MONTHYEARBYRON 2023-0065, Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline2023-11-17017 November 2023 Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline BYRON 2023-0063, Day Inservice Inspection Report for Interval 4, Period 3, (B2R24)2023-11-16016 November 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B2R24) BYRON 2023-0029, Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements2023-06-0101 June 2023 Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements BYRON 2023-0022, 2022 Annual Radiological Environmental Operating Report (AREOR)2023-05-0404 May 2023 2022 Annual Radiological Environmental Operating Report (AREOR) BYRON 2023-0002, Unit 2, Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements2023-04-0606 April 2023 Unit 2, Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements BYRON 2023-0012, Cycle 26 Core Operating Limits Report2023-03-16016 March 2023 Cycle 26 Core Operating Limits Report BYRON 2022-0081, CFR72.48 Evaluation Summary Report2022-12-0909 December 2022 CFR72.48 Evaluation Summary Report BYRON 2022-0072, Steam Generator Tube Inspection Report for Refueling Outage 232022-10-27027 October 2022 Steam Generator Tube Inspection Report for Refueling Outage 23 BYRON 2022-0069, 2021 Regulatory Commitment Change Summary Report2022-10-13013 October 2022 2021 Regulatory Commitment Change Summary Report BYRON 2022-0071, Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment2022-10-13013 October 2022 Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment BYRON 2022-0065, Registration of Use of Cask to Store Spent Fuel2022-10-13013 October 2022 Registration of Use of Cask to Store Spent Fuel BYRON 2022-0063, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report for September 9, 2021 to September 8, 20222022-09-29029 September 2022 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report for September 9, 2021 to September 8, 2022 BYRON 2022-0064, Letter 2022-0064 Submittal of Byron Integrated Initial License Training Examination Materials(Signed)2022-09-28028 September 2022 Letter 2022-0064 Submittal of Byron Integrated Initial License Training Examination Materials(Signed) BYRON 2022-0059, Registration of Use of Cask to Store Spent Fuel2022-09-15015 September 2022 Registration of Use of Cask to Store Spent Fuel BYRON 2022-0045, Day Inservice Inspection Report for Interval 4, Period 2, (B2R23)2022-07-15015 July 2022 Day Inservice Inspection Report for Interval 4, Period 2, (B2R23) BYRON 2022-0026, Annual Radiological Environmental Operating Report2022-05-0505 May 2022 Annual Radiological Environmental Operating Report BYRON 2022-0030, Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Report2022-05-0303 May 2022 Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Report BYRON 2022-0028, Cycle 24 Core Operating Limits Report2022-04-28028 April 2022 Cycle 24 Core Operating Limits Report BYRON 2022-0016, Annual Dose Report for 20212022-04-0707 April 2022 Annual Dose Report for 2021 BYRON 2021-0072, Post Exam Submittal Letter2021-10-28028 October 2021 Post Exam Submittal Letter BYRON 2021-0033, Submittal on Initial Operator Licensing Examination Outline2021-10-28028 October 2021 Submittal on Initial Operator Licensing Examination Outline BYRON 2021-0063, Reactor Coolant System Pressure and Temperature Limits Report2021-09-28028 September 2021 Reactor Coolant System Pressure and Temperature Limits Report BYRON 2021-0064, Cycle 25 Core Operating Limits Report2021-09-28028 September 2021 Cycle 25 Core Operating Limits Report BYRON 2021-0032, 2020 Annual Radiological Environmental Operating Report (AREOR)2021-05-0606 May 2021 2020 Annual Radiological Environmental Operating Report (AREOR) BYRON 2021-0031, 2020 Annual Radioactive Effluent Release Report2021-04-21021 April 2021 2020 Annual Radioactive Effluent Release Report BYRON 2021-0027, Annual Dose Report for 20202021-03-30030 March 2021 Annual Dose Report for 2020 BYRON 2021-0023, Registration of Use of Cask to Store Spent Fuel2021-03-25025 March 2021 Registration of Use of Cask to Store Spent Fuel BYRON 2021-0024, 2020 Regulatory Commitment Change Summary Report2021-03-19019 March 2021 2020 Regulatory Commitment Change Summary Report BYRON 2021-0001, Day Inservice Inspection Report for Interval 4, Period 2, (B2R22)2021-01-13013 