GO2-15-093, Second Six-Month Status Update Report for the Implementation of NRC Order EA-13-109 - Overall Integrated Plan for Reliable Hardened Containment Vents Under Severe Accident Conditions

From kanterella
Jump to navigation Jump to search
Second Six-Month Status Update Report for the Implementation of NRC Order EA-13-109 - Overall Integrated Plan for Reliable Hardened Containment Vents Under Severe Accident Conditions
ML15181A436
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 06/30/2015
From: Swank D
Energy Northwest
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
EA-13-109, GO2-15-093
Download: ML15181A436 (10)


Text

David A. Swank Columbia Generating Station P.O. Box 968, PE04 Richland, WA 99352-0968 Ph. 509-377-2309 l F. 509-377-2354 daswank@energy-northwest.com June 30, 2015 GO2-15-093 EA-13-109 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

COLUMBIA GENERATING STATION, DOCKET NO. 50-397 ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 -

OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS

References:

1. NRC Order EA-12-050, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents, March 12, 2012
2. NRC Order EA-13-109, Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions, June 6, 2013
3. Letter GO2-14-107, dated June 30, 2014, from DA Swank, Energy Northwest, to the NRC, "Energy Northwest's Phase 1 Response to NRC Order EA-13-109 - Overall Integrated Plan for Reliable Hardened Containment Vents under Severe Accident Condition"
4. Letter GO2-14-175, dated December 17, 2014, from DA Swank, Energy Northwest, to the NRC, "Energy Northwests First Six-Month Status Update Report for the Implementation of NRC Order EA-13-109

- Overall Integrated Plan for Reliable Hardened Containment Vents under Severe Accident Conditions"

Dear Sir or Madam,

On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-050, (Reference 1) which directed Energy Northwests Columbia Generating Station (Columbia) to have a reliable hardened vent to remove decay heat and maintain control of containment pressure within acceptable limits following events that result in the loss of active containment heat removal capability or prolonged Station Blackout.

On June 6, 2013, the NRC issued Order EA-13-109; (Reference 2) which rescinded the requirements imposed in Section IV and Attachment 2 of Order EA-12-050 and replaced

ENERGY NORTHWEST'S SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109- OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 2 of 2 them with the requirements contained in Section IV and Attachment 2 of Order EA-13-109. Order EA-13-109,Section IV, D.1 required all licensees to submit an Overall Integrated Plan (OIP) including a description of how compliance with the Phase 1 requirements described in Attachment 1 of the Order will be achieved.

In Reference 3, Energy Northwest submitted Columbia's OIP for the installation of a reliable hardened severe accident capable wetwell vent and in Reference 4, submitted the first 6-month update for that plan.

The attachment to this letter provides Energy Northwest's second six-month update report of Columbia's status of implementing Order EA-13-109 pursuant to Section IV, Condition C.2 of Reference 2.

There are no new or revised regulatory commitments contained in this letter. If you have any questions or require additional information, please contact Ms. L. L. Williams at (509) 377-8148.

I declare under penalty of perjury that the foregoing is true and correct.

"'1 ? f't:f ..,.--

Executed on the e<:2 day of J\Un e, , 2015 Respectfully, D.A. Swank Assistant Vice President, Engineering Attachment Second Six-Month Status Update Report for the Implementation of NRC Order EA-13-1 09 cc: NRC Region IV Administrator NRC NRA Project Manager NRC Senior Resident lnspector/988C CD Sonoda - BPA/1399 (email)

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS ATTACHMENT COLUMBIA GENERATING STATION, DOCKET NO. 50-397 SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 1 of 7 1.0 Introduction On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-050, (Reference 1) which directed Energy Northwest's Columbia Generating Station (Columbia), to have a reliable hardened containment vent (HCV) to remove decay heat and maintain control of containment pressure within acceptable limits following events that result in the loss of active containment heat removal capability or prolonged Station Blackout.

On June 6, 2013, the NRC issued Order EA-13-109; (Reference 2) which rescinded the requirements imposed in Section IV and Attachment 2 of Order EA-12-050 and replaced them with the requirements contained in Section IV and Attachment 2 of Order EA-13-109. Order EA-13-109,Section IV, D.1 required all licensees with Mark I and Mark II containments to submit an Overall Integrated Plan (OIP) including a description of how compliance with the Phase 1 requirements described in Attachment 2 of the Order will be achieved. In Reference 3, Energy Northwest submitted Columbia's Overall Integrated Plan (OIP) for the installation of a reliable, severe accident capable, hardened containment venting system.

