Title | Part 21 Report - Defective Motor Operated Potentiometer |
Event Description | The following information is excerpted from an Engine Systems, Inc. (ESI) report received via fax:
Component: Motor operated potentiometer without pre-position feature P/Ns: 72-07900-100-ESI 2-04E-184-103-ESI 2-00G-009-002-ESI System: Emergency Diesel Generator Summary: Engine Systems Inc. (ESI) began a 10CFR21 evaluation on April 12, 2017 following correspondence with Duke Energy - Catawba Nuclear Plant of a potential issue with a motor operated potentiometer (MOP) supplied by ESI. During bench testing, Duke was unable to adjust the cams of the MOP to operate the pre-position feature (also referred to as return-to-center). Further investigation revealed that the MOP supplied to Duke did not contain the desired cam arrangement. The evaluation was concluded on June 8, 2017 and it was determined that this issue is a reportable defect as defined by 10CFR21. For installations that rely on the pre-position function to drive generator output voltage to a predetermined setpoint in an emergency event, an incorrect cam arrangement on the motor operated potentiometer could negatively affect the emergency diesel generator [EDG] set's output voltage. This may prevent the EDG from carrying its safety-related loads in an emergency event. Discussion: A motor operated potentiometer is commonly used in the voltage regulator system of emergency diesel generator sets to allow for local or remote adjustment of generator output voltage. The assembly supplied by ESI was a replacement for obsolete Portec/NEI part number 72-07900-100. ESI initiated a Supplier Deviation Notification [SDN] (Part Number Change) to replace the obsolete part with one that would serve as a functional replacement using the same mounting footprint. To accomplish this, a Basler brand MOP was selected. The "-ESI" suffix was added to designate a modification to the Basler MOP by replacing the standard 2W, open-wound potentiometer with a 3W, precision-wound potentiometer identical to the one used in the original Portec units. The SDN indicated that the replacement MOP would have the pre-position feature. Note that the SDN would later be revised to include replacements for Cooper-Bessemer part numbers 2-04E-184-103 and 2-00G-009-002 which represented the same Portec part number 72-07900-100. The Basler MOP selected by ESI for the assembly was model MOC2103. A review of Basler model MOC2103 indicates that it is not a return-to-center style device and instead contains a standard cam arrangement. Photos on the following page depict the differences between the two cam arrangement styles. ESI inadvertently selected the incorrect model for this application. Reviewing the qualification testing performed by ESI revealed that ESl's testing duplicated the original Portec test procedure (whereby one cam is set to close above setpoint and one cam is set to close below setpoint). However, the testing was shown to be inadequate to fully ensure the return-to-center functionality. Though the cams were properly set above and below setpoint, a further verification that the unit would return to center, even if sufficiently away from setpoint, was not performed. For installations that rely on the preposition function, it is possible that the MOPs supplied by ESI would not return the potentiometer to setpoint. Since the MOP is used to set output voltage of the emergency diesel generator, the consequences of this issue are that the EDG may not maintain voltage within its required range to support its safety-related loads. Root cause evaluation: ESI selected the incorrect MOP to be used for this assembly. The original MOP used was a Portec/NEI P/N 72-07900-100 which became obsolete in the 1990s. ESI offered a replacement assembly (using the "-ESI" suffix) that included a Basler brand MOP, modified by replacing the factory supplied potentiometer to replicate the original Portec design. The original Portec MOP had the return-to-center feature and Basler offers some models with return-to-center and some without. ESI inadvertently selected the model without return-to-center. As a secondary cause, ESl's functional testing did not adequately verify the MOPs ability to return to center. The test procedure has steps to set the cams and limit switches as would be performed for the return-to-center style; however, the testing did not ensure that the cams would return the potentiometer back to the center, regardless of starting position. [photos submitted with report with following captions:] Photo 1: Desired Return-to-Center Cam Arrangement Photo 2: As-Supplied Standard Cam Arrangement Photos 3&4: Return-to-Center Cam Profile & Arrangement Photo 5&6: Standard Cam Profile & Arrangement Evaluation of previous shipments: ESI has supplied the replacement MOP from 2009 to 2016 on five (5) separate safety-related orders. A review of each order Indicates that the incorrect MOP was selected for the assembly. Affected Customers: ESI has supplied motor operated potentiometers with the incorrect cam arrangement to the following customers. Part Number 72-07900-100-ESI; Customer Duke Energy - Catawba; Customer PO 196046; Qty 6; ESI Serial Numbers 3013905-1.1-1 thru 6; MOP Serial Numbers H01931980, H01995582, H01995584, H01995585, H01995586, H01995587; C-of-C