MONTHYEARML24190A1452024-07-0808 July 2024 Public Meeting Slides for Arkansas Nuclear One 2023 Annual Assessment, Pope County Quorum Court ML24156A1162024-06-0404 June 2024 Correction - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations W3F1-2024-0018, Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 25 / Refuel 252024-05-0101 May 2024 Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 25 / Refuel 25 W3F1-2024-0014, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20242024-04-29029 April 2024 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2024 2CAN012401, U.S. Additional Protocol2024-01-17017 January 2024 U.S. Additional Protocol ML23107A0162023-03-31031 March 2023 6 to Updated Final Safety Analysis Report, Chapter 5, Tables ML23107A0322023-03-31031 March 2023 6 to Updated Final Safety Analysis Report, Chapter 4, Tables ML23107A0372023-03-31031 March 2023 6 to Updated Final Safety Analysis Report, Chapter 14, Tables ML23107A0512023-03-31031 March 2023 6 to Updated Final Safety Analysis Report, Chapter 6, Tables ML23107A0522023-03-31031 March 2023 6 to Updated Final Safety Analysis Report, Chapter 3, Tables ML23107A0552023-03-31031 March 2023 6 to Updated Final Safety Analysis Report, Chapter 2, Tables ML22259A1222022-09-0808 September 2022 ANO Service Water KM Version ML22224A2432022-08-19019 August 2022 Regulatory Conference Participant List July 29 2022 (No Numbers) (Enc 1) ML21354A7552021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 10 of 18 RBG-48137, Additional Information for the 2019 Annual Radioactive Effluent Release Report2021-11-12012 November 2021 Additional Information for the 2019 Annual Radioactive Effluent Release Report ML21125A3352021-04-14014 April 2021 5 to Updated Final Safety Analysis Report, Chapter 12, Figures ML21125A3362021-04-14014 April 2021 5 to Updated Final Safety Analysis Report, Chapter 15, Figures ML21125A3382021-04-14014 April 2021 5 to Updated Final Safety Analysis Report, Chapter 14, Tables IR 05000416/20200042021-02-0303 February 2021 Integrated Inspection Report 05000416/2020004 IR 05000382/20200122021-02-0202 February 2021 Design Basis Assurance Inspection (Teams) Inspection Report 05000382/2020012 ML19056A1942019-02-18018 February 2019 Attachment 3: Estimate of Initial Temperature Difference Between Cladding and Surrounding Air ML18354A4272018-12-20020 December 2018 Superseded by Table Received with Mail 15 ML18352A7532018-12-13013 December 2018 Notification of Changes to Comprehensive Recovery Plan ML18261A2142018-10-22022 October 2018 Response to Comments on the Draft Plant-Specific Supplement 58 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding River Bend Station, Unit 1 CNRO-2018-00011, Submittal of Joint Plant Access Shared Information Table2018-03-19019 March 2018 Submittal of Joint Plant Access Shared Information Table ML17226A0972017-07-28028 July 2017 Revision 25 to the Updated Safety Analysis Report, Chapter 1, Tables 1.3-1 Through 1.8-1 ML17150A2562017-06-0505 June 2017 Entergy Fleet - 2017 Onsite Insurance Submittal Review for Entergy Operations, Inc., and Entergy Nuclear Operations, Inc. (CAC No. TM3058) ML16287A4432016-10-18018 October 2016 Correction to Amendment No. 197, Request for Changing Certain TS SRs Frequency from 18 Months to 24 Months ML16112A1722016-04-25025 April 2016 Indian Point Nuclear Generating Unit Nos. 2 And 3 Interim Staff Response To Reevaluated Flood Hazards Submitted In Response To 10 CFR 50.54 (f) Information Request Flood-Causing Mechanism Reevaluation (CAC NOS. MF3313 and MF3314) ML16090A3272016-04-12012 April 2016 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR 50.54(f) Information Request - Flood-Causing Mechanism Reevaluation NL-16-035, Supplemental to Basis for Performance of the Mitigating Strategies Assessment with Flood Hazard Information & Report for Recommendations 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accid2016-04-0505 April 2016 Supplemental to Basis for