IR 05000259/1990009

From kanterella
Jump to navigation Jump to search
Insp Repts 50-259/90-09,50-260/90-09 & 50-296/90-09 on 900326-30.No Violations or Deviations Noted.Major Areas Inspected:Pipe Support Mods for Licensee IE Bulletins 79-02 & 79-14 Program & Previous Open Items
ML18033B290
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 04/24/1990
From: Blake J, Chou R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18033B288 List:
References
50-259-90-09, 50-259-90-9, 50-260-90-09, 50-260-90-9, 50-296-90-09, 50-296-90-9, IEB-79-02, IEB-79-14, IEB-79-2, NUDOCS 9005090390
Download: ML18033B290 (10)


Text

~R AKOIj c>

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323 Report Nos.:

50-259/90-09, 50-260/90-09, and 50-296/90-09 Licensee:

Tennessee Valley Authority 6N 38A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Docket Nos.:

50-259, 50-260 and 50-296 Facility Name:

Browns Ferry 1, 2, and

Inspection Conducted:

March 26-30, 1990 Inspector:

R.

C Ch Approved by:

~

~

~

.Ba Material a d Processes Engineering Branch Division of Reactor ety License Nos.:

DPR-33, DPR-52, and DPR-68 Date signed 4P ate igne SUMMARY Scope:

This routine, announced inspection was conducted in the areas of pipe support modifications for the licensee's IEBs 79-02/79-. 14 program and previous open items.

Results:

In the areas inspected, violations or deviations were not identified.

Three out of 34 pipe supports were found to have discrepancies and were additional examples of previous violation 89-57-01.

The licensee has,improved the weld quality; but should consider more training for construction foreman and guality Control (gC) inspectors, since all reinspected pipe supports had been signed off and accepted by foreman and gC inspectors.

PP0509O39 O,@90259 9OO426 POP AQOCK pDC

REPORT DETAILS 1.

Persons Contacted Licensee Employees

  • B. V. Baird, Civil Engineer P.

R. Baron, Site equality Manager

  • G. Campbell, Plant Manager
  • J. T. Carlin, Unit Operation Manager W. Massie, Site Licensing Engineer
  • J. McCarthy, Regulatory - Licensing Supervisor
  • L. W. Myers, Plant Manager

.

  • P. R. Rupert, Lead Civil Engineer
  • J. Smithson, Modification Engineer Supervisor
  • M. L. Strickland, guality Control (gC) Shift Manager
  • E. F. Thomas, Project Manager
  • N. M. Turner, guality Manager D. Winchester, Modification Engineer - Mechanical Other licensee employees contacted during this inspection included craftsmen, engineers, mechanics, technicians, and administrative personnel.

NRC Resident Inspectors

  • D. R. Carpenter, NRC Site Manager
  • E. F.'hristnot, Resident Inspector
  • K. D. Ivey, Jr.,

Resident Inspector

  • Attended,exit interview

2.

Licensee Action on Pipe Support Modifications.

a.

Reference I:

IE Bulletin 79-02,

"Pipe Support Base Plate Desi,gns Using Concrete Expansion Anchor Bolts" Reference 2:

IE Bulletin 79-14,

"Seismic Analyses For As-Built Safety-Related Piping System" (1)

Status This inspection involved pipe support modifications required to meet IEBs 79-02 and 79-14 before the restart of Unit 2.

The last inspection in this area was documented in Inspection Report Nos.

50-259$

260, 296/89-5 The licensee has completed approximately 850 pipe support modifications, which represents about 35 percent of the total to be completed before restart.

All pipe support modifications are scheduled to be completed by early July 1990 to support a

restart schedule of September 1990.

(2)

Walkdown Re-Inspection The inspector ramdonly selected 34 pipe supports which had previously been inspected and accepted by the licensee construction foreman and gC inspectors.

The 34 pipe supports, in five different systems, included large bore and small bore piping for safety-related systems located both inside and outside of containment.

The walkdown re-inspection was completed with assistance from licensee engineers and a

gC mechanical inspector who is also qualified as a

welding inspector.

The supports were partially re-inspected against detail drawings, including the original walkdown sketches, the Design Change Notices (DCNs),

and the Field Design Change Notices (FDCNs) for configuration, identification, fastener/

anchor installation, anchor size, anchor type, anchor marking, anchor edge distance, base plate size and thickness, plate warpage, member size, weld sizes, component identification numbers, component sizes and settings, dimensions, oxidation accumulation, maintenance, and damage/protection.

The supports re-inspected during the current inspection are listed below.

TABLE I Walkdown Re-Ins ection Su orts

~SN.

R 2-47B400S0009 2-47B400S0025 2-47B400S0029 2-47B400S0030 2-47B400S0133 2-47B400S0158 2-47B400S0159 2-47B400S0201 2-47B400S0209 2-47B400S0212 2-47B464S0119 000 001 001 000 001 001 001 001 001 000 000 System No.

001 001 001 001 001 001 001 001 001 001 070 System Main Steam Main Steam Main Steam Main Steam Main Steam, Main Steam Main Steam Mai'n Steam Main Steam Main Steam Reactor Building Cooling Water Large Bore or Small Bore Large Large Large Large Small Small Small Large Small Large Large Comments/

Discre ancies Note

TABLE I Walkdown Re-Ins ection Su orts (cont'd)

~SII

.

I System No.

