BYRON 2020-0084, 10 CFR 72.48 Evaluation Summary Report
ML20345A054 | |
Person / Time | |
---|---|
Site: | Byron |
Issue date: | 12/10/2020 |
From: | Welt H Exelon Generation Co |
To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation |
References | |
BYRON 2020-0084 | |
Download: ML20345A054 (1) | |
Similar Documents at Byron | |
---|---|
Category:Letter type:BYRON
MONTHYEARBYRON 2023-0065, Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline2023-11-17017 November 2023
[Table view]Unit 2 - Notification of Deviation from Electric Power Research Institute (EPRI) Topical Report MRP-227, Revision 1-A, Materials Reliability Program: Pressurized Water Reactor Internals Inspection and Evaluation Guideline BYRON 2023-0063, Day Inservice Inspection Report for Interval 4, Period 3, (B2R24)2023-11-16016 November 2023 Day Inservice Inspection Report for Interval 4, Period 3, (B2R24) BYRON 2023-0029, Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements2023-06-0101 June 2023 Response to Request for Additional Information Regarding Steam Generator Tube Inspection Reports to Reflect TSTF-577 Reporting Requirements BYRON 2023-0022, 2022 Annual Radiological Environmental Operating Report (AREOR)2023-05-0404 May 2023 2022 Annual Radiological Environmental Operating Report (AREOR) BYRON 2023-0002, Unit 2, Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements2023-04-0606 April 2023 Unit 2, Steam Generator Tube Inspection Report to Reflect TSTF-577 Reporting Requirements BYRON 2023-0012, Cycle 26 Core Operating Limits Report2023-03-16016 March 2023 Cycle 26 Core Operating Limits Report BYRON 2022-0081, CFR72.48 Evaluation Summary Report2022-12-0909 December 2022 CFR72.48 Evaluation Summary Report BYRON 2022-0072, Steam Generator Tube Inspection Report for Refueling Outage 232022-10-27027 October 2022 Steam Generator Tube Inspection Report for Refueling Outage 23 BYRON 2022-0069, 2021 Regulatory Commitment Change Summary Report2022-10-13013 October 2022 2021 Regulatory Commitment Change Summary Report BYRON 2022-0071, Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment2022-10-13013 October 2022 Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment BYRON 2022-0065, Registration of Use of Cask to Store Spent Fuel2022-10-13013 October 2022 Registration of Use of Cask to Store Spent Fuel BYRON 2022-0063, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report for September 9, 2021 to September 8, 20222022-09-29029 September 2022 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report for September 9, 2021 to September 8, 2022 BYRON 2022-0064, Letter 2022-0064 Submittal of Byron Integrated Initial License Training Examination Materials(Signed)2022-09-28028 September 2022 Letter 2022-0064 Submittal of Byron Integrated Initial License Training Examination Materials(Signed) BYRON 2022-0059, Registration of Use of Cask to Store Spent Fuel2022-09-15015 September 2022 Registration of Use of Cask to Store Spent Fuel BYRON 2022-0045, Day Inservice Inspection Report for Interval 4, Period 2, (B2R23)2022-07-15015 July 2022 Day Inservice Inspection Report for Interval 4, Period 2, (B2R23) BYRON 2022-0026, Annual Radiological Environmental Operating Report2022-05-0505 May 2022 Annual Radiological Environmental Operating Report BYRON 2022-0030, Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Report2022-05-0303 May 2022 Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Report BYRON 2022-0028, Cycle 24 Core Operating Limits Report2022-04-28028 April 2022 Cycle 24 Core Operating Limits Report BYRON 2022-0016, Annual Dose Report for 20212022-04-0707 April 2022 Annual Dose Report for 2021 BYRON 2021-0072, Post Exam Submittal Letter2021-10-28028 October 2021 Post Exam Submittal Letter BYRON 2021-0033, Submittal on Initial Operator Licensing Examination Outline2021-10-28028 