IR 05000220/2017005

From kanterella
Jump to navigation Jump to search
Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 - Inspection Report 05000220/2017005 and 05000410/2017005
ML17241A059
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 08/28/2017
From: Anthony Dimitriadis
Reactor Projects Branch 1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2017005
Download: ML17241A059 (5)


Text

August 28, 2017

SUBJECT:

UPDATED INSPECTION PLAN FOR NINE MILE POINT NUCLEAR STATION

UNITS 1 AND 2 - INSPECTION REPORT 05000220/2017005 AND

05000410/2017005

Dear Mr. Hanson:

The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for your Nine Mile Point Nuclear Station Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.

In addition to normal baseline inspection, the NRC will be performing a temporary instruction under Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans.

Please contact me at 610-337-6953 with any questions you have regarding this letter.

Sincerely,

/RA/

Anthony Dimitriadis, Chief Reactor Projects Branch 1 Division of Reactor Projects

Docket Nos.

50-220 and 50-410 License Nos. DPR-63 and DPR-69

Enclosure:

Inspection Plan

cc: Distribution via ListServ

ML17241A059

SUNSI Review

Non-Sensitive Sensitive

Publicly Available Non-Publicly Available

OFFICE RI/DRP RI/DRP

NAME ARosebrook ADimitriadis

DATE 8/15/17 8/28/17

Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Nine Mile Point Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 1 of 3 08/09/2017 12:32:57 10/23EXM

- NMP2 INITIAL OL EXAM

2 FY 18 NINE MILE PT 2 EXAM (OCTOBER 2017)

U01955 10/23/2017 10/27/2017

FY 18 NINE MILE PT 2 EXAM (OCTOBER 2017)

U01955 12/11/2017 12/15/2017 RS345

- HP INSPECTION

1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 07/24/2017 07/28/2017 1, 2 IP Occupational Dose Assessment 71124.04 07/24/2017 07/28/2017 1, 2 IP Radiation Monitoring Instrumentation 71124.05 07/24/2017 07/28/2017 TI-191

- FUKUSHIMA LESSONS-LEARNED

1, 2 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 08/21/2017 08/25/2017 7111121M

- DESIGN BASES ASSURANCE INSPECTION (TEAM)

1, 2 IP Design Bases Assurance Inspection (Teams)

7111121M 09/18/2017 09/22/2017 1, 2 IP Design Bases Assurance Inspection (Teams)

7111121M 10/02/2017 10/06/2017 7111111B

- NMP2 REQUAL INSPECTION WITH P/F RESULTS

2 IP Licensed Operator Requalification Program - Annual Review 7111111A 10/16/2017 10/20/2017

IP Licensed Operator Requalification Program 7111111B 10/16/2017 10/20/2017 EP

- EP EXERCISE INSPECTION

1, 2 IP Exercise Evaluation 7111401 10/23/2017 10/27/2017 1, 2 IP Performance Indicator Verification 71151 10/23/2017 10/27/2017 RS12

- HP INSPECTION

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/18/2017 09/22/2017 1, 2 IP Occupational ALARA Planning and Controls 71124.02 09/18/2017 09/22/2017

IP Occupational Exposure Control Effectiveness 71151-OR01 09/18/2017 09/22/2017 71152B

- PI&R BIENNIAL

1, 2 IP Problem Identification and Resolution 71152B 10/30/2017 11/03/2017 1, 2 IP Problem Identification and Resolution 71152B 11/13/2017 11/17/2017 71124

- RAD SAFETY INSP

1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 03/05/2018 03/09/2018 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 03/05/2018 03/09/2018 71124

- RAD SAFETY INSP

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/30/2018 05/04/2018 1, 2 IP Occupational ALARA Planning and Controls 71124.02 04/30/2018 05/04/2018 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/30/2018 05/04/2018 1, 2 IP Occupational Dose Assessment 71124.04 04/30/2018 05/04/2018 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Nine Mile Point Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 2 of 3 08/09/2017 12:32:57 U2 ISI

- UNIT 2 INSERVICE INSPECTION

2 IP Inservice Inspection Activities - BWR 7111108G 04/23/2018 04/27/2018 12/03EXM

- NMP1 INITIAL OL EXAM

1 FY19 NINE MILE PT 1 EXAM (DECEMBER 2018)

U01975 11/04/2018 11/09/2018

FY19 NINE MILE PT 1 EXAM (DECEMBER 2018)

U01975 12/03/2018 12/07/2018 EP

- EP PROGRAM INSPECTION

1, 2 IP Alert and Notification System Testing 7111402 07/16/2018 07/20/2018 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 07/16/2018 07/20/2018 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 07/16/2018 07/20/2018 1, 2 IP Performance Indicator Verification 71151 07/16/2018 07/20/2018 71124.08

- RADWASTE

1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 07/23/2018 07/27/2018 71124.05

- RAD INSTRUNMENTATION

1, 2 IP Radiation Monitoring Instrumentation 71124.05 08/06/2018 08/10/2018 REQUAL

- NMP1 REQUAL INSP W/ P/F RESULTS

1 IP Licensed Operator Requalification Program - Annual Review 7111111A 10/29/2018 11/02/2018

IP Licensed Operator Requalification Program 7111111B 10/29/2018 11/02/2018 7111105T

- TRIENNIAL FIRE PROTECTION

1 IP Fire Protection [Triennial]

7111105T 09/10/2018 09/14/2018

IP Fire Protection - NFPA 805 (Triennial)

7111105X 09/10/2018 09/14/2018

IP Fire Protection [Triennial]

7111105T 09/24/2018 09/28/2018

IP Fire Protection - NFPA 805 (Triennial)

7111105X 09/24/2018 09/28/2018 71124

- RAD SAFETY INSPECTION

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/15/2018 10/19/2018 1, 2 IP Occupational ALARA Planning and Controls 71124.02 10/15/2018 10/19/2018 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/15/2018 10/19/2018 1, 2 IP Occupational Dose Assessment 71124.04 10/15/2018 10/19/2018 LR PH 4

- NMP UNIT 1 - LICENSE RENEWAL PHASE 4

1 IP Post-Approval Site Inspection for License Renewal 71003 02/25/2019 03/01/2019 U1 ISI

- INSERVICE INSPECTION - UNIT 1

1 IP Inservice Inspection Activities - BWR 7111108G 03/25/2019 03/29/2019 71124

- RAD SAFETY OUT

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/01/2019 04/05/2019 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Nine Mile Point Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 3 of 3 08/09/2017 12:32:57 71124

- RAD SAFETY OUT

1, 2 IP Occupational ALARA Planning and Controls 71124.02 04/01/2019 04/05/2019 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/01/2019 04/05/2019 1, 2 IP Occupational Dose Assessment 71124.04 04/01/2019 04/05/2019 7111117T

- 50.59 PROCESS

1, 2 IP Evaluations of Changes, Tests, and Experiments 7111117T 04/22/2019 04/26/2019 71124

- RAD SAFETY 01,02,03,04

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/20/2019 05/24/2019 1, 2 IP Occupational ALARA Planning and Controls 71124.02 05/20/2019 05/24/2019 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/20/2019 05/24/2019 1, 2 IP Occupational Dose Assessment 71124.04 05/20/2019 05/24/2019 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.