GO2-12-151, Energy Northwest'S Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation

From kanterella
Jump to navigation Jump to search
Energy Northwest'S Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation
ML13091A138
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/25/2012
From: Swank D
Energy Northwest
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GO2-12-151
Download: ML13091A138 (2)


Text

ENERGY EColumbia POGenerating o6,P2 Station Richland, WA 99352-0968 EST Ph. 509-377-23091 F.509-77-2354 dNORTHW aswank @ energy-northwest.com October 25, 2012 10 CFR 2.202 G02-12-151 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

COLUMBIA GENERATING STATION, DOCKET NO. 50-397 ENERGY NORTHWEST'S INITIAL STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO RELIABLE SPENT FUEL POOL INSTRUMENTATION

Reference:

1. NRC Order Number EA-1 2-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation
2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-1 2-051, Reliable Spent Fuel Pool Instrumentation, Rev 0, August 29, 2012

Dear Sir or Madam:

On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued the referenced Order (Reference 1) to Columbia Generating Station (Columbia). Reference 1 directs Columbia to have reliable spent fuel pool level instrumentation. Specific requirements are outlined in Attachment 2 of Reference 1. Full implementation is required no later than either two refueling cycles after submittal of the overall integrated plan or by December 31, 2016, whichever comes first.

Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms Energy Northwest, the licensee for Columbia, has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in the spent fuel storage pool as described in Attachment 2 of Reference 1.

ENERGY NORTHWEST'S INITIAL STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION Page 2 of 2 Major activities completed during this reporting period:

" Identification of resources and initiation of project plans, including development of milestones, to assure compliance with Reference 1.

" Continued participation with industry in selecting a technology to be used and parameters to be considered.

Planned activities for the next six months:

" Development and submittal of the overall integrated plan.

  • Development of a conceptual design.

No technical difficulties have been identified at this time that could affect the ability to provide the February 28, 2013, submittal.

Project milestones scheduled through completion of installation and testing:

  • A project milestones schedule will be provided with the overall integrated plan.
  • Implementation of the order will be completed for Columbia prior to startup from Refueling Outage R22. This outage is scheduled to begin on May 1, 2015.

There are no new commitments contained in this letter. If you have any questions regarding the above, please contact Mr. Z. K. Dunham at (509) 377-4735.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the date of this letter.

Respectfully, D. A. Swank Assistant Vice President, Engineering cc: NRC Region IVAdministrator NRC NRR Project Manager NRC Senior Resident Inspector/988C AJ Rapacz - BPA/1 399