October 2021 Submittal on Initial Operator Licensing Examination Outline BYRON 2021-0063, Reactor Coolant System Pressure and Temperature Limits Report2021-09-28028 September 2021 Reactor Coolant System Pressure and Temperature Limits Report BYRON 2021-0064, Cycle 25 Core Operating Limits Report2021-09-28028 September 2021 Cycle 25 Core Operating Limits Report BYRON 2021-0032, 2020 Annual Radiological Environmental Operating Report (AREOR)2021-05-0606 May 2021 2020 Annual Radiological Environmental Operating Report (AREOR) BYRON 2021-0031, 2020 Annual Radioactive Effluent Release Report2021-04-21021 April 2021 2020 Annual Radioactive Effluent Release Report BYRON 2021-0027, Annual Dose Report for 20202021-03-30030 March 2021 Annual Dose Report for 2020 BYRON 2021-0023, Registration of Use of Cask to Store Spent Fuel2021-03-25025 March 2021 Registration of Use of Cask to Store Spent Fuel BYRON 2021-0024, 2020 Regulatory Commitment Change Summary Report2021-03-19019 March 2021 2020 Regulatory Commitment Change Summary Report BYRON 2021-0001, Day Inservice Inspection Report for Interval 4, Period 2, (B2R22)2021-01-13013 January 2021 Day Inservice Inspection Report for Interval 4, Period 2, (B2R22) BYRON 2020-0087, National Pollutant Discharge Elimination System (NPDES) Permit No. IL00483132020-12-16016 December 2020 National Pollutant Discharge Elimination System (NPDES) Permit No. IL0048313 BYRON 2020-0084, 10 CFR 72.48 Evaluation Summary Report2020-12-10010 December 2020 10 CFR 72.48 Evaluation Summary Report BYRON 2020-0085, 10 CFR 50.59 Summary Report2020-12-10010 December 2020 10 CFR 50.59 Summary Report BYRON 2020-0067, Cycle 22 Core Operating Limits Report2020-10-20020 October 2020 Cycle 22 Core Operating Limits Report BYRON 2020-0063, Independent Spent Fuel Storage Installation - Transmittal of Annual Radioactive Effluent Release Repo2020-10-0101 October 2020 Independent Spent Fuel Storage Installation - Transmittal of Annual Radioactive Effluent Release Repo BYRON 2020-0053, Steam Generator Tube Inspection Report for Refueling Outage 232020-09-10010 September 2020 Steam Generator Tube Inspection Report for Refueling Outage 23 BYRON 2020-0025, Annual Dose Report 20192020-03-24024 March 2020 Annual Dose Report 2019 BYRON 2020-0015, Cycle 24 Core Operating Limits Report2020-03-17017 March 2020 Cycle 24 Core Operating Limits Report BYRON 2020-0010, Revision to Byron Station Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 172020-02-13013 February 2020 Revision to Byron Station Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 17 BYRON 2020-0008, 2019 Regulatory Commitment Change Summary Report2020-02-0707 February 2020 2019 Regulatory Commitment Change Summary Report BYRON 2019-0105, Post Examination Submittal Letter2019-11-26026 November 2019 Post Examination Submittal Letter BYRON 2019-0095, Registration of Use of Cask to Store Spent Fuel2019-10-10010 October 2019 Registration of Use of Cask to Store Spent Fuel BYRON 2019-0090, Registration of Use of Cask to Store Spent Fuel2019-09-18018 September 2019 Registration of Use of Cask to Store Spent Fuel BYRON 2019-0078, Registration of Use of Cask to Store Spent Fuel2019-08-22022 August 2019 Registration of Use of Cask to Store Spent Fuel BYRON 2019-0041, Revision to Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 162019-04-25025 April 2019 Revision to Site Security Plan, Safeguards Contingency Plan, Training and Qualification Plan, and Independent Spent Fuel Storage Installation Plan, Revision 16 BYRON 2019-0035, Submittal of 2018 Annual Radioactive Effluent Release Report2019-04-18018 April 2019 Submittal of 2018 Annual Radioactive Effluent Release Report BYRON 2019-0040, Cycle 22 Core Operating Limits Report2019-04-15015 April 2019 Cycle 22 Core Operating Limits Report BYRON 2019-0039, Annual Dose Report for 