11-22-2016 | On September 24, 2016, at 20:40 hours, during reactor cooldown for Refueling Outage 29, Cooper Nuclear Station control room operators closed the inboard Main Steam Isolation Valves ( MSIV) to minimize steam flow to control the reactor cooldown rate. Reactor pressure was controlled using the Main Steam Line Drains; and the condensate/feed system was available for reactor water level control.
On September 25, 2016, at 01:03 hours, while equalizing pressure across the MSIVs to below 200 psid, a differential pressure of 190 psid was established. Upon opening MS-AO-80A, a Group 1 isolation was immediately received due to a Main Steam Line high flow signal. The control room operators subsequently equalized pressure and successfully opened MS-AO-80A, as well as the remaining MSIVs, at 18:52 hours.
The cause of the event was insufficient procedure guidance exists regarding limitations on opening the MSIVs. To correct this, the applicable procedure has been revised to change the differential pressure limitations for opening MSIVs from 200 psid to 80 psid.
The safety significance of the event is low and did not pose a threat to the health and safety of the public. |
---|
|
---|
Category:Letter
MONTHYEARML23334A2012024-01-0303 January 2024 Issuance of Amendment No. 274 Revision to Technical Specifications to Adopt TSTF-551, Revision 3, Revise Secondary Containment Surveillance Requirements ML23311A1122023-11-0909 November 2023 Project Manager Assignment ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000298/20230032023-11-0202 November 2023 Integrated Inspection Report 05000298/2023003 IR 05000298/20234012023-11-0101 November 2023 Cyber Security Report 05000298/2023401 Public ML23264A8052023-10-11011 October 2023 Issuance of Amendment No. 273 Revision to Technical Specifications to Adopt TSTF-580, Revision 1, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23233A1882023-09-0505 September 2023 Regulatory Audit Plan in Support of Relief Request RC3-02 Regarding Drywell Head Bolting IR 05000298/20243012023-09-0101 September 2023 Notification of NRC Initial Operator Licensing Examination 05000298/2024301 IR 05000298/20230052023-08-21021 August 2023 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298/2023005)- Mid Cycle Letter IR 05000298/20230022023-08-0808 August 2023 Integrated Inspection Report 05000298/2023002 IR 05000298/20234022023-08-0303 August 2023 NRC Security Inspection Report 05000298/2023402 ML23214A2742023-08-0303 August 2023 Nuclear Station - Notification of Inspection (NRC Inspection Report 05000298/2023004) and Request for Information IR 05000298/20234202023-08-0101 August 2023 Security Baseline Inspection Report 05000298/2023420 ML23173A0862023-06-26026 June 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000298/2023401 IR 05000298/20230102023-05-17017 May 2023 Biennial Problem Identification and Resolution Inspection Report 05000298/2023010 IR 05000298/20234032023-05-0404 May 2023 Security Baseline Inspection Report 05000298/2023403 ML23129A2822023-04-20020 April 2023 Submittal of Revision 31 to Updated Safety Analysis Report ML23102A0282023-04-19019 April 2023 U.S. Nuclear Regulatory Commission Presentation at the May 8, 2023, Brownville Village Meeting IR 05000298/20230012023-04-17017 April 2023 Integrated Inspection Report 05000298/2023001 ML23060A1582023-03-0808 March 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000298/2023001 IR 05000298/20220062023-03-0101 March 2023 Annual Assessment Letter for Cooper Nuclear Station Report 05000298/2022006 ML23041A1622023-02-10010 February 2023 Licensed Operator Positive Fitness-for-Duty Test Request for Additional Information IR 05000298/20220042023-01-30030 January 2023 Integrated Inspection Report 05000298/2022004 IR 05000298/20220112022-12-23023 December 2022 License Renewal Phase 4 Inspection Report 05000298/2022011 ML22286A2072022-11-30030 November 2022 Issuance of Amendment No. 272 Revision to Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements IR 