Large Bore System or Coments/

~0i I

I

~0i 2-478 464S 0120 000 2-478464S0121 000 1-478450R0009 1-478450R0020 1-478450S0019 1-478450S0025 1-478450S0030 2-478450H0035 2-478450H0039 2-478450R0025 2-478455H0075 2-478455H0088 2-478462S0003 2-478462S0004 2-478462S0006 000 001 000 000 000 001 001 000 001 001 000 000 000 2-478462S0011 000 2-478462S0012 000 2-478462S0088 000 2-478462S0061 000 2-478462S0068 000 2-478462S0073

. 000 2-478462S0075 000 2-478462S0117 000 070 070 023 023 023 023 023 023 023 023 073 073 063 063 063 063 063 063 063 063 063 063 063 Reactor Building Cooling Water Reactor Building Cooling Water RHR Service Water RHR Service Water RHR Service Water RHR Service. Water RHR Service Water RHR Service Water RHR Service Water RHR Service Water HPCI HPCI Standby Liquid Control St'andby Liquid Control Standby Liquid Control Standby Liquid Control Standby Liquid Control Standby Liquid Control Standby Liquid Control Standby Liquid Control Standby Liquid Control Standby Liquid Control Standby Liquid Control Large Large Note

Small Small Smal 1 Small Small Small Small Small Small Small Note 4 Large Large Large Large Large Large Large Large

,

Note

Large Large Small Notes:

1.

A gap of 3/8" existed between the new cover plate and the existing cover plate (gusset plate)

on the far side of Section A201-A201.

The drawings for Support No. 2-478400S0201

did not have welds on both sides between the new plates and the existing plates which is a design deficiency; the gap between the new plate and the existing plate is a

construction deficiency.

The support rod contacts adjacent conduit.

Similar pipe clearance problems on other pipe supports were previously identified by an NRR Team Inspection as open item No.

EMG-016.

The licensee is working on this problem per Task No. TSD-S101.

This support was already identified and included in the task program by the licensee.

The drawings for support No. 2-478450R0025 stated expansion anchors without specifying

"wedge anchors."

Therefore, the design capacity for expansion anchors should be the lower capacity of Self-Drilled Expansion Anchors.

The

'design calculation used the higher capacity of wedge anchors which were based on the previous installation records.

Support 2-478462S0011 is located 2'-0 I/4" from the pipe elbow.

The drawing showed the support as 1'-0 1/16" from the elbow.

'VA General Construction Specification G-43 allows

+ 6" location tolerance for small bore piping.

The discrepancies as stated for the three supports shown in notes I, 3 and 4 are additional examples of the condition described in Violation 50-260/89-57-01.

Support Calculation Review The design calculations for Support Nos.

2-478400S0201 and I-478450R0012 were partially reviewed and evaluated for thoroughness, clarity, consistency, and accuracy.

The calcula-tions contained the purpose, assumptions, references, data, computations, summaries and conclusions, and attachments.

The attachments included existing pipe support configuration from walkdowns, proposed support modifications or Design Change Notices (DCNs),

Employee Concerns Checklist, and computer input and output for frame and base plate analyses.

The review included:

that the applied loads used were taken from the latest stress calculation; computer model, computer input and output, check of displacements, member size, weld sizes and symbols, bolt sizes, and standard component capacity and settings.

In general, the design calculations were of good quality, except for the computer input assumption which differed from the drawing indicated for Support No. 2-478400S0201.

The original wide flange, W10x33, with 20" gusset plate added at the bottom, was not qualified previously to carry the snubber load This wide flange was qualified by adding a

new cover plate on each side above the existing gusset plates, to reinforce the wide flange as a

box type beam and continue the gusset plate function for reinforcement.

The drawing did not require welds between the new cover plates and the existing gusset plates for reinforcement continuation.

Therefore, the weakest portion of this post is still the portion of wide flange W10x33 located between the new cover plate and the existing gusset plate.

The design input for this post assumed the'hole length as a rein-forced WIOx33 with the new cover plates without the discon-tinuity.

The licensee evaluated this problem and will modify the support again or rerun the computer analysis based on the field condition.

b.

(Open) Violation 50-260/89-57-01, Pipe Support Discrepancies This violation involved discrepancies found during a

previous inspection of the pipe support modification program.

The licensee's response letter dated March 16, 1990, was reviewed at the site by the inspector, and discussed with the licensee's engineers.

Items I, 2, and 3 of violations are considered to be acceptable and closed.

The licensee's response on Item 4 of the violation and the engineering disposition for DCN No. 910004A, dated febr uary 22, 1990, were not 'acceptable.

The inspector and the licensee's gC shift manager reinspected the gap or warpage for Support No.

I-47B450R0012 and found that the contact area was approximately

sq. in.

Therefore, the licensee should reevaluate this problem.

The commitments listed on Items I, 2, and 4 of Enclosure 2 of Response to Violation 89-57-01 were reviewed and considered to be acceptable.

TVA will reconsider its position on Item 3 of Enclosure 2, of the response, since the commitment conflicted with internal memorandum R28-900306-901, dated March 7, 1990.

The three new examples listed in Paragraph 2.a.(2)

are taken as indications that corrective actions are not yet complete.

This violation remains open.

3.

Exit Interview The inspection scope and results were summarized on March 30, 1990, with those persons indicated in paragraph 1.

The inspector described the areas inspected and discussed in detail the inspection results.

Proprietary information is not contained in this report.

Dissenting comments were not received from the licensee.

The inspector expressed the concern about the licensee's IEBs 79-02/79-14 program on modifications because discrepancies on three more supports were found during this inspectio