August 31, 2006
SUBJECT:
FORT CALHOUN STATION - SECURITY INSPECTION 05000285/2006201
Dear Mr. Ridenoure:
On July 12, 2006, the US Nuclear Regulatory Commission (NRC) completed a security baseline inspection at the Fort Calhoun Station. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on July 12, 2006, with Ms. Mary Tesar, Division Manager, Nuclear Support Services and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. No findings of significance were identified within the scope of this inspection.
However, a requirement for additional inspection activities was identified and a Special Inspection (SIT) was conducted by Region IV inspectors from April 18 - July 5, 2006. The results of the SIT are documented in Inspection Report 05000285/2006015 which was issued on July 24, 2006.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related items contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection. Should you have any questions concerning this letter, please contact us. Your cooperation is appreciated.
Sincerely,
/RA/
Ronald J. Albert, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket No.: 50-285 License No.: DPR-40 Enclosure:
NRC Inspection Report No. 05000285/2006201 cc w/encl:
Robert E. Leopold, Administrator
Rick Sheehy, State Homeland Security Advisor
Alan Clark, Security Manager cc w/o encl:
Gary Cavanaugh, Supervisor, Regulatory Compliance Perry D. Robinson Mary Tesar, Division Manager, Nuclear Support Services