05000298/20220032022-10-27027 October 2022 Integrated Inspection Report 05000298/2022003 ML22304A0052022-10-26026 October 2022 Surveillance Capsule Location (Re-insertion Into the Reactor Vessel) IR 05000298/20223022022-10-20020 October 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022302 ML22276A1562022-10-0505 October 2022 Notification of Commercial Grade Dedication Inspection 05000298/2023011 and Request for Information IR 05000298/20224022022-09-29029 September 2022 NRC Security Inspection Report 05000298/2022402 (Full Report) IR 05000298/20220052022-08-18018 August 2022 Updated Inspection Plan for Cooper Nuclear Station (Report 05000298 2022005) IR 05000298/20223012022-08-10010 August 2022 NRC Examination Report 05000298/2022301 IR 05000298/20220022022-07-28028 July 2022 Integrated Inspection Report 05000298/2022002 ML22200A2772022-07-21021 July 2022 Correction to Proposed Inservice Testing Alternative RS-01, Revision of Error in Safety Evaluation ML22152A1232022-07-18018 July 2022 Issuance of Amendment No. 271 Request for Exception from Certain Primary Containment Leak Rate Testing Requirements IR 05000298/20224012022-06-29029 June 2022 Security Baseline Inspection Report 05000298/2022401 IR 05000298/20224032022-06-28028 June 2022 Security Baseline Inspection Report 05000298/2022403 IR 05000298/20220102022-06-16016 June 2022 Triennial Fire Protection Inspection Report 05000298/2022010 ML22140A1612022-06-0808 June 2022 Proposed Inservice Inspection Alternative RR5-01 Revision 1 ML22147A1122022-06-0101 June 2022 NRC Initial Operator Licensing Examination Approval 05000298/2022301 ML22111A1382022-05-13013 May 2022 Proposed Inservice Testing Alternative RS-01, Revision 0 IR 05000298/20220012022-04-28028 April 2022 Integrated Inspection Report 05000298/2022001 IR 05000298/20224042022-04-13013 April 2022 Material Control and Accounting Program Inspection Report 05000298/2022404 - (Public) ML22084A6032022-04-0404 April 2022 Notification of NRC Evaluations of Changes, Tests and Experiments Inspection 05000298/2022002 and Request for Information ML22090A2892022-04-0101 April 2022 John Larson'S Invitation to Participate in the 8th Nuclear Regulatory Commission'S Workshop on Vendor Oversight ML22045A0012022-03-31031 March 2022 Proposed Inservice Inspection Alternative RI5- 02 Revision 3 IR 05000298/20210062022-03-0202 March 2022 Annual Assessment Letter for Cooper Nuclear Station (Report 05000298/2021006) IR 05000298/20210042022-01-24024 January 2022 Integrated Inspection Report 05000298/2021004 ML21350A0582021-12-21021 December 2021 Withdrawal of an Amendment Request ML21340A2362021-12-20020 December 2021 Issuance of Amendment No. 270 Adoption of Technical Specifications Task Force Traveler TSTF-582, Revision 0, RPV WIC Enhancements 2024-01-03
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000298/LER-2016-0012017-09-27027 September 2017 De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused by Relay Failure Results in Loss of Safety Function and a Condition Prohibited by Technical Specifications, LER 16-001-01 for Cooper Nuclear Station Regarding De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused by Relay Failure Results in Loss of Safety Function, a Condition Prohibited by Tech Specs, and a 10 CFR Part 21 Report 05000298/LER-2017-0042017-08-17017 August 2017 Torus to Drywell Vacuum Breaker Failure to Indicate Full Closed Causes Loss of Safety Function, LER 17-004-00 for Cooper Nuclear Station Regarding Torus to Drywall Vacuum Breaker Failure to Indicate Full Closed Causes Loss of Safety Function 05000298/LER-2017-0052017-08-17017 August 2017 Traversing In-core Probe In-shield Limit Switch Mounting Failure Results in Common Cause Inoperability of Independent Trains or Channels and Condition Prohibited by Technical Specifications, LER 17-005-00 for Cooper Nuclear Station Regarding Traversing In-core Probe In-shield Limit Switch Mounting Failure Results in Common Cause lnoperability of Independent Trains or Channels and Condition