Performance of the Mitigating Strategies Assessment with Flood Hazard Information & Report for Recommendations 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accid ML16056A1392016-03-11011 March 2016 Correction to the U.S. Nuclear Regulatory Commission Analysis of Licensees' Decommissioning Funding Status Reports PNP 2015-042, One-Year Status Notification in Response to Confirmatory Order, EA-14-0132015-06-19019 June 2015 One-Year Status Notification in Response to Confirmatory Order, EA-14-013 GNRO-2015/00031, Response to Request for Additional Information Regarding Fluence License Amendment Request2015-05-0808 May 2015 Response to Request for Additional Information Regarding Fluence License Amendment Request NL-15-019, Reply to Request for Additional Information 3.0.3-2 from Set 2014-01 for the Review of the License Renewal Application2015-03-10010 March 2015 Reply to Request for Additional Information 3.0.3-2 from Set 2014-01 for the Review of the License Renewal Application ML15016A0912015-01-16016 January 2015 U.S. Nuclear Regulatory Commission, Record of Review Dispositions to Palisades Nuclear Plant (Pnp) Fire PRA (Fpra) Facts and Observations (F&Os ML15016A0732015-01-16016 January 2015 U.S. Nuclear Regulatory Commission, Record of Review Dispositions to Palisades Nuclear Plant (Pnp) Internal Events PRA (Iepra) Facts and Observations (F&Os) 2CAN011502, Response to Request for Additional Information Concerning the Spring 2014 Steam Generator Inspections2015-01-12012 January 2015 Response to Request for Additional Information Concerning the Spring 2014 Steam Generator Inspections ML14307B7072014-12-10010 December 2014 Supplemental Information Related to Development of Seismic Risk Evaluations for Information Request Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-T GNRO-2014/00010, Draft Plant-Specific Supplement 50 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants2014-02-0505 February 2014 Draft Plant-Specific Supplement 50 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants RBG-47409, Supplemental Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Hazard Walkdowns Conducted to Verify Current Plant Compliance with the Current Licensing Basis for Seismic Requirements2013-11-21021 November 2013 Supplemental Information Pursuant to 10 CFR 50.54(f) Regarding the Seismic Hazard Walkdowns Conducted to Verify Current Plant Compliance with the Current Licensing Basis for Seismic Requirements ML13133A1382013-05-10010 May 2013 One, Unit 1, ANO1 Steam Generator Tube Inspection Discussion Points, Preventative Tube Plugging and Proximity Calls ML13133A1362013-05-10010 May 2013 One, Unit 1, ANO1 Steam Generator Tube Inspection Discussion Points, Preventative Tube to Plug and Proximity Calls GNRO-2012/00107, Vibration Data Report and Commitment Change2012-09-0606 September 2012 Vibration Data Report and Commitment Change ML12241A2962012-08-28028 August 2012 RAI for the Request to Use of Alternate ASME Code Case N-770-1 Baseline Examination, Request for Alternative ANO2-ISI-007 ML12157A2572012-05-23023 May 2012 Attachment 13 to GNRO-2012/00039 - Er Reference - Mdeq. 2010a. Mississippi Dept. of Environmental Quality, Office of Land and Water Resources, Water Well Drillers, Radial-Search, Wells. E-mail Correspondence from Tommie Whitten Mdeq. Septem ML12157A2562012-05-23023 May 2012 Attachment 32 to GNRO-2012/00039 - Er Reference - MDEQ 2009a, Records of Public-Supply Wells in Mississippi, 2009 ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 ML11362A4392012-01-19019 January 2012 Enclosure 3: for Scoping Ltrs Table of Listed Species for Fws Letter ML11221A3052011-08-0909 August 2011 Lr Hearing - NIA-078 2024-07-08
[Table view] Category:Letter type:CNRO
