Tennessee Valley Authority - Radiological Emergency Plan Appendix Revision
ML22012A436
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 01/12/2022
From: Polickoski J
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
CNL-22-006
Download: ML22012A436 (2)


Text

1101 Market Street, Chattanooga, Tennessee 37402

CNL-22-006

January 12, 2022

10 CFR 50.54(q) 10 CFR 72.44(f)

ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001

Sequoyah Nuclear Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327, 50-328, and 72-034

Subject:

TENNESSEE VALLEY AUTHORITY - RADIOLOGICAL EMERGENCY PLAN APPENDIX REVISION

In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.54(q) and 10 CFR 72.44(f), Tennessee Valley Authority (TVA) is submitting a description of changes to the TVA Radiological Emergency Plan (REP). The affected document is the REP appendix listed below.

Document Revision Title Effective Date

REP-Appendix B 109 Sequoyah Nuclear Plant 12/16/2021 Radiological Emergency Plan

Description of Changes and Summary of Analysis

REP-Appendix B

TVA revised this REP as follows:

Section 3.0, Responsibility Replaced the title Unit Supervisor with current title Nuclear Unit Senior Operator (NUSO).

Section 5.0, Site Emergency Organization Moved the location of the table title, Typical Transition of Command and Control Functions, to above the table.

U.S. Nuclear Regulatory Commission CNL-22-006 Page 2 January 12, 2022

Figure B-1, OSC Emergency Organization (Including Minimum Staffing and Augmentation)

Added radiological protection technician and support at 60-minute and 90-minute response times to the Operations Suppor t Center emergency organization. The change clarifies the figure by being consistent with staffing in Figure B-2.

Figure B-2, Minimum Onshift and Augmentation Response Personnel Changed the title of Figure B-2 to reflect that the figure includes augmentation personnel. Replaced the title Unit Supervisor with current title NUSO. Added (CECC) next to Central Emergency Control Center Director title to be consistent with other positions in the table.

The above changes were evaluated in accordance with 10 CFR 50.54(q)(3) and 10 CFR 72.44(f). TVA determined that the changes did not reduce the effectiveness of the TVA REP. The TVA REP, as revised, continues to meet the requirements in Appendix E to 10 CFR 50 and the planning standards of 10 CFR 50.47(b).

There are no new regulatory commitments contained in this letter. If you have any questions regarding this submittal, please contact Kimberly D. Hulvey, Senior Manager, Fleet Licensing, at 423-751-3275.

Respectfully,

James T. Polickoski Director, Nuclear Regulatory Affairs

cc:

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant NRC Project Manager - Sequoyah Nuclear Plant NRC Director - Division of Spent Fuel Management, NMSS