Prohibited by Technical Specifications 05000298/LER-2017-0032017-07-24024 July 2017 Mispositioned Control Room Emergency Filter System Supply Fan Damper Causes Loss of Safety Function, LER 17-003-00 for Cooper Nuclear Station re Mispositioned Control Room Emergency Filter System Supply Fan Damper Causes Loss of Safety Function 05000298/LER-2017-0022017-04-27027 April 2017 Valve Test Failures Result in Condition Prohibited by Technical Specifications and a Loss of Safety Function, LER 17-002-00 for Cooper Nuclear Station Regarding Valve Test Failures Result in Condition Prohibited by Technical Specifications and a Loss of Safety Function 05000298/LER-2017-0012017-04-0505 April 2017 Residual Heat Removal Minimum Flow Valves OUt of Position Results in Loss of Safety Function and Condition Prohibited by Technical Specifications, LER 17-001-00 for Cooper Regarding Residual Heat Removal Minimum Flow Valves Out of Position Results in Loss of Safety Function and Condition Prohibited by Technical Specifications 05000298/LER-2016-0082017-01-0505 January 2017 Purchase and Installation of Incorrect Actuator Results in a Condition Prohibited by Technical Specifications, LER 16-008-00 for Cooper Nuclear Station Regarding Purchase and Installation of Incorrect Actuator Results in a Condition Prohibited by Technical Specifications 05000298/LER-2016-0072016-12-19019 December 2016 Isolation of Shutdown Cooling due to Relay Maintenance Results in a Loss of Safety Function, LER 16-007-00 for Cooper Nuclear Station Regarding Isolation of Shutdown Cooling due to Relay Maintenance Results in a Loss of Safety Function 05000298/LER-2016-0062016-12-19019 December 2016 High Vibration on Control Room Emergency Filter System Fan Results in Inoperability and Loss of Safety Function, LER-16-006-00 for Cooper Nuclear Station Regarding High Vibration on Control Room Emergency Filter System Fan Results in Inoperability and Loss of Safety Function 05000298/LER-2016-0042016-11-22022 November 2016 Closure of Multiple Main Steam Isolation Valves due to High Flow Signal, LER 16-004-00 for Cooper Nuclear Station Regarding Closure of Multiple Main Steam Isolation Valves due to High Flow Signal 05000298/LER-2016-0032016-11-0909 November 2016 Scaffold Construction Places Plant in a Condition Prohibited by Technical Specifications, LER 16-003-00 for Cooper Nuclear Station RE: Scaffold Construction Places Plant in a Condition Prohibited by Technical Specifications 05000298/LER-2016-0022016-06-27027 June 2016 De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused By Light Bulb Failure Results in Loss of Safety Function, LER 16-002-00 for Cooper Regarding De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused By Light Bulb Failure Results in Loss of Safety Function NLS2015063, Retraction of Licensee Event Report 2014-005-00, Lube Oil Leak Results in a Potential Condition Prohibited by Technical Specifications and a Potential Loss of Safety Function.2015-06-0909 June 2015 Retraction of Licensee Event Report 2014-005-00, Lube Oil Leak Results in a Potential Condition Prohibited by Technical Specifications and a Potential Loss of Safety Function. ML13149A1722013-05-26026 May 2013 E-mail from Micheal Mulligan to R.Guzman, Pilgrim Evacuation Plan Broken During Blizzard Nemo and Unenforced by the Nrc. NLS2013015, Special Report, Offgas Treatment System Charcoal Adsorbers Out of Service2013-01-29029 January 2013 Special Report, Offgas Treatment System Charcoal Adsorbers Out of Service NLS2008058, LER 08-S01-00 for Cooper Regarding Temporary Suspension of Security Measures Due to Tornado Warning2008-08-0505 August 2008 LER 08-S01-00 for Cooper Regarding Temporary Suspension of Security Measures Due to Tornado Warning 2017-09-27
[Table view] |
Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Cooper Nuclear Station 05000- 298
3. LER NUMBER
- 004 2016 -00
PLANT STATUS
Cooper Nuclear Station was in Mode 3, Hot Shutdown, at approximately 330 psig, at the time the condition was identified.