January 2021 Day Inservice Inspection Report for Interval 4, Period 2, (B2R22) BYRON 2020-0087, National Pollutant Discharge Elimination System (NPDES) Permit No. IL00483132020-12-16016 December 2020 National Pollutant Discharge Elimination System (NPDES) Permit No. IL0048313 BYRON 2020-0084, 10 CFR 72.48 Evaluation Summary Report2020-12-10010 December 2020 10 CFR 72.48 Evaluation Summary Report BYRON 2020-0085, 10 CFR 50.59 Summary Report2020-12-10010 December 2020 10 CFR 50.59 Summary Report BYRON 2020-0067, Cycle 22 Core Operating Limits Report2020-10-20020 October 2020 Cycle 22 Core Operating Limits Report BYRON 2020-0063, Independent Spent Fuel Storage Installation - Transmittal of Annual Radioactive Effluent Release Repo2020-10-0101 October 2020 Independent Spent Fuel Storage Installation - Transmittal of Annual Radioactive Effluent Release Repo BYRON 2020-0053, Steam Generator Tube Inspection Report for Refueling Outage 232020-09-10010 September 2020 Steam Generator Tube Inspection Report for Refueling Outage 23 BYRON 2020-0025, Annual Dose Report 20192020-03-24024 March 2020 Annual Dose Report 2019 BYRON 2020-0015, Cycle 24 Core Operating Limits Report2020-03-17017 March 2020 Cycle 24 Core Operating Limits Report BYRON 2020-0010, Revision to Byron Station Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 172020-02-13013 February 2020 Revision to Byron Station Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 17 BYRON 2020-0008, 2019 Regulatory Commitment Change Summary Report2020-02-0707 February 2020 2019 Regulatory Commitment Change Summary Report BYRON 2019-0105, Post Examination Submittal Letter2019-11-26026 November 2019 Post Examination Submittal Letter BYRON 2019-0095, Registration of Use of Cask to Store Spent Fuel2019-10-10010 October 2019 Registration of Use of Cask to Store Spent Fuel BYRON 2019-0090, Registration of Use of Cask to Store Spent Fuel2019-09-18018 September 2019 Registration of Use of Cask to Store Spent Fuel BYRON 2019-0078, Registration of Use of Cask to Store Spent Fuel2019-08-22022 August 2019 Registration of Use of Cask to Store Spent Fuel BYRON 2019-0041, Revision to Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 162019-04-25025 April 2019 Revision to Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 16 BYRON 2019-0035, Submittal of 2018 Annual Radioactive Effluent Release Report2019-04-18018 April 2019 Submittal of 2018 Annual Radioactive Effluent Release Report BYRON 2019-0040, Cycle 22 Core Operating Limits Report2019-04-15015 April 2019 Cycle 22 Core Operating Limits Report BYRON 2019-0039, Annual Dose Report for 20182019-04-11011 April 2019 Annual Dose Report for 2018 BYRON 2019-0022, 2018 Regulatory Commitment Change Summary Report2019-03-13013 March 2019 2018 Regulatory Commitment Change Summary Report BYRON 2019-0015, Cycle 23 Core Operating Limits Report and Byron Station Unit 2 Cycle 21 Core Operating Limits Report2019-03-0707 March 2019 Cycle 23 Core Operating Limits Report and Byron Station Unit 2 Cycle 21 Core Operating Limits Report BYRON 2018-0130, Transmittal of 90-Day Lnservice Inspection Report for Interval 4, Period 1, (B1R22)2018-12-20020 December 2018 Transmittal of 90-Day Lnservice Inspection Report for Interval 4, Period 1, (B1R22) 2023-06-01
[Table view] |
Text
Exelon Generation Company, LLC www exeloncorp com Exelkn.s Byron Station Nuclear 4450 North German Church Road Byron, IL 61010-9794 October 25, 2002 LTR: BYRON 2002-0109 File: 1.10.0101 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Byron Station Unit 2 Facility Operating License No. NPF-66 NRC Docket No. STN 50-455 Subject Byron Station Unit 2 Response to NRC Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles" On August 3, 2001, the NRC issued NRC Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles". This bulletin requires that the following information be submitted to the NRC within 30 days after plant restart following the next refueling outage:
- a description of the extent of reactor pressure vessel head penetration nozzle leakage and cracking detected, including the number, location, size, and nature of each crack detected; and
- if cracking is identified, a description of the inspections, repairs, and other corrective actions taken to satisfy applicable regulatory requirements.