20182019-04-11011 April 2019 Annual Dose Report for 2018 BYRON 2019-0022, 2018 Regulatory Commitment Change Summary Report2019-03-13013 March 2019 2018 Regulatory Commitment Change Summary Report BYRON 2019-0015, Cycle 23 Core Operating Limits Report and Byron Station Unit 2 Cycle 21 Core Operating Limits Report2019-03-0707 March 2019 Cycle 23 Core Operating Limits Report and Byron Station Unit 2 Cycle 21 Core Operating Limits Report BYRON 2018-0130, Transmittal of 90-Day Lnservice Inspection Report for Interval 4, Period 1, (B1R22)2018-12-20020 December 2018 Transmittal of 90-Day Lnservice Inspection Report for Interval 4, Period 1, (B1R22) 2023-06-01 Category:Report MONTHYEARML23321A0452023-11-17017 November 2023
[Table view]EC 639996 (Byron), Revision 1 and 640160 (Braidwood), Revision 0, Technical Evaluation for NEI 03-08 Deviation of Baffle-Former Bolts Volumetric Examinations for Byron and Braidwood BW230054, Attachment 2: MDMP Deviation Form2023-11-17017 November 2023 Attachment 2: MDMP Deviation Form RS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023 Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 BYRON 2022-0071, Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment2022-10-13013 October 2022 Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment NMP1L3469, Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits2022-06-30030 June 2022 Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits RS-22-071, License Renewal Response to Commitment 10 - Evaluation of Possible PWSCC Crack Initiation and Propagation in the Steam Generator Channel Head Assembly and Tube-to-Tubesheet Welds2022-06-0707 June 2022 License Renewal Response to Commitment 10 - Evaluation of Possible PWSCC Crack Initiation and Propagation in the Steam Generator Channel Head Assembly and Tube-to-Tubesheet Welds RS-22-047, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2022-04-0808 April 2022 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-21-112, Updated 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2021-10-22022 October 2021 Updated 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-21-093, R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2021-09-0101 September 2021 R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-21-056, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Weld2021-05-12012 May 2021 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Weld RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping BYRON 2020-0085, 10 CFR 50.59 Summary Report2020-12-10010 December 2020 10 CFR 50.59 Summary Report BYRON 2020-0084, 10 CFR 72.48 Evaluation Summary Report2020-12-10010 December 2020 10 CFR 72.48 Evaluation Summary Report ML20303A1752020-10-23023 October 2020 Proposed Relief Request from Section XI Repair/Replacement Documentation for Bolting Replacement of Pressure Retaining Bolting ML20195B1592020-07-10010 July 2020 Attachment 1 - Description and Assessment ML20195B1622020-06-30030 June 2020 Attachment 11 - SG-SGMP-17-25-NP, Revision 1, Foreign Object Limits Analysis for the Byron and Braidwood Unit 2 Steam Generators June 2020 ML20195B1612020-06-25025 June 2020 Attachment 6 - Intertek Report No. Aim 200510800-2Q-1(NP), Byron Unit 2 Operational Assessment Addressing Deferment of B2R22 Steam Generator Tube Examinations to B2R23, April 2022 ML19228A0232019-08-15015 August 2019 Proposed Alternative to Utilize Code Case N-879 ML18192C1522018-07-18018 July 2018 Review of Fall 2017 Steam Generator Tube Inservice Inspection Report ML17355A5612017-12-21021 December 2017 Ltr. 12/21/17 Response to Disputed Non-Cited Violation Documented in Byron Station, Units 1 and 2 - Evaluations of Changes, Tests, and Experiments Baseline Inspection Report 05000454/2017009; 05000455/2017009 (DRS-N.Feliz-Adorno) ML17234A4782017-08-22022 August 2017 Mitigating