05000321/LER-2008-002, Edwin L. Hatch, Unit 1 Regarding Corrosion Induced Bonding Results in Safety Relief Valve Lift Setpoint Drift

From kanterella
(Redirected from 05000321/LER-2008-002)
Jump to navigation Jump to search
Edwin L. Hatch, Unit 1 Regarding Corrosion Induced Bonding Results in Safety Relief Valve Lift Setpoint Drift
ML081480506
Person / Time
Site: Hatch 
Issue date: 05/27/2008
From: Madison D
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-08-0801 LER 08-002-00
Download: ML081480506 (5)


LER-2008-002, Edwin L. Hatch, Unit 1 Regarding Corrosion Induced Bonding Results in Safety Relief Valve Lift Setpoint Drift
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications

10 CFR 50.73(a)(2)(i)

10 CFR 50.73(a)(2)(vii), Common Cause Inoperability

10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded

10 CFR 50.73(a)(2)(viii)(A)

10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition

10 CFR 50.73(a)(2)(viii)(B)

10 CFR 50.73(a)(2)(iii)

10 CFR 50.73(a)(2)(ix)(A)

10 CFR 50.73(a)(2)(iv)(A), System Actuation

10 CFR 50.73(a)(2)(x)

10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor

10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat

10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown

10 CFR 50.73(a)(2)(v), Loss of Safety Function
3212008002R00 - NRC Website

text

D. R**diIOIIDellil)

Vice President Hatch Southern Nuclur Opending Comp...,. Inc.

Plant Edwin I. Hatch 11028 Hatch Parl<wav. North Baxley. Georgia 31513 Tel 912.537.5859 Fax 912.366.2077 SOUIHERN.\\

COMPANY May 27, 2008 Docket No.:

50-321 NL-08-0801 U. S. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant - Unit 1 Licensee Event Report Corrosion Induced Bonding Results in Safety Relief Valve Lift Setooint Drift Ladies and Gentlemen:

In accordance with the reqUirements of 10 CFR 50.73(a)(2)(i)(B), Southern Nuclear Operating Company is submitting the enclosed Licensee Event Report (LER) concerning lift setpoint drift in more than one Safety Relief Valve.

This letter contains no NRC commitments. If you have any questions. please advise.

Sincerely, I:1bJ'~ ~"o,,:

D. R. Madison Vice President - Hatch DRM/MJKldaj Enclosure: LER 1-2008-002 cc: Southern Nuclear Operating Comoany Mr. J. T. Gasser, Executive Vice President Mr. D. H. Jones, Vice President - Engineering RTYPE: CHA02.004 U. S. Nuclear Regulatory Commission Mr. L. A. Reyes, Regional Administrator Mr. R. E. Martin, NRR Project Manager - Hatch Mr. J. A. Hickey, Senior Resident Inspector - Hatch

NRC FORM 366 (9-2007)

PRINTED ON RECYCLED PAPER NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION (9-2007)

LICENSEE EVENT REPORT (LER)

APPROVED BY OMB: NO. 3150-0104 EXPIRES: 08/31/2010

, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

1. FACILITY NAME Edwin I. Hatch Nuclear Plant Unit 1
2. DOCKET NUMBER 05000 321
3. PAGE 1 OF 4
4. TITLE Corrosion Induced Bonding Results in Safety Relief Valve Lift Setpoint Drift
5. EVENT DATE
6. LER NUMBER
7. REPORT DATE
8. OTHER FACILITIES INVOLVED MONTH DAY YEAR YEAR SEQUENTIAL NUMBER REV NO.

MONTH DAY YEAR FACILITY NAME DOCKET NUMBER 05000 03 29 2008 2008 - 002 -

0 05 27 2008 FACILITY NAME DOCKET NUMBER 05000

9. OPERATING MODE 1
10. POWER LEVEL 060
11. THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR§: (Check all that apply) 20.2201(b) 20.2203(a)(3)(i) 50.73(a)(2)(i)(C) 50.73(a)(2)(vii) 20.2201(d) 20.2203(a)(3)(ii) 50.73(a)(2)(ii)(A) 50.73(a)(2)(viii)(A) 20.2203(a)(1) 20.2203(a)(4) 50.73(a)(2)(ii)(B) 50.73(a)(2)(viii)(B) 20.2203(a)(2)(i) 50.36(c)(1)(i)(A) 50.73(a)(2)(iii) 50.73(a)(2)(ix)(A) 20.2203(a)(2)(ii) 50.36(c)(1)(ii)(A) 50.73(a)(2)(iv)(A) 50.73(a)(2)(x) 20.2203(a)(2)(iii) 50.36(c)(2) 50.73(a)(2)(v)(A) 73.71(a)(4) 20.2203(a)(2)(iv) 50.46(a)(3)(ii) 50.73(a)(2)(v)(B) 73.71(a)(5) 20.2203(a)(2)(v) 50.73(a)(2)(i)(A) 50.73(a)(2)(v)(C)