BACKGROUND
The Main Steam system conducts steam from the reactor vessel, via four steam lines, through the Primary Containment to the Main Steam Turbine. Each steam line has two, normally open, Main Steam Isolation Valves (MSIVs) [EIIS:ISV], one inside and one outside the Primary Containment. The MSIVs close automatically upon receipt of certain isolation signals to prevent damage to the fuel cladding by limiting the loss of reactor water during a steam line break outside Primary Containment and also to limit the release of radioactive materials in case of a major leak from Primary Containment.
Main Steam Line (MSL) Flow-High is provided to detect a break of the MSL and to initiate closure of the MSIVs. If the steam were allowed to continue flowing out of the break, the reactor would depressurize and the core could uncover. If the Reactor Pressure Vessel (RPV) water level decreases too far, fuel damage could occur. Therefore, the isolation is initiated on high flow to prevent or minimize core damage. The MSL high flow trip setting was selected high enough to permit the isolation of one MSL for test at rated power without causing an automatic isolation of the rest of the steam lines yet low enough to permit early detection of a steam line break.
The MSL flow signals are initiated from 16 differential pressure switches [EIIS:PDIS] that are connected to the four MSLs. The differential pressure switches are arranged such that, even though physically separated from each other, all four connected to one MSL would be able to detect the high flow.
EVENT DESCRIPTION
On September 24, 2016, at 20:40 hours, during reactor cooldown for Refueling Outage 29, Operations closed the inboard MSIVs to minimize steam flow to control the reactor cooldown rate in accordance with the Normal Shutdown procedure. Reactor pressure was controlled using the main steam line drains.
The condensate/feed system was available for reactor water level control.
On September 25, 2016, at 01:03 hours, when Operations utilized the Main Steam procedure to equalize pressure across the MSIVs to below 200 psid, a differential pressure (DP) of approximately 190 psid was established. When MS-AO-80A was opened, a Group 1 Isolation was immediately received. All open MSIVs, as well as the MSL Drain Isolation Valves MS-MO-74 and MS-MO-77, closed. The Group 1 isolation was caused by a MSL high flow signal on MSL 'A' as the valve was opening. This was a valid signal based on a review of the steam flow indication for MSL 'A'.
Upon investigation it was discovered that the Differential Pressure Indicating Switches (DPIS) for the MSL 'A' high flow signal have a setpoint of 105.8 psid, with a calibration tolerance of +/- 3 psid. The DPIS' measure DP created by flow through the flow element upstream of the MSIV. Therefore, with static DP across the closed MSIVs, at approximately 190 psid prior to opening MS-AO-80A, it was possible that the DPIS' would exceed their setpoint as the MSIV opened and the DP was transferred to Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
3. LER NUMBER 2. DOCKET NUMBER 05000- 298 Cooper Nuclear Station - 004 -00 2016 the flow element in MSL 'A'. To ensure another Group 1 isolation would not occur, the MSIV DP would have to be below the lowest possible setpoint of the DPIS' (approximately 100 psid).
In order to provide margin below the setpoint for the Group 1 isolation, Operations determined that the DP across the MSIVs would be reduced to 75 psid prior to opening the MSIVs.
To increase the reactor cooldown rate and lower RPV pressure, Operations began to blow down using Reactor Water Cleanup to Radwaste. Reactor cooldown was also increased by starting Reactor Core Isolation Cooling in pressure control mode.