Strategies Assessment (MSA) Report for the Reevaluated Seismic Hazard Information - NEI 12-06, Appendix H, Revision 2, H.4.4 Path 4: GMRS ≪ 2xSSE RS-17-048, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2017-04-0707 April 2017 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML17024A0362016-12-31031 December 2016 Operating Data Report for 2016 ML16344A0062016-12-0909 December 2016 10 CFR 72.48 Evaluation Summary of Biennial Report of Changes, Tests, or Experiments, Performed RS-17-039, Attachment 6, Areva Document 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations.2016-10-0707 October 2016 Attachment 6, Areva Document 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations. ML17360A1742016-10-0707 October 2016 Attachment 6: Areva Document 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations (Non-Proprietary) ML16356A0202016-10-0707 October 2016 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations. ML17095A2692016-10-0707 October 2016 Attachment 6, Areva Document 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations. ML17170A1472016-10-0707 October 2016 Areva, 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations. RS-16-122, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2016-08-31031 August 2016 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident ML16236A2082016-08-23023 August 2016 Report of Backfit Appeal Review Panel ML16214A1992016-08-11011 August 2016 an Assessment of Core Damage Frequency for Byron/Braidwood Backit Appeal Review RS-16-088, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2016-07-15015 July 2016 Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-16-073, Submittal of Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2016-04-0707 April 2016 Submittal of Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-16-057, Supplement to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds2016-03-15015 March 2016 Supplement to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds RS-15-267, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-11-30030 November 2015 Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-15-072, Comments on the Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 542015-02-12012 February 2015 Comments on the Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 54 RS-14-348, Comments on the Safety Evaluation Report with Open Items, Related to the License Renewal Application2014-12-15015 December 2014 Comments on the Safety Evaluation Report with Open Items, Related to the License Renewal Application RS-14-277, Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 12014-09-24024 September 2014 Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 ML14128A5562014-06-30030 June 2014 Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML14178B2222014-06-24024 June 2014 Technical Review of TIA 2013-02, Single Spurious Assumptions for Braidwood and Byron Stations Safe-Shutdown Methodology ML14085A5332014-05-29029 May 2014 Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident ML14120A0392014-04-24024 April 2014 Units 1 & 2 - License Amendment Request to Install New Low Degraded Voltage Relays & Timers on the 4.16 Kv Engineered Safety Features (ESF) Buses BYRON 2014-0040, Pressure and Temperature Limits Report (PTLR) Revised for Negative Pressure Application During Reactor Coolant System Vacuum Fill2014-03-27027 March 2014 Pressure and Temperature Limits Report (PTLR) Revised for Negative Pressure Application During Reactor Coolant System Vacuum Fill ML14079A4232014-03-12012 March 2014 Enclosure 1, Byron Nuclear Generating Station, Flood Hazard Reevaluation Report, Revision 0 ML14066A4792014-03-0404 March 2014 Clarification of Licensing Basis Assumptions for a Natural Circulation Cooldown Event RS-14-082, ECCS Evaluation Model Error - 10 CFR 50.46 30-Day Report2014-02-27027 February 2014 ECCS Evaluation Model Error - 10 CFR 50.46 30-Day Report BYRON 2014-0003, Pressure and Temperature Limits Report (PTLR) for Measurement Uncertainty Recapture (Mur) Power Uprate2014-02-13013 February 2014 Pressure and Temperature Limits Report (PTLR) for Measurement Uncertainty Recapture (Mur) Power Uprate ML13225A5952013-12-17017 December 2013 Interim Staff Evaluation Related to Integrated Plan in Response to Order EA-12-049(Mitigation Strategies) 2023-09-29 Category:Technical MONTHYEARRS-23-094, Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 752023-09-29029 September 2023
[Table view]Relief Request I4R-24, Alternative for Post-Peening Reexamination Frequency for Reactor Pressure Vessel Head Penetration Nozzle Number 75 RS-23-056, Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 102023-04-20020 April 2023 Response to Request for Additional Information to Braidwood Station, Unit 1, and Byron Station, Unit 1, for Steam Generator License Renewal Response to Commitment 10 BYRON 2022-0071, Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment2022-10-13013 October 2022 Materials Reliability Program: Topical Report for Primary Water Stress Corrosion Cracking Mitigation by Surface Stress Improvement (MRP-335, Revision 3-A) Final Causal Report and Description of Corrective Action Assignment NMP1L3469, Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits2022-06-30030 June 2022 Constellation Energy Company, LLC, Request for Use of Honeywell Mururoa V4F1 R Supplied Air Suits RS-21-093, R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections2021-09-0101 September 2021 R. E. Ginna, Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections RS-21-056, Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Weld2021-05-12012 May 2021 Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Weld RS-21-001, Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping2021-01-0404 January 2021 Revised Proposed Alternative to Utilize Code Cases N-878 and N-880 for Carbon Steel Piping BYRON 2020-0085, 10 CFR 50.59 Summary Report2020-12-10010 December 2020 10 CFR 50.59 Summary Report BYRON 2020-0084, 10 CFR 72.48 Evaluation Summary Report2020-12-10010 December 2020 10 CFR 72.48 Evaluation Summary Report ML20195B1592020-07-10010 July 2020 Attachment 1 - Description and Assessment ML20195B1622020-06-30030 June 2020 Attachment 11 - SG-SGMP-17-25-NP, Revision 1, Foreign Object Limits Analysis for the Byron and Braidwood Unit 2 Steam Generators June 2020 ML20195B1612020-06-25025 June 2020 Attachment 6 - Intertek Report No. Aim 200510800-2Q-1(NP), Byron Unit 2 Operational Assessment Addressing Deferment of B2R22 Steam Generator Tube Examinations to B2R23, April 2022 ML19228A0232019-08-15015 August 2019 Proposed Alternative to Utilize Code Case N-879 ML17234A4782017-08-22022 August 2017 Mitigating Strategies Assessment (MSA) Report for the Reevaluated Seismic Hazard Information - NEI 12-06, Appendix H, Revision 2, H.4.4 Path 4: GMRS ≪ 2xSSE ML16356A0202016-10-0707 October 2016 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations. ML17360A1742016-10-0707 October 2016 Attachment 6: Areva Document 51-9263014-000, PWSCC Evaluation of Uhp Cavitation Peening for Byron and Braidwood Reactor Vessel Head Penetrations (Non-Proprietary) RS-16-057, Supplement to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds2016-03-15015 March 2016 Supplement to Response to Requests for Additional Information for Relief for Alternate Requirements for Repair of Reactor Vessel Head Penetrations with Nozzles Having Pressure-Retaining Partial-Penetration J-Groove Welds RS-15-267, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2015-11-30030 November 2015 Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) RS-14-277, Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 12014-09-24024 