specification Bases Changes, 10 CFR 50.59 Evaluation Summary, and Regulatory Commitment Change Summary – November 2021 Through October 2023 L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23306A0992023-11-0202 November 2023 and Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) IR 05000293/20234012023-08-31031 August 2023 NRC Inspection Report No. 05000293/2023401 & 2023001 (Cover Letter Only) IR 05000293/20230022023-08-0404 August 2023 NRC Inspection Report No. 05000293/2023002 L-23-008, Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI)2023-05-23023 May 2023 Correction to Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations Holtec Decommissioning International, LLC (HDI) ML23135A2152023-05-15015 May 2023 Annual Radioactive Effluent Release Report, January 1 Through December 31, 2022 ML23136A7792023-05-15015 May 2023 Annual Radiological Environmental Operating Report, January 1 Through December 31, 2022 L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance ML23069A2782023-03-13013 March 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1 Subsequent License Renewal Application ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000293/20220042023-02-15015 February 2023 NRC Inspection Report No. 05000293/2022004 ML22356A0712023-01-31031 January 2023 Issuance of Exemption for Pilgrim Nuclear Power Station ISFSI Regarding Annual Radioactive Effluent Release Report - Cover Letter ML22347A2782022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 L-22-041, Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension2022-12-0909 December 2022 Supplemental Information to Enhance Exemption Request Detail for Pilgrim ISFSI Annual Radioactive Effluent Release Report Due Date Extension IR 05000293/20220032022-11-18018 November 2022 NRC Inspection Report No. 05000293/2022003 L-22-036, Decommissioning Trust Fund Agreement2022-11-0808 November 2022 Decommissioning Trust Fund Agreement ML22276A1762022-10-24024 October 2022 Decommissioning International Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22266A1922022-09-23023 September 2022 and Pilgrim Nuclear Power Station - Request to Withdraw Prior Submissions from NRC Consideration ML22272A0352022-09-22022 September 2022 S. Lynch-Benttinen Letter Regarding U.S. Citizen Intent to Sue U.S. Fish and Wildlife and NOAA Fisheries Representing the Endangered Species (Na Right Whale) Which Will Be Adversely Affected by Holtec International Potential Actions ML22269A4202022-09-22022 September 2022 Citizen Lawsuit ML22241A1122022-08-29029 August 2022 Request for Exemption from 10 CFR 72.212(a)(2), (b)(2), (b)(3), (b)(4), (B)(5)(i), (b)(11), and 72.214 for Pilgrim ISFSI Annual Radioactive Effluent Release Report IR 05000293/20220022022-08-12012 August 2022 NRC Inspection Report No. 05000293/2022002 ML22215A1772022-08-0303 August 2022 Decommissioning International (HDI) Proposed Revisions to the Quality Assurance Program Approval Forms for Radioactive Material Packages ML22221A2592022-08-0101 August 2022 LTR-22-0217-1-NMSS - Town of Duxbury Letter Opposing the Irradiated Water Release from Pilgrim (Docket No. 05000293) ML22206A1512022-08-0101 August 2022 NRC Office of Investigations Case Nos. 1-2022-002 & 1-2022-006 ML22175A1732022-07-28028 July 2022 LTR-22-0153-1 - Response Letter to D. Turco, Cape Downwinders, from A. Roberts, NRC, Regarding Holtec-Pilgrim Plans to Dump One Million Gallons of Radioactive Waste Into Cape Cod Bay ML22193A1662022-07-28028 July 2022 LTR-22-0154-1 - Heather Govern, VP, Clean Air and Water Program, Et Al., Letter Regarding Radioactive Wastewater Disposal from the Pilgrim Nuclear Power Station (Docket No. 05000293) ML22154A4882022-06-0101 June 2022 Letter from Conservation Law Foundation Regarding Irradiated Water Release from Pilgrim ML22154A1622022-05-26026 May 2022 Letter and Email from Save Our Bay/Diane Turco Regarding Irradiated Water Release from Pilgrim ML22136A2602022-05-16016 May 2022 Submittal of Annual Radiological Environmental Operating Report for January 1 Through December 31, 2021 ML22136A2572022-05-16016 May 2022 Submittal of Annual Radioactive Effluent Release Report for January 1 Through December 31, 2021 2024-09-18
[Table view] Category:License-Operator Examination Report
MONTHYEARIR 05000293/20173012017-05-15015 May 2017 Initial Operator Licensing Examination Report 05000293/2017301 IR 05000293/20143012014-04-16016 April 2014 Er 05000293/14-301; February 24 - March 31, 2014; Pilgrim Nuclear Power Station, Initial Operator Licensing Examination Report IR 05000293/20113022012-01-24024 January 2012 Er 05000293-11-302, on December 21, 2011, Pilgrim Nuclear Power Station, Initial Operator Licensing Retake Examination Report IR 05000293/20113012011-04-19019 April 2011 Er 05000293/2011301; February 21 - March 4, 2011; Pilgrim Nuclear Power Station; Initial Operator Licensing Examination Report IR 05000293/20093012009-05-12012 May 2009 Er 05000293/2009301; March 20 - April 14, 2009; Pilgrim Nuclear Power Station; Initial Operator Licensing Examination Report IR 05000293/20073012007-04-17017 April 2007 IR 05000293-07-301; February 23, 2007 - March 1, 2007; Pilgrim Nuclear Power Station; Initial Operator Licensing Examination IR 05000293/20023012002-09-10010 September 2002 IR Exam Report 50-293/02-301; July 26 - August 2, 2002; Pilgrim Nuclear Power Station; Initial Operator Licensing Examination Report. Seven of Seven Applicants (3 ROs and 4 SRO Instants) Passed the Examination 2017-05-15
[Table view] |
Text
ril 17, 2007
SUBJECT:
PILGRIM NUCLEAR POWER STATION OPERATOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATION REPORT NO. 05000293/07-301
Dear Mr. Bronson:
This report transmits the results of the Reactor Operator (RO) and Senior Reactor Operator (SRO) licensing examination conducted by the NRC during the period of February 23 -
March 1, 2007. This examination addressed areas important to public health and safety and was developed and administered using the guidelines of the Examination Standards for Power Reactors (NUREG-1021, Revision 9).
