Annual Assessment Letter for Nine Mile Point Nuclear Station LLC, Units 1 and 2 (Report 05000220/2017006 and 05000410/2017006, Report 05000220/2017402 and 05000410/2017402, and Report 05000220/2017501 and 05000410/2017501)
ML18053A715
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 02/28/2018
From: Michelle Catts
NRC Region 1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2017006, IR 2017402, IR 2017501
Download: ML18053A715 (7)


Text

ebruary 28, 2018

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR NINE MILE POINT NUCLEAR STATION LLC, UNITS 1 AND 2 (REPORT 05000220/2017006 AND 05000410/2017006, REPORT 05000220/2017402 AND 05000410/2017402, AND REPORT 05000220/2017501 AND 05000410/2017501)

Dear Mr. Hanson:

The NRC has completed its end-of-cycle performance assessment of Nine Mile Point Nuclear Station LLC, Units 1 and 2 (Nine Mile Point), reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2017 through December 31, 2017. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined the performance at Nine Mile Point during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green.) Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2019. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In addition to normal baseline inspections, the NRC will be performing Inspection Procedure (IP) 71003, Post Approval Site Inspection For License Renewal, for Nine Mile Point Unit 1 and IP 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants, at your facility. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 610-337-5012 with any questions you have regarding this letter.

Sincerely,

/RA/

Michelle Catts, Acting Chief Projects Branch 1 Division of Reactor Projects Docket Nos. 50-220 and 50-410 License Nos. DPR-63 and NPF-69 Enclosure: Nine Mile Point Inspection Plan cc: Distribution via ListServ

ML18053A715 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME A.Rosebrook M.Catts DATE 2/15/18 2/20/18

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count RAD SAFETY INSP 1 1, 2 03/05/2018 03/09/2018 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 03/05/2018 03/09/2018 IP 71151 000746 Performance Indicator Verification NMP Unit 2 ISI 1 2 04/23/2018 04/27/2018 IP 71111.08G 000701 Inservice Inspection Activities - BWR RAD SAFETY INSP 1 1, 2 04/30/2018 05/04/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/30/2018 05/04/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 04/30/2018 05/04/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/30/2018 05/04/2018 IP 71124.04 000729 Occupational Dose Assessment MC&A 1 1, 2 06/18/2018 06/22/2018 IP 71130.11 000742 Material Control and Accounting (MC&A)

EP PROGRAM INSPECTION 1 1, 2 07/16/2018 07/20/2018 IP 71114.02 000717 Alert and Notification System Testing 1, 2 07/16/2018 07/20/2018 IP 71114.03 000718 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 07/16/2018 07/20/2018 IP 71114.05 000720 Correction of Emergency Preparedness Weaknesses and Deficiencies 1, 2 07/16/2018 07/20/2018 IP 71151 001397 Performance Indicator Verification RADWASTE 1 1, 2 07/23/2018 07/27/2018 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation RAD INSTRUNMENTATION 1 1, 2 08/06/2018 08/10/2018 IP 71124.05 000729 Radiation Monitoring Instrumentation TRIENNIAL FIRE PROTECTION 6 1 09/10/2018 09/14/2018 IP 71111.05T 000696 Fire Protection (Triennial)

2 09/10/2018 09/14/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)

1 09/24/2018 09/28/2018 IP 71111.05T 000696 Fire Protection (Triennial)

2 09/24/2018 09/28/2018 IP 71111.05XT 000697 Fire Protection - NFPA 805 (Triennial)

This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.

