Response to USNRC Request for Additional Information - CPSES Security Plan (Contingency Plan Section) - Teleconference Clarification Responses
ML042450327
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 08/27/2004
From: Madden F
TXU Power
To: Chernoff M
NRC/NRR/DLPM/LPD2
References
CPSES-200402018, TAC MC2906, TAC MC2907, TXX-04159
Download: ML042450327 (3)


Text

. I At TXU Power TXU Power Mike Blevins Comanche Peak Steam Senior Vice President &

Electric Station Chief Nuclear Officer P. O. Box 1002 (E01) Ref: NRC RAI Glen Rose, TX 76043 Tel: 254 897 5209 TAC: MC2906 / MC2907 Fax: 254 897 6652 mike.blevins~txu.com CPSES-200402018 Log # TXX-04159 August 27, 2004 Ms. Margaret H. Chernoff, Project Manager Security Plan Review Team Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Room 8 GI5, Mail Stop 8 G9A 11555 Rockville Pike Rockville, Maryland 20852

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 RESPONSE TO USNRC REQUEST FOR ADDITIONAL INFORMATION - CPSES SECURITY PLAN (CONTINGENCY PLAN SECTION) - TELECONFERENCE CLARIFICATION RESPONSES

REFERENCES:

(1) USNRC Request for Additional Information (RAI),

Receipt Dated June 21, 2004; Security Plan Section 10 - 19 (2) USNRC Request for Additional Information (RAI),

Receipt Dated June 28, 2004; Security Plan Sections 1- 9 (3) USNRC Request for Additional Information (RAI),

Receipt Dated July 12, 2004, Security Plan Sections 4.0, 3.1, Critical Task Matrix - Table 1 (4) USNRC Request for Additional Information (RAI),

Receipt Dated July 26, 2004, Contingency Plan Attachment contains Safeguards Information.

Upon separation, this page is decontrolled A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway

  • Comanche Peak- Diablo Canyon
  • Palo Verde
  • Wolf Creek
  • - A);P("t<

TXX-04159 Page 2 of 3 Ms. Chernoff:

Via the references, the Nuclear Regulatory Commission (NRC) requested additional information for certain sections in the CPSES Security Plan. By this transmittal, TXU Generation Company LP (TXU Power) acknowledges the four referenced RAI letters. Previous correspondence from TXU Power has provided preliminary responses to referenced letters 1 through 4.

Based upon the tele-conference with you and NRC plan review personnel on August 25, 2004, TXU Power attained an understanding of specific information necessary for revision of our original responses to answer the RAI questions in referenced letter 4. This letter provides those follow-up responses as clarified in the tele-conference.

TXU Power's preliminary responses associated with the Contingency Plan portion of the Comanche Peak Security Plan (CSP) RAIs, are found in the attachment to this transmittal. This material is Safeguards Information.

Should you have any questions or require additional information, please contact Mr. Don Alps, Security Manager at 254-897-5432 or Mr. Greg Bell, Security Coordinator at 254-897-5290. This communication contains no new or revised commitments for CPSES, Units I and 2 Sincerely, TXU Generation Company LP By: TXU Generation Management Company LLC, Its General Partner Mike Blevins By: LIV 2QL

/Fred W. Madden Director, Regulatory Affairs Attachment contains Safeguards Infonnation.