September 2014 Proposed Alternative to Utilize Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping Section XI, Division 1 ML14178B2222014-06-24024 June 2014 Technical Review of TIA 2013-02, Single Spurious Assumptions for Braidwood and Byron Stations Safe-Shutdown Methodology BYRON 2014-0040, Pressure and Temperature Limits Report (PTLR) Revised for Negative Pressure Application During Reactor Coolant System Vacuum Fill2014-03-27027 March 2014 Pressure and Temperature Limits Report (PTLR) Revised for Negative Pressure Application During Reactor Coolant System Vacuum Fill ML14079A4232014-03-12012 March 2014 Enclosure 1, Byron Nuclear Generating Station, Flood Hazard Reevaluation Report, Revision 0 RS-14-082, ECCS Evaluation Model Error - 10 CFR 50.46 30-Day Report2014-02-27027 February 2014 ECCS Evaluation Model Error - 10 CFR 50.46 30-Day Report BYRON 2014-0003, Pressure and Temperature Limits Report (PTLR) for Measurement Uncertainty Recapture (Mur) Power Uprate2014-02-13013 February 2014 Pressure and Temperature Limits Report (PTLR) for Measurement Uncertainty Recapture (Mur) Power Uprate ML13338A6422013-12-0909 December 2013 Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Byron Station, Units 1 and 2, TAC Nos.: MF0893 and MF0894 ML17255A8322013-07-0101 July 2013 Full Action Request Report AR 1531420, No Actions Tracking Update to Calculation 3C8-0282-001, Redacted RS-17-119, Byron, Units 1 and 2 - Full Action Request Report AR 1531420, No Actions Tracking Update to Calculation 3C8-0282-001, Redacted2013-07-0101 July 2013 Byron, Units 1 and 2 - Full Action Request Report AR 1531420, No Actions Tracking Update to Calculation 3C8-0282-001, Redacted ML17255A8312011-10-31031 October 2011 Full Action Request Report AR 1284054, Legacy Issues with Main Steam Tunnel Pressurization Calculation, Redacted RS-17-119, Byron, Units 1 and 2 - Full Action Request Report AR 1284054, Legacy Issues with Main Steam Tunnel Pressurization Calculation, Redacted2011-10-31031 October 2011 Byron, Units 1 and 2 - Full Action Request Report AR 1284054, Legacy Issues with Main Steam Tunnel Pressurization Calculation, Redacted ML12083A1232011-06-30030 June 2011 WCAP-17330-NP, Rev. 1, H*: Resolution of NRC Technical Issue Regarding Tubesheet Bore Eccentricity (Model F/Model D5). RS-12-023, WCAP-17330-NP, Rev. 1, H*: Resolution of NRC Technical Issue Regarding Tubesheet Bore Eccentricity (Model F/Model D5).2011-06-30030 June 2011 WCAP-17330-NP, Rev. 1, H*: Resolution of NRC Technical Issue Regarding Tubesheet Bore Eccentricity (Model F/Model D5). ML1117900382011-06-23023 June 2011 Steam Generator Tube Rupture Analysis Report, Attachment 5a to Braidwood Station, Units 1 & 2, Byron Station, Unit 1 & 2, Request for License Amendment Regarding Measurement Uncertainty Recapture (Mur) Power Uprate ML1117900422011-06-21021 June 2011 Mur Technical Evaluation, (Non-Proprietary Version), Attachment 7 to Braidwood Station, Units 1 & 2, Byron Station, Unit 1 & 2, Request for License Amendment Regarding Measurement Uncertainty Recapture (Mur) Power Uprate ML1000503662009-09-18018 September 2009 Exelon Nuclear, Form NIS-2 Owner'S Report for Repair/Replacement Activity as Required by the Provisions of the ASME Code Section Xi BYRON 2010-0001, Form NIS-2 Owner'S Report for Repair/Replacement Actitivity as Required by the Provisions of the ASME Code Section XI2009-09-16016 September 2009 Form NIS-2 Owner'S Report for Repair/Replacement Actitivity as Required by the Provisions of the ASME Code Section XI ML0925202652009-09-0404 September 2009 Attachment 3, Corrected Pages to WCAP-17072-NP (Non-Proprietary) ML17255A8302009-07-0101 July 2009 Engineering Change EC 366685, Revision 67, OP Eval. 07-006, Aux Feed Tunnel Covers Installation, Redacted RS-17-119, Byron, Units 1 and 2 - Engineering Change EC 