Retraction of Emergency License Amendment Request 10-02, One Time Revision to Technical Specification 3.8.1, AC Sources - Operating.
ML100970061
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 03/24/2010
From: Becker J
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DCL-10-032
Download: ML100970061 (1)


Text

Pacific Gas and Electric CompanyMarch 24, 2010 PG&E Letter DCL-10-032 James R. Becker Site Vice President Diablo Canyon Power Plant Mail Code 104/5/601 P2 0. Box 56 Avila Beach, CA 93424 805.545.3462 Internal:

691.3462 Fax: 805.545.6445 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 10 CFR 50.90 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Retraction of Emergency License Amendment Request 10-02 One Time Revision to Technical Specification 3.8.1, "AC Sources -Operating" On March 11, 2010, PG&E submitted Emergency License Amendment Request 10-02, One Time Revision to Technical Specification 3.8.1, "AC Sources -Operating." The license amendment request (LAR) was submitted in anticipation of requiring more than the allowed 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to implement modifications associated with the discovery of a nonconservative technical specification (TS). At approximately 13:45, on March 12, 2010, following modifications, operators exited TS Action 3.8.1.Therefore, PG&E is no longer requesting an emergency license amendment and hereby retracts emergency LAR 10-02.This letter was submitted March 12, 2010, but incorrectly specified it contained an"enclosure", and is therefore being re-submitted.

PG&E makes no regulatory commitments (as defined by NEI 99-04) in this letter.This letter includes no revisions to existing regulatory commitments.

If you have any questions or require additional information, please contact Mr. Tom Baldwin at (805) 545-4720.Sincerely, James R. Becker LMP1/3386/N50304168 cc: Gary W. Butner, California Department of Public Health Elmo E. Collins, NRC Region IV Michael S. Peck, NRC, Senior Resident Inspector Alan B. Wang, NRC Project Manager, Office of NRR Diablo Distribution A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway -Comanche Peak -Diablo Canyon