Date 5/30/2015 Part Number 72-07900-100-ESI; Customer Dremel/CFE - Laguna Verde; Customer PO 14-011/700427979; Qty 1; ESI Serial Number 3011566-3.1-1; MOP Serial Number H01798043; C-of-C Date 2/13/2015 Part Number 2-04E-184-103-ESI; Customer APS - Palo Verde; Customer PO 500530279; Qty 3; ESI Serial Numbers 3005695-1.1-1 thru 3; MOP Serial Numbers: H00958610, H00961219, 333861; C-of-C Date 7/31/2009 Part Number 2-04E-184-103-ESI; Customer APS - Palo Verde; Customer PO 500555659; Qty 3; ESI Serial Numbers 3008341-1.1-1 thru 3; MOP Serial Numbers H01151813, H01161548, H01161550; C-of-C Date 212/2012 Part Number 2-00G-009-002-ESI; Customer South Texas Project; Customer PO 200410; Qty 2; ESI Serial Numbers 3015607-1.1-1 thru 2; MOP Serial Numbers H02027435, H02027436; C-of-C Date 8/19/2016 Total Quantity 15 Corrective Action: Customers that have installed the motor operated potentiometer must evaluate the impact on their specific system. It may be acceptable to continue to use the MOP if other provisions are in place to ensure the EDG voltage is within an acceptable range for safety-related operation. Credit may also be taken for site acceptance testing following installation of the MOP. If the MOP is deemed acceptable for the application, no further action is necessary. For those customers that have determined the MOP is unacceptable for their application and/or would simply rather ensure they have the correct MOP, it may be returned to ESI for warranty replacement. Once a warranty order and Return Goods Authorization (RGA) is issued, supply of safety-related replacement MOP(s) is expected to be complete within 90 days. To prevent recurrence of this issue, ESI is implementing a revision to the procurement process for this assembly to update the part number of the MOP utilized. In addition, the dedication inspection and testing activities are being revised to ensure testing properly validates the return-to-center feature. This action is currently underway and will be completed prior to any future shipments. If you have any questions, you may call: Tom Horner Quality Assurance Manager Tel: (252) 977-2720 ESI Report ID: 10CFR21-0117, Rev. 0, dated 06/09/17 |
Where | |
---|---|
Engine Systems, Inc Rocky Mount, North Carolina (NRC Region 1) | |
Organization: | Engine Systems, Inc |
Reporting | |
10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
Time - Person (Reporting Time:+37 h1.542 days <br />0.22 weeks <br />0.0507 months <br />) | |
Opened: | Tom Horner 17:00 Jun 9, 2017 |
NRC Officer: | Bethany Cecere |
Last Updated: | Jun 9, 2017 |
52798 - NRC Website | |
Engine Systems, Inc with 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
WEEKMONTHYEARENS 565382023-03-28T04:00:00028 March 2023 04:00:00
[Table view]10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Defect Identified in Emergency Diesel Generator Governor ENS 556052021-11-09T17:00:0009 November 2021 17:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - Hinge Pin Retainer Plug Defective on Diesel Check Valve ENS 555312021-08-20T16:00:00020 August 2021 16:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Pressure Regulator Valve Failure ENS 553472021-05-11T16:00:00011 May 2021 16:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Initial Report - Deviation Identified Loose Zinc Anodes Installed in Heat Exchangers for Diesel Generators ENS 544672020-01-08T05:00:0008 January 2020 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Inadequate Selenium Surge Suppressor Thread Modification ENS 543502019-09-06T04:00:0006 September 2019 04:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Emd Fuel Injectors Seized Plunger and Bushing ENS 542362019-08-22T04:00:00022 August 2019 04:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Cracked Spray Tip on Emd Fuel Injector ENS 537632018-11-30T05:00:00030 November 2018 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect En Revision Imported Date 12/24/2018 ENS 536002018-07-19T04:00:00019 July 2018 04:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Motor Operated Potentiometer Defect ENS 533022018-02-01T04:00:0001 February 2018 04:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Refurbished Pressure Regulator May Result in Emergency Diesel Generator Failure to Start ENS 527982017-06-08T04:00:0008 June 2017 04:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - Defective Motor Operated Potentiometer ENS 524662016-12-21T05:00:00021 December 2016 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Issues Identified with the Enterprise Diesel Engine Subcover ENS 524772016-11-12T05:00:00012 November 2016 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Seizure of Fuel Injector on Emergency Diesel Generator ENS 511292015-06-05T22:12:0005 June 2015 22:12:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 - Incorrect Part Number Relay Shipped to Brunswick Nuclear Plant ENS 489602013-04-19T04:00:00019 April 2013 04:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - Esi Refurbished Emergency Diesel Generator Cylinder Heads May Have Valve Keeper Seals Missing ENS 485642012-12-06T05:00:0006 December 2012 05:00:00 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Esi Refurbished Emergency Diesel Generator Cylinder Head with Foreign Material in Intake Port 2023-03-28T04:00:00 | |