Entergy Operations, Inc.

P. O. Box 756 Port Gibson, MS 39150 James Nadeau Manager, Regulatory Assurance Grand Gulf Nuclear Station Tel. (601) 437-2103 GNRO-2014/00048 July 28, 2014 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Correction of Technical Specification Typographical Error Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29

REFERENCE:

1. Grand Gulf Nuclear Station Unit 1 - Issuance of Amendment RE:

Extended Power Uprate (TAC NO. ME4679)

2. Letter: License Amendment Request Extended Power Uprate Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29, dated September 8, 2010 (ADAMS Accession No. ML102660403)
3. Proposed Guidance for Correction of Technical Specification Typographical Errors, SECY-96-238, dated November 19, 1996

Dear Sir or Madam:

This letter requests the NRC approval of a correction to-typographical errors in Grand Gulf Nuclear Station Unit 1 Technical Specifications which were inadvertently introduced during License Amendment 191 (Reference 1).

It was not addressed in the notice to public nor reviewed by the NRC and falls within the scope of the guidance provided in SECY-96-238 (Reference 3) for corrections.

Attachement 1 describes the typographical errors and corrections. Attachment 2 provides a marked-up of the Technical Specification pages. Attachment 3 provides a clean copy of the Technical Specification pages. Entergy will issue the change notification to all holders of controlled copies of the Grand Gulf Nuclear Station Technical Specifications upon receipt of NRC approval of these corrections.

This letter contains no new commitments. If you have any questions or require additional information, please contact James Nadeau at 601-437-2103.

Sincerely, L /Jf~

IN/ram (;l ~ ~

GNRO-2014/00048 Page 2 of 2 Attachments: 1. Description of Technical Specification Typographical Errors

2. Marked-up Technical Specification Pages Correcting the Typographical Errors
3. Clean Copies of Technical Specification Pages Correcting the Typographical Errors cc:

U.S. Nuclear Regulatory Commission ATTN: Mr. A. Wang, NRR/DORL Mail Stop OWFN/8 G14 11555 Rockville Pike Rockville, MD 20852-2378 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150 U. S. Nuclear Regulatory Commission ATTN: Marc L. Dapas (w/2)

Regional Administrator, Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511

Attachment 1 to GNRO-2014/00048 Description of Technical Specification Typographical Errors GNRO-2014/00048 Page 1 of 1 A. Requested Action Consistent with the information contained in SECY-96-238, Grand Gulf Nuclear Station is requesting correction for two inadvertent typographical errors that were introduced into the Grand Gulf Nuclear Station Technical Specification.

B. Typographical Error Two typographical errors were introduced into the Grand Gulf Nuclear Station Technical Specification (TS) during License Amendment 191 Reference 1). The specification of the errors and proposed" corrections are described below.

TS Table of Content page iv Amendment 191 did not include the listing for Technical Specification 3.7.7, Main Turbine Bypass System.

This error was not noticed to the public nor approved by the NRC during review and approval of Amendment 191.

TS Table of Content page xi Amendment 191 did not include the listing for Technical Specification B 3.7.7, Main Turbine Bypass System.

This error was not noticed to the public nor approved by the NRC during review and approval of Amendment 191.

C. Corrections to the Affected Technical Specification Pages SECY96-238, (Reference 1) provides guidance to correct inadvertent typographical errors in the Technical Specification pages.

The above typographical errors were not noticed to the public nor reviewed by the NRC as part the application amendment process. Therefore it may be corrected without a license amendment.

Accordingly, upon approval from the NRC, corrected TS table of content pages iv and xi will be distributed to all holders of controlled TS.

Attachment 2 to GNRO*2014/00048 Marked-up Technical Specification Pages Correcting the Typographical Errors Table of Contents Page iv Table of Contents Page xi

TABLE OF CONTENTS 3.6 CONTAINMENT SYSTEMS (continued) 3.6.4.2 Secondary Containment Isolation Valves 3.6-45 (SCIVs) 3.6.4.3 Standby Gas Treatment (SGT) System 3.6-49 3.6.5.1 Drywell 3.6-52 3.6.5.2 Drywell Air Lock 3.6-54 TR3.6.5.2 Drywell Air Lock Instrumentation 3.6-57-11 3.6.5.3 Drywell Isolation Valves 3.6-58 3.6.5.4 Drywell Pressure 3.6-62 3.6.5.5 Drywell Air Temperature 3.6-63 3.6.5.6 Drywell Vacuum Relief System 3.6-64 TR3.6.5.6 Drywell Vacuum Breaker and Associated 3.6-67-1 Isolation Valve Position Indication 3.7 PLANT SYSTEMS 3.7-1 3.7.1 Standby Service Water (SSW) System and 3.7-1 Ultimate Hept Sink (UHS)

TR3.7.1 Standby Service Water (SSW) System and 3.7-4-1 Ultimate Heat Sink (UHS) - Shutdown 3.7.2 High Pressure Core Spray' (HPCS) Service 3.7-5 Water System (SWS)

TR3.7.2 High Pressure Core Spray (HPCS) Service 3.7-5-1 Water System (SWS) - Shutdown 3.7.3 Control Room Fresh Air (CRFA) System 3.7-6 3.7.4 Control Room Air Conditioning (AC) System 3.7-9 3.7.5 Main Condenser Offgas 3.7-12 3.7.6 Fuel Pool Water Level 3.7-14 TR3.7.6 Fuel Pool Water Level non TS) 3.7-14-1 3.8 3.8 I 3.8.1 3.8-1 3.8.2 3.8-18 3.8.3 3.8-22 3.8.4 3.8-26 3.8.5 3.8-31 3.8.6 3.8-34 3.8.7 3.8-38 3.8.8 3.8-40 3.9 REFUELING OPERATIONS 3.9-1 3.9.1 Refueling Equipment Interlocks 3.9-1 3.9.2 Refuel Position One-Rod-Out Interlock 3.9-2 3.9.3 Control Rod Position 3.9-4 3.9.4 Control Rod Position Indication 3.9-5 3.9.5 Control Rod OPERABILITY - Refueling 3.9-7 GRAND GULF iv 12/05

TABLE OF CONTENTS B 3.6 CONTAINMENT SYSTEMS (continued)

B 3.6.1.4 Primary Containment Pressure B 3.6-26 B 3.6.1.5 Primary Containment Air Temperature B 3.6-29 B:3.6.1.6 Low-Low Set (LLS) Valves B 3.6-32 B 3.6.1.7 Residual Heat Removal (RHR) Containment B 3.6-36 Spray System B 3.6.1.8 Feedwater Leakage Control System (FWLCS) B 3.6-41 B 3.6.1.9 Main Stearn Isolation Valve (MSIV) Leakage B 3.6-44 Control System (LCS)

B 3.6.2.1 Suppression Pool Average Temperature B 3.6-48 B 3.6.2.2 Suppression Pool Water Level B 3.6-53 B 3.6.2.3 Residual Heat Removal (RHR) Suppression B 3.6-56 pool Cooling B 3.6.2.4 Suppression Pool Makeup (SPMU) System B 3.6-60 B 3.6.3.1 Deleted B 3.6.3.2 Primary Containment and Drywell Hydrogen B 3.6-72 Igniters B 3.6.3.3 Drywell Purge System B 3.6-78 B 3.6.4.1 Secondary Containment B 3.6-83 B 3.6.4.2 Secondary Containment Isolation Valves B 3.6-88 (SCIVs)

B 3.6.4.3 Standby Gas Treatment (SGT) System B 3.6-96 B 3.6.5.1 Drywell B 3.6-102 B 3.6.5.2 Drywell Air Lock B 3.6-106 B 3.6.5.3 Drywell Isolation Valves B 3.6-113 B 3.6.5.4 Drywell Pressure B 3.6-120 B 3.6.5.5 Drywell Air Temperature B 3.6-123 B 3.6.5.6 Drywell Vacuum Relief System B 3.6-126 B 3.7 PLANT SYSTEMS B 3.7-1 B 3.7.1 Standby Service Water (SSW) System and B 3.7-1 Ultimate Heat Sink (UHS)

B 3.7.2 High Pressure Core Spray (HPCS) Service B 3.7-8 Water System (SWS)

B Control Room Fresh Air (CRFA) System B 3.7-11 B Control Room Air Conditioning (AC) System B 3.7-17 B Main Condenser Offgas B 3.7-22 B Fuel Pool Water Level B 3.7-25

.J  !

B ELECTRICAL POWER SYSTEMS B 3.8-1 B 3.8.1 AC Sources - Operating B 3.8-1 B 3.8.2 AC Sources - Shutdown B 3.8-35 B 3.8.3 Diesel Fuel Oil, Lube Oil, and Starting B 3.8-42 Air B 3.8.4 DC Sources - Operating B 3.8-51 B 3.8.5 DC Sources - Shutdown B 3.8-60 GRAND GULF xi 12/05

Attachment 3 to GNRO-2014100048 Clean Copies of Technical Specification Pages Correcting the Typographical Errors

TABLE OF CONTENTS 3.6 CONTAINMENT SYSTEMS (continued) 3.6.4.2 Secondary Containment Isolation Valves 3.6-45 (SCIVs) 3.6.4.3 Standby Gas Treatment (SGT) System 3.6-49 3.6.5.1 Drywell 3.6-52 3.6.5.2 Drywell Air Lock 3.6-54 TR3.6.5.2 Drywell Air Lock Instrumentation 3.6-57-11 3.6.5.3 Drywell Isolation Valves 3.6-58 3.6.5.4 Drywell Pressure 3.6-62 3.6.5.5 Drywell Air Temperature 3.6-63 3.6.5.6 Drywell Vacuum Relief System 3.6-64 TR3.6.5.6 Drywell Vacuum Breaker and Associated 3.6-67-1 Isolation Valve Position Indication 3.7 PLANT SYSTEMS 3.7-1 3.7.1 Standby Service Water (SSW) System and 3.7-1 Ultimate Heat Sink (UHS)

TR3.7.1 Standby Service Water (SSW) System and 3.7-4-1 Ultimate Heat Sink (UHS) - Shutdown 3.7.2 High Pressure Core Spray (HPCS) Service 3.7-5 Water System (SWS)

TR3.7.2 High Pressure Core Spray (HPCS) Service 3.7-5-1 Water System (SWS) - Shutdown 3.7.3 Control Room Fresh Air (CRFA) System 3.7-6 3.7.4 Control Room Air Conditioning (AC) System 3.7-9 3.7.5 Main Condenser Offgas 3.7-12 3.7.6 Fuel Pool Water Level 3.7-14 TR3.7.6 Fuel Pool Water Level (non TS) 3.7-14-1 3.7.7 Main Turbine Bypass System 3.7-15 3.8 ELECTRICAL POWER SYSTEMS 3.8-1 3.8.1 AC Sources - Operating 3.8-1 3.8.2 AC Sources - Shutdown 3.8-18 3.8.3 Diesel Fuel Oil, Lube Oil, and Starting 3.8-22 Air 3.8.4 DC Sources - Operating 3.8-26 3.8.5 DC Sources - Shutdown 3.8-31 3.8.6 Battery Cell Parameters 3.8-34 3.8.7 Distribution Systems - Operating 3.8-38 3.8.8 Distribution Systems - Shutdown 3.8-40 3.9 REFUELING OPERATIONS 3.9-1 3.9.1 Refueling Equipment Interlocks 3.9-1 3.9.2 Refuel Position One-Rod-Out Interlock 3.9-2 3.9.3 Control Rod Position 3.9-4 3.9.4 Control Rod Position Indication 3.9-5 3.9.5 Control Rod OPERABILITY - Refueling 3.9-7 GRAND GULF iv 12/05

TABLE OF CONTENTS B 3.6 CONTAINMENT SYSTEMS (continued)

B 3.6.1.4 Primary Containment Pressure B 3.6-26 B 3.6.1.5 Primary Containment Air Temperature B 3.6-29 B 3.6.1.6 Low-Low Set (LLS) Valves B 3.6-32 B 3.6.1.7 Residual Heat Removal (RHR) Containment B 3.6-36 Spray System B 3.6.1.8 Feedwater Leakage Control System (FWLCS) B 3.6-41 B 3.6.1.9 Main Steam Isolation Valve (MSIV) Leakage B 3.6-44 Control System (LCS)

B 3.6.2.1 Suppression Pool Average Temperature B 3.6-48 B 3.6.2.2 Suppression Pool Water Level B 3.6-53 B 3.6.2.3 Residual Heat Removal (RHR) Suppression B 3.6-56 pool Cooling B 3.6.2.4 Suppression Pool Makeup (SPMU) System B 3.6-60 B 3.6.3.1 Deleted B 3.6.3.2 Primary Containment and Drywell Hydrogen B 3.6-72 Igniters B 3.6.3.3 Drywell Purge System B 3.6-78 B 3.6.4.1 Secondary Containment B 3.6-83 B 3.6.4.2 Secondary Containment Isolation Valves B 3.6-88 (SCIVs)

B 3.6.4.3 Standby Gas Treatment (SGT) System B 3.6-96 B 3.6.5.1 Drywell B 3.6-102 B 3.6.5.2 Drywell Air Lock B 3.6-106 B 3.6.5.3 Drywell Isolation Valves B 3.6-113 B 3.6.5.4 Drywell Pressure B 3.6-120 B 3.6.5.5 Drywell Air Temperature B 3.6-123 B 3.6.5.6 Drywell Vacuum Relief System B 3.6-126 B 3.7 PLANT SYSTEMS B 3.7-1 B 3.7.1 Standby Service Water (SSW) System and B 3.7-1 Ultimate Heat Sink (UHS)

B 3.7.2 High Pressure Core Spray (HPCS) Service B 3.7-8 Water System (SWS)

B 3.7.3 Control Room Fresh Air (CRFA) System B 3.7-11 B 3.7.4 Control Room Air Conditioning (AC) System B 3.7-17 B 3.7.5 Main Condenser Offgas B 3.7-22 B 3.7.6 Fuel Pool Water Level B 3.7-25 B 3.7.7 Main Turbine Bypass System B 3.7-28 B 3.8 ELECTRICAL POWER SYSTEMS B 3.8-1 B 3.8.1 AC Sources - Operating B 3.8-1 B 3.8.2 AC Sources - Shutdown B 3.8-35 B 3.8.3 Diesel Fuel Oil, Lube Oil, and Starting B 3.8-42 Air B 3.8.4 DC Sources - Operating B 3.8-51 B 3.8.5 DC Sources - Shutdown B 3.8-60 GRAND GULF xii 12/05