MONTHYEARCNRO-2022-00015, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling Using the Consolidated Line-Item Improvement Process2022-05-26026 May 2022 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling Using the Consolidated Line-Item Improvement Process CNRO-2021-00023, Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L2021-10-0606 October 2021 Entergy Operations, Inc. - Supplement to CNRO-2021-00002, Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L CNRO-2021-00002, Entergy Operations, Inc. - Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L2021-01-28028 January 2021 Entergy Operations, Inc. - Basis for Concluding the Terms of Confirmatory Order EA-17-132/EA-17-153 Are Complete, Element L CNRO-2020-00023, Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K 2020 Summary2020-12-17017 December 2020 Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K 2020 Summary CNRO-2020-00021, Response to Request for Additional Information Regarding Relief Requests GG-ISI-020 and RBS-ISI-0192020-11-0909 November 2020 Response to Request for Additional Information Regarding Relief Requests GG-ISI-020 and RBS-ISI-019 CNRO-2020-00016, Entergy Nuclear Operations, Inc - Relief Request EN-RR-20-002: Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv)2020-08-12012 August 2020 Entergy Nuclear Operations, Inc - Relief Request EN-RR-20-002: Proposed Use of Subsequent ASME Code Edition and Addenda in Accordance with 10 CFR 50.55a(g)(4)(iv) CNRO-2020-00015, Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019)2020-06-0808 June 2020 Request to Update ASME Code Relief Request Safety Evaluations with NRC-Approved Revision of BWRVIP Guidelines (GG-ISI-020, and RBS-ISI-019) CNRO-2020-00009, Application to Revise Technical Specifications to Adopt TSTF-501 Relocate Stored Fuel Oil and Lube Oil Volumes to Licensee Control, Revision 12020-02-26026 February 2020 Application to Revise Technical Specifications to Adopt TSTF-501 Relocate Stored Fuel Oil and Lube Oil Volumes to Licensee Control, Revision 1 CNRO-2020-00006, Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO, Revision 22020-01-24024 January 2020 Application to Revise Technical Specifications to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO, Revision 2 CNRO-2020-00008, Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR-Shutdown Cooling Subsystems Using the Consolidated Line Item Improvement Process2020-01-24024 January 2020 Application to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR-Shutdown Cooling Subsystems Using the Consolidated Line Item Improvement Process CNRO-2019-00030, Response to Confirmatory Order EA-17-132/EA-17-153, Element K 2019 Summary2019-12-30030 December 2019 Response to Confirmatory Order EA-17-132/EA-17-153, Element K 2019 Summary CNRO-2019-00007, Grand Gulf Nuclear Station; and Waterford 3 Steam Electric Station - Decommissioning Funding Status Report2019-03-28028 March 2019 Grand Gulf Nuclear Station; and Waterford 3 Steam Electric Station - Decommissioning Funding Status Report CNRO-2019-00006, Stations - Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2018 - 10 CFR 50.82(a)(8)(vii) - Entergy Nuclear Operations, Inc2019-03-28028 March 2019 Stations - Status of Funding for Managing Irradiated Fuel for Year Ending December 31, 2018 - 10 CFR 50.82(a)(8)(vii) - Entergy Nuclear Operations, Inc CNRO-2019-00010, Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3))2019-03-28028 March 2019 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) CNRO-2019-00005, Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc2019-03-28028 March 2019 Stations - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) - Entergy Nuclear Operations, Inc CNRO-2019-00013, Entergy Response to Confirmatory Order EA-17-132/EA-17-1532019-03-21021 March 2019 Entergy Response to Confirmatory Order EA-17-132/EA-17-153 CNRO-2019-00009, Stations - Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR, Revision 22019-03-0707 March 2019 Stations - Application to Revise Technical Specifications to Adopt TSTF-564, Safety Limit MCPR, Revision 2 CNRO-2019-00003, Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 42019-01-31031 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 4 