OTHER 20.2203(a)(2)(vi) 50.73(a)(2)(i)(B) 50.73(a)(2)(v)(D)

Specify in Abstract below or in NRC Form 366A

12. LICENSEE CONTACT FOR THIS LER FACILITY NAME Edwin I. Hatch / Kathy Underwood, Performance Analysis Supervisor TELEPHONE NUMBER (Include Area Code) 912-537-5931 CAUSE SYSTEM COMPONENT MANU-FACTURER REPORTABLE TO EPIX

CAUSE

SYSTEM COMPONENT MANU-FACTURER REPORTABLE TO EPIX B

SB RV T020 Yes

14. SUPPLEMENTAL REPORT EXPECTED YES (If yes, complete 15. EXPECTED SUBMISSION DATE)

NO

15. EXPECTED SUBMISSION DATE MONTH DAY YEAR ABSTRACT (Limit to 1400 spaces, i.e., approximately 15 single-spaced typewritten lines)

On March 29, at approximately 1104 EDT, Unit 1 was at 1697 CMWTh, which is 60.5 percent of rated thermal power (RTP). On that day, it was identified during bench testing that two Safety Relief Valves (SRVs) experienced setpoint drift that exceeded the allowable plant Technical Specifications (TS) limit. At the conclusion of bench testing, a total of three of the eleven SRVs were identified as having setpoint drift in excess of the TS limit.

The root cause of the SRV setpoint drift is corrosion-induced bonding between the pilot disc and seating surface.

Immediate corrective actions for this event included replacement of all eleven SRVs with refurbished pilot valves which have pilot discs made from Stellite 21 material, which is more resistant to corrosion bonding in this application. In addition, the pilot discs on the eleven valves that were removed for testing will be replaced with pilot discs made from Stellite 21.

Evaluation of additional actions to further improve SRV performance will be tracked under the plants corrective action program.

(If more space is required, use additional copies of NRC Form 366A)

PLANT AND SYSTEM IDENTIFICATION

General Electric - Boiling Water Reactor Energy Industry Identification System codes appear in the text as (EIIS Code XX).

DESCRIPTION OF EVENT

On March 29, at approximately 1104 EDT, Unit 1 was at 1697 CMWTh, which is 60.5 percent RTP. On that day it was identified during bench testing that two Safety Relief Valves (SRVs) (EIIS Code SB) experienced setpoint drift that exceeded the allowable plant Technical Specifications (TS) limit. At the conclusion of bench testing, a total of three of the eleven SRVs were identified as having setpoint drift in excess of the TS limit which is +/-

3%. The setpoint for each of the eleven SRVs is 1150 +/- 34.5 psig. The following is a tabulation of the test results for the eleven SRVs:

MPL Number Pilot Serial Number As-Found Lift Pressure Percent Drift 1B21-F013A 1190 1165 101.3 1B21-F013B 1003 1316 114.4 1B21-F013C 312 1177 102.3 1B21-F013D 1009 1161 101.0 1B21-F013E 311 1182 102.8 1B21-F013F 1227 1162 101.0 1B21-F013G 1226 1175 102.2 1B21-F013H 1011 1187 103.2 1B21-F013J 303 1180 102.6 1B21-F013K 1008 1175 102.2 1B21-F013L 301 1230 107.0 These valves were removed from service during the Spring 2008 refueling outage and replaced with like kind valves that were serviced and tested in accordance with plant procedures. These replacement valves had pilot discs made from Stellite 21 material, which is more resistant to corrosion bonding in this application.

