Finding | |
---|---|
Title | Reactor Down Power due to Reactor Recirculation Pump Motor Lower Bearing Oil Leak |
Description | A self-revealed finding of very low safety significance was identified for the licensees failure to comply with the requirements of station procedure MAAA716004, Compression Fittings Inspection, Installation, Remake and Repair, Revision 3. Specifically, the licensee failed to properly assemble a joint that was part of the reactor recirculation (RR) pump motor B oil level monitoring system that subsequently leaked requiring the plant operators to perform an unplanned power reduction to allow for identification and repairs of the leak. The licensee documented this issue in the corrective action program (CAP) as Action Request (AR) 04029024. As corrective actions, the licensee made repairs to the effected joint, inspected the remaining joints to ensure proper integrity, and filled the lower bearing reservoir. This issue was more than minor because it was associated with the equipment performance attribute of the Initiating Events cornerstone and impacted the cornerstone objective of limiting the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the leak on the reactor recirculation pump motor oil level monitoring system would have eventually resulted in the failure of the reactor recirculation pump causing a transient and upsetting plant stability. This finding was determined to be of very low safety significance because the event did not cause a reactor trip. The inspectors determined this finding affected the cross-cutting area of human performance in the aspect of work management, where the organization implements a process of planning, controlling, and executing work activities such that nuclear safety is the overriding priority. The work process includes the identification and management of risk commensurate to the work and the need for coordination with different groups or job activities. Specifically, the licensee failed to ensure that all personnel installing the compression fittings received an installers brief prior to performing work on the reactor recirculation pump motor oil level monitoring system. [H.5] |
Site: | Clinton |
---|---|
Report | IR 05000461/2017004 Section 4OA3 |
Date counted | Dec 31, 2017 (2017Q4) |
Type: | NCV: Green |
cornerstone | Initiating Events |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71153 |
Inspectors (proximate) | W Schaup E Sanchez-Santiago R Baker N Fields G Hansen M Holmberg D Reeser G Roach K Stoedter |
Violation of: | 10 CFR 50.65(a)(4) |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |