MONTHYEARDCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System DCL-23-092, Material Status Report for the Period Ending August 31, 20232023-09-28028 September 2023 Material Status Report for the Period Ending August 31, 2023 DCL-23-077, License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-27027 September 2023 License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors DCL-23-083, Upcoming Meeting with Nuclear Security and Incident Response Staff2023-09-13013 September 2023 Upcoming Meeting with Nuclear Security and Incident Response Staff DCL-23-078, Nuclear Material Transaction Report for New Fuel2023-09-0606 September 2023 Nuclear Material Transaction Report for New Fuel DCL-23-070, Withdrawal of Request Regarding Senior Reactor Operator License Application2023-08-16016 August 2023 Withdrawal of Request Regarding Senior Reactor Operator License Application DCL-23-068, Nuclear Material Transaction Report for New Fuel2023-08-0909 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-066, Nuclear Material Transaction Report for New Fuel2023-08-0303 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-065, Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure2023-07-27027 July 2023 Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure DCL-23-064, Nuclear Material Transaction Report for New Fuel2023-07-26026 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-054, License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-07-13013 July 2023 License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-055, Nuclear Material Transaction Report for New Fuel2023-07-0606 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-042, Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 02023-05-24024 May 2023 Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 0 DCL-23-032, Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program2023-05-22022 May 2023 Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program DCL-23-041, 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 20222023-05-22022 May 2023 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 2022 DCL-23-038, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule2023-05-15015 May 2023 Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule DCL-23-034, 2022 Annual Nonradiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Nonradiological Environmental Operating Report DCL-23-036, 2022 Annual Radiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Radiological Environmental Operating Report DCL-23-025, 2022 Annual Radioactive Effluent Release Report2023-05-0101 May 2023 2022 Annual Radioactive Effluent Release Report DCL-2023-512, Submittal of Receiving Water Monitoring Program 2022 Annual Report2023-04-27027 April 2023 Submittal of Receiving Water Monitoring Program 2022 Annual Report DCL-23-035, Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application2023-04-24024 April 2023 Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application DCL-23-028, Technical Specification Bases, Revision 142023-04-24024 April 2023 Technical Specification Bases, Revision 14 DCL-2023-511, Report on Discharge Monitoring for the First Quarter of 20232023-04-20020 April 2023 Report on Discharge Monitoring for the First Quarter of 2023 DCL-23-031, Submittal of Annual Report of Occupational Radiation Exposure for 20222023-04-19019 April 2023 Submittal of Annual Report of Occupational Radiation Exposure for 2022 DCL-23-024, Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System2023-04-0404 April 2023 Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System DCL-23-022, 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant2023-03-29029 March 2023 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-23-021, Independent Spent Fuel Storage Installation, Emergency Plan Update2023-03-23023 March 2023 Independent Spent Fuel Storage Installation, Emergency Plan Update DCL-23-020, Responses to NRC Questions Regarding License Renewal Efforts2023-03-17017 March 2023 Responses to NRC Questions Regarding License Renewal Efforts DCL-23-009, Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage2023-02-22022 February 2023 Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage DCL-23-008, Request Regarding Senior Reactor Operator License Application2023-02-22022 February 2023 Request Regarding Senior Reactor Operator License Application DCL-2023-503, Annual Sea Turtle Report2023-01-26026 January 2023 Annual Sea Turtle Report DCL-2023-502, (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring2023-01-18018 January 2023 (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring DCL-22-091, Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage2022-12-20020 December 2022 Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage DCL-22-089, Core Operating Limits Report for Unit 2 Cycle 242022-12-20020 December 2022 Core Operating Limits Report for Unit 2 Cycle 24 DCL-22-085, Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application2022-10-31031 October 2022 Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 2024-01-29
[Table view] |
Text
E Pacific Gas and
.19 ElectrcCompany David H.Datley Diablo Canyon Power Plant Vice President and PO. Box 56 General Manager Avila Beach, CA 93424 805.545.4350 April 23, 2004 Fax: 805.545A234 PG&E Letter DCL-04-052 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Supplemental Information Regarding Response to NRC Bulletin 2002-02. "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs"
Dear Commissioners and Staff:
In PG&E Letter DCL-02-109, "30-Day Response to NRC Bulletins 2002-02, 'Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs,"'
PG&E stated that details would be provided to the NRC six months prior to Unit 2 refueling outage twelve (2R12) on the reactor head volumetric inspection scheduled for 2R1 2, including inspection scope, methods, qualification, and acceptance criteria.
Since responding to NRC Bulletin 2002-02, the NRC has issued Order EA-03-009, which has subsequently been superseded by the First Revised Order EA-03-009.
The First Revised Order provides details for acceptable scope and methods for nonvisual nondestructive examinations (NDE) of reactor pressure vessel head penetrations in Section IV.C.(5).(b.).((i), (ii), and (iii)). PG&E consented to the First Revised Order in PG&E Letter DCL-04-021, "Twenty-Day Response to First Revision of NRC Order Modifying Licenses (EA-03-009)." Therefore, the scope and methods for the nonvisual NDE of reactor pressure vessel head penetrations to be performed in 2R12 will be consistent with the scope and methods described in the First Revised Order.
