3F0698-06, Notifies of Scheduled Completion Date for Unit 3 Re Analysis/Calculation Upgrade Program.Addl Details in Analysis/Calculation Upgrade Program Document,Available on Site

From kanterella
Jump to navigation Jump to search
Notifies of Scheduled Completion Date for Unit 3 Re Analysis/Calculation Upgrade Program.Addl Details in Analysis/Calculation Upgrade Program Document,Available on Site
ML20249B297
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 06/18/1998
From: Baumstark J
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F0698-06, 3F698-6, NUDOCS 9806220294
Download: ML20249B297 (2)


Text

_ - - - - . - - _ - - _ - - _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ _ _ _ _

Firrida 1 Power i E N E ,VJ a ". een.12 ET~.iL"o U.* w l!

l l

June 18,1998 3F0698-06 U.S. Nuclear Regulatory Commission l Attn: Document Control Desk {

Washington, DC 20555-0001 l

)

Subject:

Notification of the Scheduled Completion Date for the Crystal River Unit 3 i

" Analysis / Calculation Upgrade Program"

Reference:

FPC to NRC letter,3F0298-09, dated February 9,1998, "Non-Restart Follow-up ,

Items"

)

Dear Sir:

In the above referenced letter, Florida Power Corporation (FPC) committed to complete the development of the Crystal River Unit 3 (CR-3) Analysis / Calculation Upgrade Program by June 19, j l 1998, and notify the NRC of the scheduled completion date. l The Program was completed and approved by FPC Engineering management on June 11,1998. f '

Under the Program guidelines, the analyses / calculations have been prioritized by safety significance. Analyses / calculations that have already been upgraded or are covered by other ongoing site programs are not included. The Program completion date is December 18, 2003 (this commitment is contained in the Attachment to this letter). Additional details are in our Analysis / Calculation Upgrade Program document, which is available on site.

If you have any ouestions regarding this letter, please contact Ms. Sherry Bernhoft, Manager, l Nuclear Licensing at (352) 563-4566. I Sincerely 4 L% /

J. S. aumstark Director Nuclear Engineering and Projects j

l JSB/jnb y L.3 >

)b '

f

~

l Attachment xc: Regional Administrator, Region 11 Senior Resident Inspector NRR Project Manager 9806220294 980618 PDR ADOCK 05000302 P Pm CRYSTAL RIVER ENERGY COMPLEX: 15760 W. Power Line Street

  • Crystal River, Florida 34428 4708 (352)796 4486 l A Florida Progress Company L.__. . _ _ . - . _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ - - _ . _ _ _ _ _ _ _

~

e U.S. Nuclear Regulatory Commission Attachment

- 3F%98-06 Page1 of1 i

" (

List of Regulatory Commitments

' The following table identifies those actions committed to by Florida Power Corporation in this document. Any other actions discussed in the submittal represent intended or planned actions by Florida Power Corporation. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Manager of Nuclear Licensing of any questions regarding this document or any associated regulatory commitments.

ID NUMBER COMMITMENT DUE DATE 3F0698-06 Florida Power Corporation will complete the December 18,2003

" Analysis / Calculations Upgrade Program" for Crystal River Unit 3

)