CAUSE OF EVENT

The cause of the SRV setpoint drift exceeding the allowable plant TS limit is corrosion-induced bonding between the pilot disc and seating surface. (9-2007)

LICENSEE EVENT REPORT (LER)

CONTINUATION SHEET U.S. NUCLEAR REGULATORY COMMISSION

1. FACILITY NAME
2. DOCKET
6. LER NUMBER
3. PAGE YEAR SEQUENTIAL NUMBER REVISION NUMBER Edwin I. Hatch Nuclear Plant Unit 1 05000321 2008 002 0

3 OF 4

PRINTED ON RECYCLED PAPER REPORTABILITY ANALYSIS AND SAFETY ASSESSMENT This event is reportable per 50.73(a)(2)(i)(B) because an event occurred which is prohibited by Technical Specifications (TS). Specifically, multiple test failures of the SRVs is defined as reportable in NUREG-1022, Revision 2, dated October 2000, in section 3.2.2, example 3, titled Multiple Test Failures.

The 11 SRVs, which are located on the four main steam lines within the drywell between the reactor vessel and the inboard main steam isolation valves (MSIV EIIS Code SB), are required during Modes 1, 2, and 3 to limit the peak pressure in the nuclear system such that it will not exceed the applicable ASME Boiler and Pressure Vessel Code limits for the reactor coolant pressure boundary. Per TS Surveillance Requirement 3.4.3.1, the valves are tested in accordance with the In-service Testing Program to verify the safety function lift setpoints are within the specified limits. The SRVs must accommodate the most severe pressurization transient which, for the purposes of demonstrating compliance with the ASME Code limit of 1375 psig peak vessel pressure, has been defined as a closure of all MSIVs with a failure of the direct reactor protection system trip from the MSIV position switches; the reactor ultimately shutdowns from a high neutron flux trip. Analysis of this event using the as-found bench test results for SRV actuation pressures has demonstrated that the resultant peak pressure was within the ASME Code limit. Furthermore, the plant TS overpressure safety limit of 1325 psig dome pressure must be met during normal operations and for anticipated operational occurrences (AOOs). The analysis of the as-found test results also showed that for the MSIV Closure AOO with the MSIV position switches providing the reactor protection system trip, the resultant dome pressure was within the plant TS Safety Limit.

In addition, a non-credited electrical actuation system was installed in 1993 to ensure proper actuation of the SRVs. This system provides a redundant, independent method (i.e., electrical signal) to actuate the SRVs. During the run cycle the redundant electrical system was available. The system was procured to Class 1E environmental and seismic standards, and is deemed highly reliable.

Based on this analysis, it is concluded that this event had no adverse impact on nuclear safety. (9-2007)

LICENSEE EVENT REPORT (LER)

CONTINUATION SHEET U.S. NUCLEAR REGULATORY COMMISSION

1. FACILITY NAME
2. DOCKET
6. LER NUMBER
3. PAGE YEAR SEQUENTIAL NUMBER REVISION NUMBER Edwin I. Hatch Nuclear Plant Unit 1 05000321 2008 002 0

4 OF 4

PRINTED ON RECYCLED PAPER

CORRECTIVE ACTIONS

All eleven pilot valves have been replaced with refurbished pilot valves which have pilot discs made from Stellite 21 material.

Each of the eleven pilot discs from the valves removed for testing will be replaced with a pilot disc made from Stellite 21 material. Implementation will be tracked under the corrective action program.

SNC will continue to participate in industry working groups in evaluating potential solutions to this industry issue. Any additional actions to further improve SRV performance will be tracked under the plants corrective action program.

ADDITIONAL INFORMATION

Other Systems Affected: None

Failed Components Information

Master Parts List Number: 1B21-F013 EIIS System Code: SB Manufacturer: Target Rock Reportable to EPIX: Yes Model Number: 7567F Root Cause Code: B Type: Relief Valve EIIS Component Code: RV Manufacturer Code: T020 Commitment Information: This report does not create any new permanent licensing

commitments

Previous Similar Events

LER 2-2007-006, identified multiple SRV setpoint drift for five of the eleven SRVs.

Corrective actions for that LER were not yet implemented for the Unit 1 SRVs and thus could not have prevented this event. The eleven pilot discs replaced this outage on Unit 1 were replaced with pilot discs made from Stellite 21 material.

LER 1-2006-003, which identified an error in reporting multiple SRV setpoint drift, also described results from the previous three outages where multiple SRV setpoint drift had occurred. Corrective actions for that LER focused on ensuring proper reporting of SRV setpoint drift was performed.