1/24/2018 1:30:08 PM

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count RAD SAFETY INSPECTION 1 1, 2 10/15/2018 10/19/2018 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/15/2018 10/19/2018 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/15/2018 10/19/2018 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/15/2018 10/19/2018 IP 71124.04 000729 Occupational Dose Assessment 1, 2 10/15/2018 10/19/2018 IP 71151 000746 Performance Indicator Verification ACCESS CONTROL, EQUIP PERF, TRAINING 3 1, 2 10/15/2018 10/19/2018 IP 71130.02 000734 Access Control 1, 2 10/15/2018 10/19/2018 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 10/15/2018 10/19/2018 IP 71130.07 000739 Security Training 1, 2 10/15/2018 10/19/2018 IP 71151 001338 Performance Indicator Verification NMP1 REQUAL INSP W/ P/F RESULTS 2 1 10/29/2018 11/02/2018 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance -

Annual 1 10/29/2018 11/02/2018 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance -

Biennial NMP1 INITIAL OL EXAM 4 1 11/05/2018 11/09/2018 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1 12/03/2018 12/14/2018 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

NMP UNIT 1 - LICENSE RENEWAL PHASE 4 2 1 02/25/2019 03/01/2019 IP 71003 000687 Post-Approval Site Inspection for License Renewal INSERVICE INSPECTION - UNIT 1 1 1 03/25/2019 03/29/2019 IP 71111.08G 000701 Inservice Inspection Activities - BWR RAD SAFETY OUT 1 1, 2 04/01/2019 04/05/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 04/01/2019 04/05/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 04/01/2019 04/05/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 04/01/2019 04/05/2019 IP 71124.04 000729 Occupational Dose Assessment This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.

1/24/2018 1:30:08 PM

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count 50.59 PROCESS 3 1, 2 04/22/2019 04/26/2019 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments RAD SAFETY 01,02,03,04 1 1, 2 05/20/2019 05/24/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 05/20/2019 05/24/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 05/20/2019 05/24/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 05/20/2019 05/24/2019 IP 71124.04 000729 Occupational Dose Assessment ACCESS CONTROL, PROTECTIVE STRATEGY, TSR 4 1, 2 05/20/2019 05/24/2019 IP 71130.02 000734 Access Control 1, 2 05/20/2019 05/24/2019 IP 71130.05 000737 Protective Strategy Evaluation 1, 2 05/20/2019 05/24/2019 IP 71130.14 000743 Review of Power Reactor Target Sets 1, 2 05/20/2019 05/24/2019 IP 71151 001338 Performance Indicator Verification CYBER MS8 2 1, 2 06/03/2019 06/07/2019 IP 71130.10P 000741 Cyber Security 1, 2 06/17/2019 06/21/2019 IP 71130.10P 000741 Cyber Security ISFSI Loading Campaign Inspection 2 1, 2 07/22/2019 07/26/2019 IP 60855 001001 Operation Of An ISFSI 1, 2 07/22/2019 07/26/2019 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants RAD SAFETY 01,02,03,04 1 1, 2 07/22/2019 07/26/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 07/22/2019 07/26/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 07/22/2019 07/26/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 07/22/2019 07/26/2019 IP 71124.04 000729 Occupational Dose Assessment 1, 2 07/22/2019 07/26/2019 IP 71151 000746 Performance Indicator Verification NMP EP EXERCISE INSPECTION 5 1, 2 07/29/2019 08/02/2019 IP 71114.01 000716 Exercise Evaluation Heat Sink 1 1, 2 08/05/2019 08/09/2019 IP 71111.07T 000700 Heat Sink Performance -Triennial This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.

1/24/2018 1:30:08 PM

IP 22 Inspection Activity Plan Report Nine Mile Point 01/01/2018 - 12/31/2019 Unit Start End Activity CAC Title Staff Count PI&R BIENNIAL 1 1, 2 08/12/2019 08/16/2019 IP 71152B 000747 Problem Identification and Resolution 1, 2 08/26/2019 08/30/2019 IP 71152B 000747 Problem Identification and Resolution RAD SAFETY REMP 1 1, 2 09/09/2019 09/13/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 09/09/2019 09/13/2019 IP 71151 000746 Performance Indicator Verification NMP2 REQUAL INSP W/ P/F RESULTS 2 2 10/21/2019 10/25/2019 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance -

Annual 2 10/21/2019 10/25/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance -

Biennial EQ PROGRAM 3 1, 2 10/21/2019 10/25/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

1, 2 11/04/2019 11/08/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)

NMP2 INITIAL OL EXAM 4 2 11/11/2019 12/06/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

2 12/09/2019 12/20/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.