366685, Revision 67, OP Eval. 07-006, Aux Feed Tunnel Covers Installation, Redacted2009-07-0101 July 2009 Byron, Units 1 and 2 - Engineering Change EC 366685, Revision 67, OP Eval. 07-006, Aux Feed Tunnel Covers Installation, Redacted ML0821900132008-08-0707 August 2008 Monthly Operating Reports Second Quarter 2008 ML17255A8402008-06-30030 June 2008 Full Action Request Report AR 792213, MSLB Calc. Energy Release Error, Redacted ML17255A8372008-06-12012 June 2008 Full Action Request Report AR 789344, Error in Ms Tunnel Pressurization Calculation, Redacted RS-17-119, Byron, Units 1 and 2 - Full Action Request Report AR 789344, Error in Ms Tunnel Pressurization Calculation, Redacted2008-06-12012 June 2008 Byron, Units 1 and 2 - Full Action Request Report AR 789344, Error in Ms Tunnel Pressurization Calculation, Redacted RS-08-075, LTR-CDME-08-11, Rev. 3 Np, Interim Alternate Repair Criterion (ARC) for Cracks in the Lower Region of the Tubesheet Expansion Zone.2008-06-0303 June 2008 LTR-CDME-08-11, Rev. 3 Np, Interim Alternate Repair Criterion (ARC) for Cracks in the Lower Region of the Tubesheet Expansion Zone. ML0802304852008-01-14014 January 2008 Evaluation of 2002 USGS National Seismic Hazard Assessment, Final Report RS-07-100, Emergency Core Cooling System Evaluation Model Error - 10 CFR 50.46 Report2007-06-22022 June 2007 Emergency Core Cooling System Evaluation Model Error - 10 CFR 50.46 Report RS-07-079, Plant Specific ECCS Evaluation Change - 10 CFR 50.46 Report2007-05-10010 May 2007 Plant Specific ECCS Evaluation Change - 10 CFR 50.46 Report RS-07-059, Transmittal of WCAP-16401-NP, Revision 0, Technical Basis for Repair Options for Reactor Vessel Head Penetration Nozzles and Attachment Welds: Byron and Braidwood Units 1 & 2.2007-05-0303 May 2007 Transmittal of WCAP-16401-NP, Revision 0, Technical Basis for Repair Options for Reactor Vessel Head Penetration Nozzles and Attachment Welds: Byron and Braidwood Units 1 & 2. BYRON 2007-0051, Reactor Coolant System (RCS) Pressure and Temperature Limits Reports (PTLR)2007-04-17017 April 2007 Reactor Coolant System (RCS) Pressure and Temperature Limits Reports (PTLR) ML0702402612007-01-23023 January 2007 Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) ML0634601312006-12-0707 December 2006 Attachment 11, Exelon/Amergen Response to the Request for Additional Information, EP-EAL-0611, Criteria for Choosing Containment Radiation Monitor Reading Indicative Loss of the RCS Barrier 2023-09-29 |
Text
Byron Generating Station Exelon Generation 4450 North German Church Rd Byron. IL 61010 -9794 www.exeloncorp.com December 10, 2020 10 CFR 72.48 LTR: BYRON 2020-0084 File: 1.10.0101 (10.101) 2.07.0611 (5F.108)
U.S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555-001 Byron Station, Units 1 and 2 Renewed Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455
Subject:
10 CFR 72.48 Evaluation Summary Report The purpose of this letter is to submit the initial biennial report of changes, tests, or experiments, performed by Exelon Generation Company, LLC (EGC) for the Byron Station (Byron) Independent Spent Fuel Storage Installation (ISFSI), as required by 10 CFR 72.48, "Changes, tests, and experiments," paragraph (d)(2). Subsequent reports will be provided within an interval of 24 months, as required by 10 CFR 72.48(d)(2) .
This report addresses the period from November 1, 2018 through October 31, 2020.
There were no 10 CFR 72.48 Evaluations performed for the Byron ISFSI during this period. Thus, no 10 CFR 72.48 Evaluation summaries are provided.
There are no regulatory commitments contained in this letter.
Should you have any questions, please contact Ms. Lisa Zurawski, Regulatory Assurance Manager, at (815) 406-2800.
Respectfully, Harris Welt Plant Manager Byron Generating Station HW/LZ/tv cc: NRC Regional Administrator- NRC Region Ill