CNRO-2019-00002, Relief Request Number EN-19-RR-1, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 12019-01-31031 January 2019 Relief Request Number EN-19-RR-1, Proposed Alternative to Use ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 1 CNRO-2018-00051, Grand Gulf Nuclear Station, Palisades Nuclear Plant, River Bend Station, Pilgrim Nuclear Station and Waterford 3 - Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K2018-12-28028 December 2018 Grand Gulf Nuclear Station, Palisades Nuclear Plant, River Bend Station, Pilgrim Nuclear Station and Waterford 3 - Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element K CNRO-2018-00047, Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving Conforming License Amendment; and Request for Exemption from 10 CFR 50.82(a)(8)(i)(A)2018-11-16016 November 2018 Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving Conforming License Amendment; and Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) CNRO-2018-00039, Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element J2018-09-27027 September 2018 Entergy Response to Confirmatory Order EA-17-132/EA-17-153, Element J CNRO-2018-00031, Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E2018-07-0303 July 2018 Request for Exemptions from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E CNRO-2018-00023, Request to Revise Quality Assurance Program Approval for Radioactive Material Packages No. 02402018-06-18018 June 2018 Request to Revise Quality Assurance Program Approval for Radioactive Material Packages No. 0240 CNRO-2018-00021, Response to Request for Supplemental Information Regarding Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in the Spent Fuel Pools for Indian Point Energy Center, Unit 3 and Waterford 3 Steam Electric Station2018-05-30030 May 2018 Response to Request for Supplemental Information Regarding Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in the Spent Fuel Pools for Indian Point Energy Center, Unit 3 and Waterford 3 Steam Electric Station CNRO-2018-00018, Anchor Darling Double Disc Gate Valve Information and Status2018-04-16016 April 2018 Anchor Darling Double Disc Gate Valve Information and Status CNRO-2018-00012, Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2018-03-29029 March 2018 Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) CNRO-2018-00011, Submittal of Joint Plant Access Shared Information Table2018-03-19019 March 2018 Submittal of Joint Plant Access Shared Information Table CNRO-2017-00022, Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 12017-11-17017 November 2017 Relief Request Number EN-17-RR-1 - Proposed Alternative to Use ASME Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate-Energy Class 2 or 3 Piping, Section XI, Division 1 CNRO-2017-00012, Request to Remove James A. FitzPatrick Nuclear Power Plant from Quality Assurance Program Approval for Radioactive Material Packages No. 02402017-06-14014 June 2017 Request to Remove James A. FitzPatrick Nuclear Power Plant from Quality Assurance Program Approval for Radioactive Material Packages No. 0240 CNRO-2017-00009, Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2017-03-31031 March 2017 Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) CNRO-2017-00010, Entergy Operations, Inc. - Decommissioning Funding Status Report2017-03-31031 March 2017 Entergy Operations, Inc. - Decommissioning Funding Status Report CNRO-2017-00007, Nuclear Property Damage Insurance (10 CFR 50.54(w)(3))2017-03-30030 March 2017 Nuclear Property Damage Insurance (10 CFR 50.54(w)(3)) CNRO-2017-00005, and Isfsl - License Amendment Request for Administrative Change to Licensee Name2017-03-29029 March 2017 and Isfsl - License Amendment Request for Administrative Change to Licensee Name CNRO-2017-00004, Notice Regarding Third Proposed Amendment to Master Trust and Planned Distribution of Assets from FitzPatrick Unit Fund to Trust Established2017-01-20020 January 2017 Notice Regarding Third Proposed Amendment to