Revises Completion Date for EOPs at Crystal River Unit 3 from 970331 to 970829.Completion of EOP Enhancements Required to Support Operating Crew Training
ML20137E915
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 03/25/1997
From: Cowan J
FLORIDA POWER CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
3F0397-15, 3F397-15, NUDOCS 9703280303
Download: ML20137E915 (1)


Text

~

Florida Power CORPORATION n=*mUN March 25 1997 i 3F0397-1$  !

U.S. Nuclear Regulatory Commission  :

Attention: Document Control Desk I Washington, D.C. 20555-0001  !

Subject:

Emergency Operating Procedure Enhancement

References:

A. FPC to NRC letter, 3F0296-02, dated February 1, 1996 B. FPC to NRC letter, 3F0896-21, dated August 26, 1996 C. FPC to NRC letter, 3F1296-05, dated December 13, 1996

Dear Sir:

The purpose of this letter is to change the date for completing Emergency Operating Procedures (E0Ps) at Crystal River 3 (CR-3) from March 31, 1997 to August 29, 1997. Reference B informed the NRC that Florida Power Corporation (FPC) would complete the Emergency Operating Procedure Enhancement Program at Crystal River Unit 3 by March 31, 1997. This change is necessary to ensure the E0Ps contain the technical and design basis improvements identified during the current outage, which will complete in December,1997. The E0P Enhancement Program as previously identified in References A and B continues to progress.

The revised E0Ps will be issued by November 21, 1997, which is prior to restart from the current outage. In addition, operating crews will be trained prior to changing to Mode 4 or above. The completion of the E0P enhancements is required to support operating crew training, which is being tracked as Restart Item 0-3 (Reference C - Restart Issues List).

Sincerely, j IM w John Paul Cowan C Vice President [/ QC Nuclear Production 3 xc: Regional Administrator, Region II Senior Resident Inspector l NRR Project Manager l 9703280303 970325 l}lll))[lllll*]l*l[ill1lhl]ll l PDR ADOCK 05000302