Operations isolated the steam supply to gland steam, High Pressure (HP) turbine cylinder heating, and the Reactor Feed Pump Turbine HP stop valve above the seat drains, bringing the main steam equalizing header pressure up to approximately 118 psig, and the DP across the MSIVs down'to approximately 65 psid. At 18:52 hours, MS-AO-80A was successfully opened and the remaining MSIVs were subsequently opened.
BASIS FOR REPORT
This condition is reportable in accordance with 10 CFR 50.73(a)(2)(iv)(A) as any event or condition that resulted in manual or automatic actuation of any of the systems listed in paragraph (a)(2)(iv)(B) of this section, except when (1) the actuation resulted from and was part of a pre-planned sequence during testing or reactor operation; or (2) the actuation was invalid and the system properly removed-from service or with the safety function already completed.
SAFETY SIGNIFICANCE
The occurrence of the Group 1 isolation signal did not compromise safety systems required to mitigate the consequences of an accident or transient. At the time of the event, the reactor vessel was at approximately 330 psig with all control rods previously inserted as part of the shutdown process. All high pressure and low pressure emergency core cooling systems were operable. The isolation signal was a main steam line high flow, however, no steam leak or break was observed. The plant response to the isolation was as expected. The safety significance of the event is low and did not pose a threat to the health and safety of the public.
CAUSE
The apparent cause was insufficient procedure guidance exists regarding limitations on opening the MSIVs.
CORRECTIVE ACTIONS
The applicable procedure has been revised to change the DP limitation for opening an MSIV from 200 psid to 80 psid.
Reported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by e-mail to Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
05000- 298 Cooper Nuclear Station
3. LER NUMBER
PREVIOUS EVENTS
There have been no automatic or manual system actuations in the past three years.
2016 - 004 -00
|
---|
|
|
| | Reporting criterion |
---|
05000298/LER-2016-001 | De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused by Relay Failure Results in Loss of Safety Function and a Condition Prohibited by Technical Specifications LER 16-001-01 for Cooper Nuclear Station Regarding De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused by Relay Failure Results in Loss of Safety Function, a Condition Prohibited by Tech Specs, and a 10 CFR Part 21 Report | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000298/LER-2016-002 | De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused By Light Bulb Failure Results in Loss of Safety Function LER 16-002-00 for Cooper Regarding De-Energized High Pressure Coolant Injection Auxiliary Lube Oil Pump Caused By Light Bulb Failure Results in Loss of Safety Function | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000298/LER-2016-003 | Scaffold Construction Places Plant in a Condition Prohibited by Technical Specifications LER 16-003-00 for Cooper Nuclear Station RE: Scaffold Construction Places Plant in a Condition Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000298/LER-2016-004 | Closure of Multiple Main Steam Isolation Valves due to High Flow Signal LER 16-004-00 for Cooper Nuclear Station Regarding Closure of Multiple Main Steam Isolation Valves due to High Flow Signal | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000298/LER-2016-005 | Implementation of Enforcement Guidance Memorandum 11-003, Revision 3, Causes Conditions Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000298/LER-2016-006 | High Vibration on Control Room Emergency Filter System Fan Results in Inoperability and Loss of Safety Function LER-16-006-00 for Cooper Nuclear Station Regarding High Vibration on Control Room Emergency Filter System Fan Results in Inoperability and Loss of Safety Function | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000298/LER-2016-007 | Isolation of Shutdown Cooling due to Relay Maintenance Results in a Loss of Safety Function LER 16-007-00 for Cooper Nuclear Station Regarding Isolation of Shutdown Cooling due to Relay Maintenance Results in a Loss of Safety Function | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000298/LER-2016-008 | Purchase and Installation of Incorrect Actuator Results in a Condition Prohibited by Technical Specifications LER 16-008-00 for Cooper Nuclear Station Regarding Purchase and Installation of Incorrect Actuator Results in a Condition Prohibited by Technical Specifications | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|