Master Trust and Planned Distribution of Assets from FitzPatrick Unit Fund to Trust Established CNRO-2016-00023, Request EN-ISI-16-1: Use of Later Edition/Addenda of Amse Section XI Code for ISI Related Activities2016-12-0101 December 2016 Request EN-ISI-16-1: Use of Later Edition/Addenda of Amse Section XI Code for ISI Related Activities CNRO-2016-00020, Application for Order to Transfer Master Decommissioning Trust from PASNY to ENO, Consenting to Amendments to Trust Agreement, and Approving Proposed License Amendments to Modify and Delete Decommissioning .2016-08-16016 August 2016 Application for Order to Transfer Master Decommissioning Trust from PASNY to ENO, Consenting to Amendments to Trust Agreement, and Approving Proposed License Amendments to Modify and Delete Decommissioning . CNRO-2016-00017, Entergy Nuclear Operations - Request for Approval of Change to the Quality Assurance Program Manual2016-07-19019 July 2016 Entergy Nuclear Operations - Request for Approval of Change to the Quality Assurance Program Manual CNRO-2016-00016, Entergy - Response to RAI Questions and Submittal of Relief Request EN-ISI-15-1 (Updated)2016-06-0202 June 2016 Entergy - Response to RAI Questions and Submittal of Relief Request EN-ISI-15-1 (Updated) CNRO-2016-00008, Entergy - Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3))2016-03-30030 March 2016 Entergy - Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) CNRO-2016-00010, Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v)2016-03-30030 March 2016 Entergy Nuclear Operations, Inc. - Decommissioning Funding Status Report, Per 10 CFR 50.75(f)(1) and 10 CFR 50.82(a)(8)(v) CNRO-2016-00009, Unit 3 - Supplement to Notice of Change in Corporate Form of Entergy Nuclear New York Investment Company I and Creditor Agreement2016-03-21021 March 2016 Unit 3 - Supplement to Notice of Change in Corporate Form of Entergy Nuclear New York Investment Company I and Creditor Agreement CNRO-2016-00005, Response to Request for Additional Information Pertaining to a Change to the Entergy Quality Assurance Program Manual (QAPM)2016-02-25025 February 2016 Response to Request for Additional Information Pertaining to a Change to the Entergy Quality Assurance Program Manual (QAPM) CNRO-2016-00006, Notice of Change in Corporate Form of Entergy Nuclear New York Investment Company I and Creditor Agreement2016-02-25025 February 2016 Notice of Change in Corporate Form of Entergy Nuclear New York Investment Company I and Creditor Agreement CNRO-2016-00004, Notice Regarding Acquisition of Title to Leased Interest2016-02-10010 February 2016 Notice Regarding Acquisition of Title to Leased Interest CNRO-2016-00002, Entergy - Relief Request Number RR EN-15-1, Rev. 1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Water Service, Secti2016-01-29029 January 2016 Entergy - Relief Request Number RR EN-15-1, Rev. 1 - Proposed Alternative to Use ASME Code Case N-789-1, Alternative Requirements for Pad Reinforcement of Class 2 and 3 Moderate Energy Carbon Steel Piping for Raw Water Service, Section Xl, CNRO-2015-00002, Entergy Operations, Inc. - Response to RAI Questions and Submittal of RR EN-15-2, Rev. 12015-12-0404 December 2015 Entergy Operations, Inc. - Response to RAI Questions and Submittal of RR EN-15-2, Rev. 1 CNRO-2015-00022, Entergy - Relief Request EN-ISI-15-1: Proposed Alternative to Maintain ISI-Related Activities to the 2001 Edition/2003 Addendum of ASME Section Xl Code2015-11-20020 November 2015 Entergy - Relief Request EN-ISI-15-1: Proposed Alternative to Maintain ISI-Related Activities to the 2001 Edition/2003 Addendum of ASME Section Xl Code CNRO-2015-00023, Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM)2015-11-0606 November 2015 Request for Approval of Change to the Entergy Quality Assurance Program Manual (QAPM) CNRO-2015-00021, Confirmatory Order - Action H2015-11-0303 November 2015 Confirmatory Order - Action H 2022-05-26
[Table view] |
Text
Entergy Nuclear Operations, Inc.
