05000272/FIN-2016004-03
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Licensee-Identified Violation |
Description | The following PSEG-identified violation of NRC requirements was determined to be of very low safety significance (Green) and meet the NRC Enforcement Policy criteria for being dispositioned as an NCV. As a result of a Salem Post-Fire Safe Shutdown Analysis update, PSEG submitted LER 272/1999-009-00 when they identified that cables for pressurizer PORVs and associated block valves were routed in the same containment cable trays, a fire-induced spurious operation concern, that could result in a pathway for a loss of reactor coolant inventory and pressure control. A similar condition was also identified for a fire in the control or relay rooms that could affect alternate shutdown capability. The NRC dispositioned this issue in IR 05000272;311/1999-010. On August 26, 2015, PSEG identified that they had not adequately completed corrective actions associated with the relay rooms. Specifically, a fire scenario involving cables within cabinets existed that could result in spurious PORV operation while preventing the ability to manually close block valves. At the time of this discovery, the safe shutdown analysis did not include the evaluations required to credit closure of both PORVs and block valves in the main control room prior to evacuation. Local, manual closure of the block valves had been incorporated into procedures but could be delayed up to 40 minutes in the scenario while EDGs were restored. The loss of reactor coolant inventory and pressure control had not been accounted for during this timeframe. The issue was determined to be more than minor since it was associated with the protection against external factors (Fire) attribute of the Mitigating Systems cornerstone and adversely affected its objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The finding was evaluated in accordance with IMC 0609, Appendix A, Attachment 4, and Appendix F. The IMC 0609, Appendix F, Attachment 1, Step 1.6, permits screening of the issue with PSEG fire PRA results provided there is an approved fire PRA for the plant. PSEG provided a fire PRA evaluation for the degraded condition but since the PRA results were not from a finalized, approved fire PRA, additional evaluation was required. The Senior Reactor Analyst (SRA) conducted a detailed assessment of the issue using the External Initiator Risk Informed Inspection Notebook for Salem Generating Station (Revision 1). Fires of concern were determined to be those confined to the Unit 1 and Unit 2 Relay Rooms. This is modeled in table 3.3.13 of the notebook as Fire Group M. For evaluation, it was assumed that Spurious PORV Due to Hot Short had a probability of 1.0. For this model, this would indicate a condition in which a PORV and its associated block valve were open. Given the exposure period of greater than 30 days, this would result in a change in core damage frequency of approximately 1E-8, Green, for Unit 1 and Unit 2. The notebook was conservative since the evaluation assumed the failure of the PORV to close as opposed to the more realistic probability that fire would cause a spurious failure of a PORV and hot short resulting in failure of the block valve. The dominant sequences included: 1) Fire in the relay room with a failure of the PORV to close and a failure of high pressure injection and 2) Fire in the relay room with a failure of the PORV to close and a failure of high pressure recirculation. PSEGs results were consistent with the SRAs analysis. Title 10 CFR Part 50, Appendix B, Criterion XVI, requires, in part, that conditions adverse to quality are promptly identified and corrected. Salem Unit 1 and 2 license conditions 2.(C).5 and 2.(C).10 respectively require, in part, that PSEG shall implement and maintain all provisions of the fire protection program. PSEGs Quality Assurance Topical Report states that the Quality Assurance Program is applied to the Fire Protection Program consistent with Branch Technical Position APCSB 9.5-1 Appendix A, Section C requirements that include, under Corrective Action, that conditions adverse to fire protection are promptly identified, reported, and corrected. Contrary to this, from about 1999 to August 2015, actions from a previous, related fire-induced circuit failure scenario did not completely correct the condition resulting in the inability to credit manual closure of PORV and PORV block valves in an associated fire scenario. PSEG entered this in their CAP as NOTFs 20700943 and 20750010. |
Site: | Salem |
---|---|
Report | IR 05000272/2016004 Section 4OA7 |
Date counted | Dec 31, 2016 (2016Q4) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | Licensee-identified |
Inspection Procedure: | |
Inspectors (proximate) | A Ziedonis F Bower J Deboer J Hawkins J Kulp P Finney P Ott |
Violation of: | 10 CFR 50 Appendix B Criterion XVI |
INPO aspect | |
' | |
Finding - Salem - IR 05000272/2016004 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Salem) @ 2016Q4
Self-Identified List (Salem)
| ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||