Section IV, Condition D.3, of Reference 2 also required status reports at 6-month intervals following the submittal of the Phase 1 OIP. This report is Energy Northwest's second six-month status report of Columbia's implementation of Phase 1 for Order EA-13-109.

2.0 Milestone Accomplishments The following milestones have been completed since the update submitted on December 17, 2014.

  • Submittal of second 6-month update 3.0 Milestone Schedule Status The following provides an updated milestone schedule to support reliable hardened vent OIP. There are three Target Completion Date changes due to design development delays. These changes have not impacted the overall scheduled completion.

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 2 of 7 Revised Target Target Milestones Completion Activity Status Completion Date Date Correspondence & Reports:

Submit the Reliable Hardened Containment Vents under Severe Accident Conditions Jun 30, 2014 Completed N/A Overall Integrated Plan for Phase 1 First Status Update Report for the Overall Reliable Hardened Containment Vents under Dec 31, 2014 Completed N/A Severe Accident Conditions Integrated Plan for Phase 1 Second Status Update Report for the Overall Reliable Hardened Containment Vents Jun 30, 2015 Completed N/A under Severe Accident Conditions Integrated Plan for Phase 1 Third Status Update Report for the Overall Reliable Hardened Containment Vents under Dec 31, 2015 N/A Severe Accident Conditions Integrated Plan for Phase 1 Fourth Status Update Report for the Overall Reliable Hardened Containment Vents under Jun 30, 2016 N/A Severe Accident Conditions Integrated Plan for Phase 1 Fifth Status Update Report for the Overall Reliable Hardened Containment Vents under Dec 31, 2016 N/A Severe Accident Conditions Integrated Plan for Phase 1 Final Completion Report for the Overall Reliable Hardened Containment Vents under June 2017 N/A Severe Accident Conditions Integrated Plan for Phase 1

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 3 of 7 Revised Target Target Milestones Completion Activity Status Completion Date Date Engineering & Modifications:

Develop Engineering Design for Modifications (100% package) Apr 2015 In Process Dec 2015 for Phase 1 Plant Modification Installation for Awaiting design June 2017 NA Phase 1 completion Program & Procedures:

Develop the program and Awaiting design procedures to operate, test, and June 2015 Dec 2016 completion maintain the HVCS for Phase 1 Coordinate procedures for HCVS Awaiting design with AOPs, EOPs, SAGs FSGs, Mar 2017 NA completion and SAMGs for Phase 1 Implement the procedures for Awaiting design June 2017 NA Phase 1 completion Operations & Training:

Develop the training for all Awaiting design personnel expected to operate Mar 2017 NA completion the HCVS - Phase 1 Complete the training of Awaiting design Mar 2017 Jun 2017 personnel - Phase 1 completion 4.0 Changes to Compliance Method Columbia will be moving the rupture disk to inside the secondary containment and does not anticipate any changes to the compliance method. Any changes in the compliance method will be provided in a subsequent update.

5.0 Need for Relief/Relaxation and Basis for the Relief/Relaxation Energy Northwest expects to fully comply with the Order and its implementation date and does not anticipate a request for relief and/or relaxation of Order EA 109, Phase 1.

6.0 Open Items There are no changes in the licensee identified open items listed below. A new table of the open items from the Interim Staff Evaluation (Reference 5) has been added for completeness.

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 4 of 7 Licensee Identified Open Items from Overall Integrated Plan Open Item Open Items Action Status Response Number Provide resolution of the potential Columbia will use a rupture disk to secondary containment bypass leakage 1 Closed prevent secondary containment path in the first 6-month update of the bypass leakage HCVS OIP Evaluate the location of the ROS for 2

accessibility.

Determine the location of the portable air 3 compressor and evaluate for accessibility under SA HCVS use.

Evaluate the location of the FLEX DGs 4 for accessibility under Severe Accident HCVS use.

Confirm suppression pool heat capacity Calculation ME-02-14-02, Revision 0, Appendix C confirms that there is sufficient heat capacity in the 5 Closed suppression pool water when at a minimum Technical Specification level to control pressure in containment before venting commences.

Determine the method of qualification for 6

each instrument listed Complete the evaluation to determine accessibility, habitability, staffing 7

sufficiency, and communication capability of the ROS.