The qualification requirements and acceptance criteria of the volumetric examinations will be consistent with industry practices developed from EPRI research on volumetric inspection of the reactor pressure vessel head penetrations.
The vendor contracted for these examinations has demonstrated detection and sizing capabilities on the Materials Reliability Program blind sample test set.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Catlaway
Document Control Desk PG&E Letter DCL-04-052 April 23, 2004 Page 2 If you have questions regarding this response, please contact Mr. Stan Ketelsen at (805) 545-4720.
Sincerely, David H. Oatley Vice President and General Manager - Diablo Canyon mjr/4557 cc: Edgar Bailey, DHS Bruce S. Mallett David L. ProuIx Girija S. Shukla Diablo Distribution A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
PG&E Letter DCL-04-052 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
) Docket No. 50-275 In the Matter of ) Facility Operating License PACIFIC GAS AND ELECTRIC COMPANY) No. DPR-80
)
Diablo Canyon Power Plant ) Docket No. 50-323 Units 1 and 2 ) Facility Operating License
) No. DPR-82 AFFIDAVIT David H. Oatley, being of lawful age, first being duly sworn upon oath says that he is Vice President and General Manager - Diablo Canyon of Pacific Gas and Electric Company; that he has executed this supplemental response to NRC Bulletin 2002-02 on behalf of said company with full power and authority to do so; that he is familiar with the content thereof; and that the facts stated therein are true and correct to the best of his knowledge, information, and belief.
David H. Oatley Vice President and General Manager - Diablo Canyon Subscribed and sworn to before me this 23rd day of April 2004.
____ ____ ___ AN DR EATHERLY Notary Pdb4c - California Notary Public > I Commkb~Jn# 1425568 County of San Luis Obispo SanLuesObispoqounty State of California IMy Comm. Expis Jii 1. 2007i
Text
E Pacific Gas and
.19 ElectrcCompany David H.Datley Diablo Canyon Power Plant Vice President and PO. Box 56 General Manager Avila Beach, CA 93424 805.545.4350 April 23, 2004 Fax: 805.545A234 PG&E Letter DCL-04-052 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Supplemental Information Regarding Response to NRC Bulletin 2002-02. "Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs"
Dear Commissioners and Staff:
In PG&E Letter DCL-02-109, "30-Day Response to NRC Bulletins 2002-02, 'Reactor Pressure Vessel Head and Vessel Head Penetration Nozzle Inspection Programs,"'
PG&E stated that details would be provided to the NRC six months prior to Unit 2 refueling outage twelve (2R12) on the reactor head volumetric inspection scheduled for 2R1 2, including inspection scope, methods, qualification, and acceptance criteria.
Since responding to NRC Bulletin 2002-02, the NRC has issued Order EA-03-009, which has subsequently been superseded by the First Revised Order EA-03-009.
The First Revised Order provides details for acceptable scope and methods for nonvisual nondestructive examinations (NDE) of reactor pressure vessel head penetrations in Section IV.C.(5).(b.).((i), (ii), and (iii)). PG&E consented to the First Revised Order in PG&E Letter DCL-04-021, "Twenty-Day Response to First Revision of NRC Order Modifying Licenses (EA-03-009)." Therefore, the scope and methods for the nonvisual NDE of reactor pressure vessel head penetrations to be performed in 2R12 will be consistent with the scope and methods described in the First Revised Order.
The qualification requirements and acceptance criteria of the volumetric examinations will be consistent with industry practices developed from EPRI research on volumetric inspection of the reactor pressure vessel head penetrations.
The vendor contracted for these examinations has demonstrated detection and sizing capabilities on the Materials Reliability Program blind sample test set.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Catlaway
Document Control Desk PG&E Letter DCL-04-052 April 23, 2004 Page 2 If you have questions regarding this response, please contact Mr. Stan Ketelsen at (805) 545-4720.
Sincerely, David H. Oatley Vice President and General Manager - Diablo Canyon mjr/4557 cc: Edgar Bailey, DHS Bruce S. Mallett David L. ProuIx Girija S. Shukla Diablo Distribution A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
PG&E Letter DCL-04-052 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION
) Docket No. 50-275 In the Matter of ) Facility Operating License PACIFIC GAS AND ELECTRIC COMPANY) No. DPR-80
)
Diablo Canyon Power Plant ) Docket No. 50-323 Units 1 and 2 ) Facility Operating License
) No. DPR-82 AFFIDAVIT David H. Oatley, being of lawful age, first being duly sworn upon oath says that he is Vice President and General Manager - Diablo Canyon of Pacific Gas and Electric Company; that he has executed this supplemental response to NRC Bulletin 2002-02 on behalf of said company with full power and authority to do so; that he is familiar with the content thereof; and that the facts stated therein are true and correct to the best of his knowledge, information, and belief.
David H. Oatley Vice President and General Manager - Diablo Canyon Subscribed and sworn to before me this 23rd day of April 2004.
____ ____ ___ AN DR EATHERLY Notary Pdb4c - California Notary Public > I Commkb~Jn# 1425568 County of San Luis Obispo SanLuesObispoqounty State of California IMy Comm. Expis Jii 1. 2007i