Entergy Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 601-368-5000 Phil Couture Manager, Fleet Licensing Programs CNRO-2018-00011 March 19, 2018 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
SUBJECT:
NextEra Energy-Entergy Joint Plant Access Shared Information Table Arkansas Nuclear One Units 1 & 2 Pilgrim Nuclear Power Station Docket Nos. 50-313 & 50-368 Docket No. 50-293 Grand Gulf Nuclear Station River Bend Station Docket No. 50-416 Docket No. 50-458 Indian Point Nuclear Generating Units 2 & 3 Waterford 3 Steam Electric Station Docket Nos. 50-247 & 50-286 Docket No. 50-382 Palisades Nuclear Power Plant Docket No. 50-255
REFERENCE:
NextEra Energy letter L-2018-067, dated March 19, 2018
Dear Sir or Madam:
Entergy Operations, Inc. and Entergy Nuclear Operations, Inc. (collectively referred to as Entergy) hereby submits the enclosed information table which describes our compliance with all elements of licensee shared information as described in 10 CFR 73.56, 10 CFR 26, and NEI-03-01 (Nuclear Power Plant Access Authorization Program). This table shows how the Energy operating fleet is implementing the provisions of NEI 03-01 without having access to the industry system.
This letter contains no new regulatory commitments.
If you have any questions or require additional information, please contact me at (601) 368-5102.
Sincerely, PC
Enclosure:
NextEra/Entergy Alternative Process with no Personnel Access Database System (PADS) Access (5 pages)
CNRO-2018-00011 / Page 2 of 2 cc: USNRC Director, Office of Nuclear Security and Incident Response USNRC Regional Administrator, Region I USNRC Regional Administrator, Region III USNRC Regional Administrator, Region IV USNRC Project Manager, ANO 1/2 USNRC Project Manager, Grand Gulf USNRC Project Manager, Indian Point 2/3 USNRC Project Manager, Palisades USNRC Project Manager, Pilgrim USNRC Project Manager, River Bend USNRC Project Manager, Waterford 3 Ms. Margaret OBanion, Project Manager, NRC/NRR/DORL Mr. Jason J. Drake, Project Manager, NRR USNRC Senior Resident Inspector, ANO 1/2 USNRC Senior Resident Inspector, Grand Gulf USNRC Senior Resident Inspector, Indian Point 2/3 USNRC Senior Resident Inspector, Palisades USNRC Senior Resident Inspector, Pilgrim USNRC Senior Resident Inspector, River Bend USNRC Senior Resident Inspector, Waterford 3 Mr. A. Bakken III (ECH)
Mr. J. Ventosa (ECH)
Mr. C. Costanzo (ECH)
Mr. L. Coyle (ECH)
Mr. R. Anderson (ANO)
Mr. E. Larson (GGNS)
Mr. A. Vitale (IPEC)
Mr. C. Arnone (PAL)
Mr. B. Sullivan (PNPS)
Mr. W. Maguire (RBS)
Mr. J. Dinelli (WF3)
Mr. O. Limpias (ECH)
Mr. K. Jury (ECH)
Mr. R. Gaston (ECH)
Ms. M. Halter (ECH)
NextEra/Entergy Alternative Process with no Personnel Access Database System (PADS) Access
Background
10 CFR 73.56(h)(6) discusses information sharing and provides that licensees, applicants, and contractors or vendors may rely upon such shared information.
NEI 03-01, Nuclear Power Plant Access Authorization Program, Section 12 provides guidance on how the sharing of information is conducted via the information-sharing mechanism also known as the Personnel Access Data System (PADS) and, if the information-sharing mechanism is unavailable, the manual process available to licensees to ensure information is shared.