Pursuant to 10 CFR 50.54, "Conditions of Licenses," paragraph (f), Attachment I to this letter provides the Byron Station Unit 2 30-day response. This response is due to the NRC by November 6, 2002.
October 25, 2002 U.S. Nuclear Regulatory Commission Page 2 If you have any questions or desire additional information regarding this letter, please contact William Grundmann, Regulatory Assurance Manager, at (815) 406-2800.
sptfully, Ocard P.' Loprior Site Vice Presiden Byron Nuclear Generating Station RPLJMR/rah
Enclosures:
Attachment 1, Byron Station Unit 2 Response to NRC Bulletin 2001-01 cc: Regional Administrator- NRC Region III NRC Senior Resident Inspector- Byron Station NRC Project Manager- NRR - Byron Station Office of Nuclear Facility Safety - Illinois Department of Nuclear Safety
STATE OF ILLINOIS )
COUNTY OF OGLE )
IN THE MATTER OF EXELON GENERATION COMPANY, LLC ) Docket Numbers BYRON STATION UNIT 2 ) STN 50-455
SUBJECT:
Byron Station Unit 2 Response to NRC Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles" AFFIDAVIT I affirm that the content of this transmittal iitýe and correct to the best of my knowledge, information and belief.
ý-Acfard P. L~p 'lr Site Vice Presidet Byron Nuclear Ge erating Station Subscribed and sworn to before me, a Notary Public in and for the State above named, this . . day of 0 20 0 Notary Public
,N8trPtda Hayenga YPbcState of Jlnf E:W0My omsi q1res 3/2lj
ATTACHMENT I Byron Station Unit 2 Response to NRC Bulletin 2001-01 "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles"
Attachment I Byron Station Unit 2 Response to NRC Bulletin 2001-01 On August 3, 2001, the NRC issued NRC Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head Penetration Nozzles". This bulletin requires that the following information be submitted to the NRC within 30 days after plant restart following the next refueling outage:
- 5. Addressees are requested to provide the following information within 30 days afterplant restartfollowing the next refueling outage:
- a. a descriptionof the extent of vessel headpenetration (VHP) nozzle leakage and cracking detected at your plant, including the number, location,size, and nature of each crack detected;
- b. if cracking is identified, a descriptionof the inspections (type, scope, qualification requirements,and acceptance criteria),
repairs,and othercorrective actions you have taken to satisfy applicableregulatoryrequirements. This information is requested only if there are any changes from priorinformation submitted in accordancewith this bulletin.
Byron Station Unit 2 Response
- a. a description of the extent of VHP nozzle leakage and crackingdetected at your plant, including the number, location, size, and nature of each crack detected;
Response
No VHP nozzle leakage or cracking was detected during refueling outage B2R10 in Fall 2002. The following inspections were performed on the reactor pressure vessel (RPV) head during refueling outage B2R10:
Pre and post-outage VT-2 examinations of the accessible areas on top of the RPV head (i.e., control rod drive mechanism housings) were performed at normal reactor coolant system pressure. No evidence of leakage, boric acid residue, or degradation of material due to corrosion was identified during these inspections.
VT-1 examinations were performed on the core exit thermocouple clamp assemblies. There was no evidence of erosion, corrosion, or wear of the bolting material, and there were no instances of bolting material degradation due to corrosion. These connections, which are disassembled each refueling outage, were specifically examined for leakage by VT-2 qualified personnel during unit startup and no abnormal conditions were identified.
Page 1 of 2
Attachment I A 100% bare metal RPV head examination was completed. This examination consisted of visual examinations (3600) of the RPV head vent penetration and all RPV head nozzles (78) at the annulus region to determine if any boric acid leakage was evident. In addition, the bare metal RPV head was visually examined for general condition and to ensure no RPV head wastage was present. These examinations found no evidence of boric acid leakage from the nozzles or degradation of the RPV head.
- b. if cracking is identified, a descriptionof the inspections (type, scope, qualification requirements,and acceptance criteria),repairs,and other corrective actionsyou have taken to satisfy applicable regulatory requirements. This information is requested only if there are any changes from priorinformationsubmitted in accordancewith this bulletin.
Response
No VHP nozzle leakage or cracking was identified during refueling outage B2R10; therefore, no inspections, repairs, or other corrective actions were required.
Page 2 of 2