LER-2005-001, Failure to Use an Ap a endix J 0 Ition B T re C Tested Component to Isolate Primary Containment Penetration
Edwin I. Hatch Nuclear Plant - Unit 1
Event date: 56-29-2005
Report date: 1-0-5000
Reporting criterion: 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications
3212005001R00 - NRC Website

PLANT AND SYSTEM IDEN1INCATION General Electric - Boiling Water Reactor Energy Industry Identification System codes appear in the text as (EIIS Code XX).

DESCRIPTION OF EVENT

On 4/29/2005, a problem was identified with instrument 1P7O-N003 following a routine calibration. This instrument provides annunciation to the Main Control Room if the nitrogen supply pressure to the drywell pneumatics is out of specifications. A Work Order (WO) was generated to replace 1P70-N003-TV-1. The WO was scheduled to be worked June 28, 2005. The WO was planned, reviewed, and packaged and the associated tag out for this work was drafted, reviewed and approved. Valve 1P70-N003-TV-1 was actually removed June 29, 2005 for replacement.

On 7/01/2005 at 1545 ET, Unit 1 was in the Run Mode at an approximate power level of 2793 CMWT (100 percent rated thermal power). At that time, it was determined that the valve used to isolate primary containment (EITS Code JM) on 6/29/2005 during work on component 1P7O-N003 (a barrier for primary containment penetration 22) was not in accordance with Technical Specification (TS) 3.6.1.3 Condition C.

This resulted in a condition prohibited by the plant's Technical Specifications. Component 1P70-N003 associated with penetration 22 functions as a single barrier for the penetration and is therefore governed by Technical Specification 3.6.1.3 Condition C. The Bases for TS 3.6.1.3 Condition C states in part that if the inoperable valve is required to be Type C tested per 10 CFR 50, Appendix J, Option B, the device chosen to isolate the penetration must also be subjected to Appendix J, Option B, Type C testing. The valve used to isolate the work activities associated with 1P70-N003 was valve 1P70-F133 and this valve is not subjected to Appendix J, Option B, Type C testing. The work on component 1P7O-N003 was completed and the clearance restored on 6/30/2005. The duration of the work and inspection activities exceeded the Required Action Statement times associated with TS 3.6.1.3 Condition C.

The WO for this activity was stamped "LLRT Review Required." The LLRT review was performed without identifying any concerns for performing this activity in Modes 1, 2, or 3. The LLRT review process does not require an Operations evaluation if the WO is scheduled to be performed during Modes 1, 2 or 3.

The clearance review for operation impact was performed by a System Operator, which is a non-licensed position. There were two questions required to be answered by this review that were relevant to this event.

One question was does the Technical Specifications allow the equipment to be out of service with other activities scheduled during this time? The second question was, can the Clearance be performed in the current or planned Plant Status? These questions were intended to establish barriers that would prevent the plant from operating in a condition prohibited by the Technical Specifications. This form was completed by a System Operator that was not trained in Licensing or Technical Specifications. It should be noted however, that the Tagout Coordinator, a licensed SRO, did review the tagout without recognizing that the isolation valve being used by this clearance (1P70-F133) was not an Appendix J, Option B, Type C tested component.

The Nitrogen Supply to the Drywell Pneumatics was still in service and pressurized to approximately 95 psig with no apparent leakage past isolation valve 1P70-F133. The piping downstream of the 1P70-F133 was open after the removal of 1P70-003-TV-1 and the workers performing the work did not observe any nitrogen leaking past 1P70-F133. As a result, primary containment was never actually open to the environment during this evolution.

CAUSE OF EVENT

The evaluations for the impact of performing this evolution on line were inadequate.

The requirement for the WO to have an LLRT review and to be worked while the plant was operating in Mode 1 did not specifically trigger an operations review. The planners and schedulers did not realize that performing WO 1051076502 in Mode 1 would impact Primary Containment.

The Operations Department Instruction required evaluations that were beyond the knowledge level or training of the System Operator performing the evaluation.

REPORTABILITY ANALYSIS AND SAFETY ASSESSMENT

This report is required by 10 CFR 50.73(a)(2)(i)(B) because the plant entered a condition that was prohibited by the plant's Technical Specifications. Specifically, Technical Specification Bases for 3.6.1.3 Condition C requires in part that; 4 4 . . . with one PCIV inoperable, except due to leakage not within limits, the inoperable valve must be restored to OPERABLE status or the affected penetration flow path must be isolated. The method of isolation must include the use of at least one isolation barrier that cannot be adversely affected by a single active failure. Isolation barriers that meet this criterion are a closed and de- activated automatic valve, a closed manual valve, and a blind flange. A check valve may not be used to isolate the affected penetration. The device must be subjected to leakage testing requirements equivalent to the inoperable valve, except for inoperable valves in the Core Spray and Low Pressure Coolant Injection (LPCI) systems. For example: 1) if the inoperable valve is required to be Type C tested per 10 CFR 50, Appendix J, Option B, the device chosen to isolate the penetration must also be subjected to Appendix J, Option B, Type C testing.

The valve used to isolate the work activities associated with 1P70-N003 was valve 1P70-F133 and this valve was not subjected to Appendix J, Option B, Type C testing. The work on component 1P70-N003 was completed and the clearance restored on 6/30/2005. The duration of the work activity exceeded the Required Action Statement times associated with TS 3.6.1.3 Condition C resulting in the plant being in a condition prohibited by the plant's Technical Specifications. Although the work activity was actually performed within the Required Action Times associated with TS 3.6.1.3, the work was not inspected and tested until after the Required Action Times had been exceeded. Nevertheless, the inspections confirmed the work had been done satisfactorily and thus the valve was leak tight.

During this event primary containment was maintained by the closure of valve 1P70-F133. The leak tightness of this valve was assured in that the Nitrogen Supply to the Drywell Pneumatics was still in service and pressurized to approximately 95 psig with no apparent leakage past isolation valve 1P7O-F133.

Therefore, it is concluded this event had no adverse impact on nuclear safety. This analysis is applicable to all power levels.

CORRECTIVE ACTIONS

The repair work was verified to be leak tight on July 1, 2005 in accordance with the provisions of 10 CFR 50 Appendix J Option B.

The appropriate personnel associated with the approval of this work activity were counseled concerning this event.

A requirement has been established for Operations to review work orders performed during Modes 1,2 or 3 on LLRT/lLRT components that may affect containment.

The Operations Department Instruction has been revised to require a currently licensed person to evaluate and complete any checklist item that addresses licensing issues if safety related equipment is involved with the work or tagout.

ADDITIONAL INFORMATION

Other Systems Affected: No systems other than those already mentioned in this report were affected by this event.

Failed Components Information: No failed components directly caused or resulted from this event.

Commitment Information: This report does not create any permanent licensing commitments.

Previous Similar Events: There has not been any previous similar event in the past two years in which a primary containment isolation valve repair was not isolated with a Tech Spec compliant device.