Identify design codes after design is 8

finalized.

Equipment qualifications will include temperature, pressure, radiation level, 9 and total integrated dose radiation from the effluent vent pipe at local and remote locations.

Provide site-specific details of the EOPs 10 when available.

List of Open Items from the Interim Staff Evaluation (ISE)

ISE Item Action Status Response Number Make available for NRC staff audit 1

the location of the ROSs.

Make available for NRC staff audit 2 the location of the portable air compressor.

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 5 of 7 List of Open Items from the Interim Staff Evaluation (ISE)

ISE Item Action Status Response Number Make available for NRC staff audit 3 the location of the portable diesel generators.

Make available for NRC staff audit an evaluation of temperature and radiological conditions to ensure that 4

operating personnel can safely access and operate controls and support equipment.

Make available for NRC staff audit analyses demonstrating that HCVS has the capacity to vent the steam/energy equivalent of one percent of uprated licensed/rated thermal power (unless a lower value is justified), and that the suppression 5 pool and the HCVS together are able to absorb and reject decay heat, such that following a reactor shutdown from full power containment pressure is restored and then maintained below the primary containment design pressure and the primary containment pressure limit.

Make available for NRC staff audit the descriptions of local conditions (temperature, radiation and humidity) anticipated during ELAP and severe accident for the components (valves, instrumentation, sensors, 6 transmitters, indicators, electronics, control devices, etc.) required for HCVS venting including confirmation that the components are capable of performing their functions during ELAP and severe accident conditions.

Make available for NRC staff audit documentation of the HCVS nitrogen 7

pneumatic system design including sizing and location.

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 6 of 7 List of Open Items from the Interim Staff Evaluation (ISE)

ISE Item Action Status Response Number Make available for NRC staff audit the final sizing evaluation for HCVS 8 batteries/battery charger including incorporation into FLEX DG loading calculation.

Make available for NRC staff audit documentation that demonstrates adequate communication between 9 the remote HCVS operation locations and HCVS decision makers during ELAP and severe accident conditions.

Provide a description of the strategies for hydrogen control that minimizes 10 the potential for hydrogen gas migration and ingress into the reactor building or other buildings.

Make available for NRC staff audit descriptions of all instrumentation 11 and controls (existing and planned) necessary to implement this order including qualification methods.

Make available for NRC staff audit documentation of an evaluation verifying the existing containment isolation valves, relied upon for the 12 HCVS, will open under the maximum expected differential pressure during BDBEE and severe accident wetwell venting.

Make available for NRC staff audit 13 site specific details of the EOPs when available.

Provide justification for not leak testing the HCVS every three 14 operating cycles and after restoration of any breach of system boundary within buildings.

ENERGY NORTHWESTS SECOND SIX-MONTH STATUS UPDATE REPORT FOR THE IMPLEMENTATION OF NRC ORDER EA-13-109 - OVERALL INTEGRATED PLAN FOR RELIABLE HARDENED CONTAINMENT VENTS UNDER SEVERE ACCIDENT CONDITIONS Page 7 of 7 7.0 Potential Safety Evaluation Impacts Energy Northwest does not anticipate any impacts to the Interim Safety Evaluation.

8.0 References

1. NRC Order EA-12-050, Order Modifying Licenses with Regard to Reliable Hardened Containment Vents, March 12, 2012 (ADAMS Accession No.:

ML12054A694)

2. NRC Order EA-13-109, Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions, June 6, 2013 (ADAMS Accession No.: ML13143A334 (Pkg.))
3. Letter GO2-14-107, dated June 30, 2014, from DA Swank, Energy Northwest, to the NRC, "Energy Northwest's Phase 1 Response to NRC Order EA-13-109 - Overall Integrated Plan for Reliable Hardened Containment Vents under Severe Accident Condition" (ADAMS Accession No.: ML14191A688)
4. Letter GO2-14-175, dated December 17, 2014, from DA Swank, Energy Northwest, to the NRC, "Energy Northwests First Six-Month Status Update Report for the Implementation of NRC Order EA-13-109 - Overall Integrated Plan for Reliable Hardened Containment Vents under Severe Accident Conditions" (ADAMS Accession No.: ML14357A069)
5. NRC letter "Columbia Generating Station - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Phase 1 of Order EA-13-109 (Severe Accident Capable Hardened Vents)" March 25, 2015 (TAC No.

MF4383) (ADAMS Accession No.: ML14335A258)