NextEra1 and Entergy2 are no longer members of the Nuclear Energy Institute and therefore, as of February 4th, 2018, both fleets are now utilizing manual processes in lieu of PADS to ensure all elements of licensee shared information as described in 10 CFR 73.56, 10 CFR 26, and NEI 03-01 are being maintained. The following table shows how both fleets are implementing the provisions of NEI 03-01 without having access to the PADS system.
NEI 03-01 Information Mitigation 12(a) The NRC requires that key access authorization and NextEra and Entergy provide a daily spreadsheet to fitness-for-duty program information be accessible by other industry counterparts via an e-mail identifying if an power reactor licensee. However, this requirement extends individual is still currently badged or has been terminated, to other entities committed to 10 CFR 73.56, 10 CFR 26, along with a favorable or unfavorable flag. The receiving and NEI 03-01 who agree to participate in the industry licensees are responsible for checking the spreadsheet information-sharing program. The section defines the and requesting further information or a transfer of an minimum elements that must be made available by individuals record.
licensees or other entities to me requirements. The industry database may require additional information to facilitate data management and audit requirements.
12(c) If the shared information used for determining an On a daily basis, NextEra and Entergy transfer the name individuals trustworthiness and reliability changes or new or of those individuals who have been placed in a denial additional information is developed about the individual, the status or have a change in status in the follow-up drug licensees or Contractor/Vendors (C/Vs) that acquire this testing program to NEI PADS Central. PADS Central then 1
In this paper, NextEra refers to Florida Power & Light Company, NextEra Energy Seabrook, LLC, NextEra Energy Duane Arnold, LLC, and NextEra Energy Point Beach, LLC.
2 In this paper, Entergy or Entergy Nuclear, refers to both Entergy Operations, Inc., the licensed operator for the Arkansas Nuclear One Units 1 & 2, Grand Gulf Nuclear Station, River Bend Station, and Waterford 3 Steam Electric Station, and to Entergy Nuclear Operations, Inc., the licensed operator for Indian Point Nuclear Generating Units 2 & 3, Palisades Nuclear Power Plant and Pilgrim Nuclear Power Station.
1
information shall correct or augment the data contained in adds those individuals to the PADS database and the information sharing mechanism. provides NextEra and Entergy with a new daily list of those individuals currently denied or in a follow-up program.
12(d) If the changed, additional or developed information has In addition to the data provided to PADS Central for the implications for adversely affecting and individuals daily update or the industry e-mailed spreadsheet, trustworthiness and reliability, the licensee or C/V who separate forms were developed for Potentially discovered or obtained the new, additional or changed Disqualifying Information (PDI) and 10 CFR Part 26 information, shall on the day of discovery, inform the Follow-up program requirements for providing the industry reviewing official of any licensee access authorization information of any change where a licensee could request program under which the individual is maintaining his or her a transfer of information.
UAA/UA status of the updated information.
As some licensees make changes to individuals that may affect their access, those licensees are providing the individuals name to us as notice. Our internal systems are checked to determine whether the individual is or has ever been badged at any of the NextEra or Entergy fleet sites.
If currently badged, a transfer of information is requested from the licensee that provided the information in order to obtain the relevant details to make an access determination. If never badged, the licensee supplying the information is informed of such. Other licensees are providing their derogatory information to both NextEra and Entergy to ensure compliance since there is no awareness if the individual is currently badged or not at our sites. Our response is a courtesy. If the individual was badged at some point but is not currently badged, our internal system is annotated with the appropriate flag for resolution upon their return to any fleet site.
12(f) If the information-sharing mechanism is unavailable and a Because NextEra and Entergy no longer have access to notification of change or updated information is required, PADS, this provision is critical to NextEras and Entergys licensees and C/Vs shall take manual actions to ensure that regulatory compliance. Transfer of information forms were the information is shared and update the data in the developed by NextEra and Entergy independently of NEI information-sharing mechanism as soon as reasonably forms and automated for fast turnaround on a licensee possible. request. Similarly, when NextEra or Entergy requires information from another licensee, a transfer request is 2
provided to a receiving licensee for their cooperation and response. If this information is not returned, Entergy and/or NextEra take alternate measures, such as; conducting a new initial investigation; going back to the last known licensee where information can be validated; and re-fingerprinting those individuals. The denial list and the follow-up lists are checked prior to the certifying of Unescorted Access Authorization (UAA) or the granting of Unescorted Access (UA) 12(g) Records maintained in the database must be available for Records associated with this process are available for NRC review. review by the NRC.