Based on the results of the examination, all applicants passed all portions of the examination.
The five applicants included two ROs and three instant SROs. Examination results indicated that the applicants were well prepared for the examination. Mr. Johnson discussed performance insights observed during the examination with Mr. Mark Santiago on March 1, 2007. On March 8, 2007, final examination results, including individual license numbers, were given during a telephone call between Mr. Johnson and Mr. Santiago.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). These records include the final examination and are available in ADAMS (Master File - Accession Number ML060800104; RO and SRO Written - Accession Number ML070820363; RO and SRO Operating Section A - Accession Number ML070820392; RO and SRO Operating Section B - Accession Number ML070820405; and RO and SRO Operating Section C - Accession Number ML070820446), and ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Mr. Kevin Bronson 2 Should you have any questions regarding this examination, please contact me at (610) 337-5046, or by E-mail at MDS1@NRC.GOV.
Sincerely,
/RA/
Marvin D. Sykes, Chief Operations Branch Division of Reactor Safety Docket No. 50-293 License No. DPR-35
Enclosure:
Initial Examination Report No. 05000293/07-301
REGION I==
Docket No: 50-293 License No: DPR-35 Report No: 05000293/07-301 Licensee: Entergy Nuclear Operations, Inc.
Facility: Pilgrim Nuclear Power Station Dates: February 23, 2007 (Written Examination Administration)
February 26-March 1, 2007 (Operating Test Administration)
March 1-March 6, 2007 (Examination Grading)
March 1, 2007 (Final facility post exam comments on JPMs, end of examination period)
March 8, 2007 (Licenses issued to five applicants)
Examiners: Gilbert A. Johnson, Operations Engineer (Chief Examiner)
Joseph M. DAntonio, Senior Operations Engineer Peter A. Presby, Operations Engineer Approved by: Marvin D. Sykes, Chief Operations Branch Division of Reactor Safety i Enclosure
SUMMARY OF FINDINGS
IR 05000293/2007-301; February 23, 2007 - March 1, 2007; Pilgrim Nuclear Power Station;
Initial Operator Licensing Examination. Five of five applicants passed the examination (two reactor operators, and three SRO instants).
The written examinations were administered by the facility and the operating tests were administered by three NRC region-based examiners. The examiners observed Simulator Fidelity during the administration of the Operating test. There were no inspection findings of significance associated with the examinations.
ii
REPORT DETAILS
REACTOR SAFETY
Mitigating Systems - Reactor Operator (RO) and Senior Reactor Operator (SRO) Initial
a. Scope
of Review The facility examination team developed the written and operating initial examination.
NRC examiners, together with facility training and operations personnel verified or ensured, as applicable, the following:
- The examination was prepared and developed in accordance with the guidelines of Revision 9 of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors. A review was conducted both in the Region I office and at the Peach Bottom plant and training facility. Final resolution of comments and incorporation of test revisions were conducted during and following the onsite preparation week.
- Simulation facility operation was proper.
- A test item analysis was completed on the written examination for feedback into the systems approach to training program.
- Examination security requirements were met.
The NRC examiners administered the operating portion of the examination to all applicants from February 26, 2007 to March 1, 2007. The written examination was previously administered by the PNPS training staff on February 23, 2007.
b. Findings
Grading and Results All five applicants (three SROs and two ROs) passed all portions of the initial licensing examination.
The facility had no post examination comments.
Examination Administration and Performance No findings of significance were identified. One JPM was found to be defective after administration and was replaced. This was documented by the licensee in CR-PNP-2007-00762. The replacement JPM addressed the same K/A area and was successfully administered to all applicable applicants.
4OA6 Exit Meeting Summary
On March 8, 2007, the NRC provided conclusions and examination results to PNPS management representatives via the telephone. License numbers for five of five applicants were also provided during this time.
The NRC expressed appreciation for the cooperation and assistance that was provided during the preparation and administration of the examination by the licensees training staff.
ATTACHMENT:
SUPPLEMENTAL INFORMATION
ATTACHMENT
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
Robert Coolage Supervisor, Operator Training
Mark Santiago Superintendent, Operator Training
David Noyes Assistant Operations Manager
NRC
Gilbert A. Johnson Operations Engineer (Chief Examiner)
Joseph M. DAntonio Senior Operations Engineer
Peter A. Presby Operations Engineer
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
ITEM NUMBER TYPE DESCRIPTION
NONE
Post Exam Comments (NONE)
Attachment