12.1(c) c. The most recent data that provides the basis for the Key UAA/UA elements are made available to the industry current authorization needs to be provided. The information via the daily spreadsheet identified in 12(a) above. Upon a to be shared includes: licensees identification of an individual on the
- 1. date current UAA/UA granted; spreadsheet where they would require a transfer of
- 2. employer; information, this information would be provided upon their
- 3. date psychological evaluation completed; request.
- 4. date CHRI received (the date the CHRI is reviewed and approved);
- 5. date of FFD chemical sample collected and reason for test;
- 6. date BI and suitable inquiry completed;
- 7. licensee providing the information;
- 8. company holding the supporting records, if not the licensee;
- 9. whether additional information is held by the licensee;
- 10. follow-up information; begin date, estimated end date frequency of testing, and number of tests required; and
- 11. whether the individual is participating in a treatment plan.
12.1(d) d. For individuals granted UAA/UA after July 7, 2003 , the Key UAA/UA elements are made available to the industry information to be shared includes: via the daily spreadsheet identified in 12(a) above. Upon a
- 1. date UA granted; licensees identification of an individual on the
- 2. employer; spreadsheet where they would require a transfer of
- 3. citizenship; information, this information would be provided upon their
- 4. date psychological evaluation completed; request.
3
- 5. date CHRI received, (the date the CHRI is reviewed and approved);
- 6. date of FFD chemical sample collected and reason for test;
- 7. date of completion of Plant Access Training and BOP training and other training as defined in NEI 03-04;
- 8. date UAA completed;
- 9. licensee providing the information;
- 10. company holding the supporting records, if not the licensee;
- 11. whether additional information is held by the licensee; and
- 12. follow-up information; begin date, estimated end date frequency of testing, and number of tests required.
12.1(f)&(g) f. Licensees shall ensure the demographic information of Upon a licensees identification of an individual on the any person formally applying for UAA/UA to a licensee spreadsheet where they would require a transfer of facility, is added to or updated in the method. information, this information would be provided to the
- g. Demographic data for individuals granted UA after July 7, requesting licensee upon their request.
2003 includes:
- 1. current address;
- 2. height;
- 3. weight;
- 4. eye color;
- 5. hair color;
- 6. gender; and
- 7. Place of birth (city, US state or province, and country if not US).
12.4(a) Licensees shall ensure those persons denied UA since See 12(a) above January 1, 1997, are identifiable by other licensees through the established methods.
12.5(a) Licensees shall include the follow-up information regarding See 12(c) above all persons in a UAA/UA status, including the date the follow-up commenced and the date the follow-up is expected to end.
12.6(c) UAA/UA Denial Review Process On a daily basis, NextEra and Entergy transfer to NEI (c) If the review finds in favor of the individual, the licensee PADS Central the names of those individuals who had 4
shall update the relevant records to reflect the outcome of been placed in a denial status and subsequently have had the review and delete or correct all information the review their denial overturned through the UAA/UA Denial found to be inaccurate. Review Process.
12.7(a) Except for emergency conditions e.g., ambulance, fire, law See 12(c) above. In addition, the spreadsheet from PADS enforcement response, etc., and NRC employees all Central is uploaded to a security file share where it is visitors will be checked against the industry database to accessed by those performing visitor checks prior to an ensure that they are not currently denied access. The check individuals entry in to the PA.
for each visitor will be performed at least once daily (00:01-2400 hours) prior to the workers first daily entry into the protected area.
5